VAIBHAV
by GAVDEVI SHELTER · Survodaya Nagar, Thane
Possession date of VAIBHAV: 30 June 2025, moved from 30 December 2022 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700023656. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about VAIBHAV?
How the possession date of VAIBHAV has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT51700013264)
Reason the builder gave MahaRERA: “Such as Weather, Equipment failures, and Labour shortages.”
30 December 2024
Extended at the builder's request (MahaRERA application EXT51700018234)
Reason the builder gave MahaRERA: “LIFT SANCTION WORK PENDING.”
30 June 2025
Extended at the builder's request (MahaRERA application EXT51700027541)
Reason the builder gave MahaRERA: “FINANCE RELATED ISSUE”
Source: VAIBHAV’s extension records on MahaRERA (P51700023656), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VAIBHAV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700023656
- Status
- Lapsed (registration period ended)
- Builder
- GAVDEVI SHELTER
- Location
- Survodaya Nagar, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 24 Dec 2019
- Completion date at registration
- December 2022
- Latest completion date
- June 2025
- Delay so far
- 30 months
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VAIBHAV, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VAIBHAV | 100% | 6% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VAIBHAV every month.
VAIBHAV: buildings, flats and land, as filed on MahaRERA
- Buildings: VAIBHAV (5 floors)
- Land: 739 sq m (about 0.2 acres) · sanctioned built-up 1,254 sq m
The builder’s record and reviews
Gavdevi Shelter (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of VAIBHAV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VAIBHAV: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VAIBHAV
What is the possession date of VAIBHAV?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VAIBHAV in Survodaya Nagar, Thane is 30 June 2025 — 30 months later than 30 December 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for VAIBHAV?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VAIBHAV's builder has filed on MahaRERA, the official one, is 30 June 2025, already 30 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VAIBHAV extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2023, giving the reason "Such as Weather, Equipment failures, and Labour shortages."; to 30 December 2024, giving the reason "LIFT SANCTION WORK PENDING."; to 30 June 2025, giving the reason "FINANCE RELATED ISSUE".
What is the RERA number of VAIBHAV?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VAIBHAV in Survodaya Nagar, Thane is P51700023656.
Is VAIBHAV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV is registered as P51700023656 and its status is "Lapsed (registration period ended)".
What is the construction status of VAIBHAV?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VAIBHAV is 6% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does VAIBHAV have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VAIBHAV safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV is registered on MahaRERA as P51700023656, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VAIBHAV's possession date changes?
The latest dates are on VAIBHAV's MahaRERA page (P51700023656). GharKundli's Kundli Watch sends a free WhatsApp update on VAIBHAV every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VAIBHAV have?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV has one building filed: VAIBHAV with 5 floors.
How big is the land of VAIBHAV?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV stands on 739 sq m of land (about 0.2 acres), with 1,254 sq m of sanctioned built-up area.
What is the track record of VAIBHAV's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gavdevi Shelter (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VAIBHAV?
Google Maps has reviews of VAIBHAV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VAIBHAV?
VAIBHAV by GAVDEVI SHELTER is in Survodaya Nagar, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700023656, per GharKundli's check of MahaRERA records.
When was VAIBHAV registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV was registered on MahaRERA on 24 December 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on VAIBHAV?
No court cases are listed for VAIBHAV on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VAIBHAV?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GAVDEVI SHELTER.
Check it yourself on MahaRERA
- How to check the possession date of VAIBHAV
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ambarnath
- Nature Vista Building - 1
- MIDTOWN B AND C WING
- MERY VILLA CHSL
- SAI UNIVERSE
- DATTATRAY RESIDENCY
- MAHADEV HEIGHTS
- CHADHA RESIDENCY
- NEW NEELGAGAN CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.