Shree Empire
by SHREE GURUKRUPA DEVELOPERS · Dombivli East, Thane 421201Also near Vishnunagar, Manpada
What’s in the report? →Possession date of Shree Empire (MahaRERA P51700024947): 30 April 2028, moved from 30 December 2022 (60 months later). It has 43 homes, 60% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700024947, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700024947, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shree Empire?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shree Empire has moved
30 December 2022
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700018700)
Reason the builder gave MahaRERA: “Reason for Delay, due to price escalation and a bit shortage of funds and labour”
31 December 2027
Extended at the builder's request (MahaRERA application EA25092517945)
Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shree Empire’s extension records on MahaRERA (P51700024947), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Empire
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700024947
- Status
- Registered and active
- Builder
- SHREE GURUKRUPA DEVELOPERS
- Location
- Dombivli East, Thane · 421201
- Project type
- Mixed
- Registered on
- 12 Mar 2020
- Completion date at registration
- December 2022
- Latest completion date
- April 2028
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 43
- Sold or booked
- 60%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Shree Empire, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE EMPIRE A WING | 100% | 100% | 80% | 80% |
| SHREE EMPIRE B WING | 100% | 100% | 100% | 85% |
Commencement certificate (CC), as filed on MahaRERA
- SHREE EMPIRE A WING: covers 6 floors
- SHREE EMPIRE B WING: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Empire every 1–2 months.
Shree Empire: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE EMPIRE A WING (14 floors, 25 units) · SHREE EMPIRE B WING (14 floors, 45 units)
- Land: 2,900 sq m (about 0.7 acres) · sanctioned built-up 1,932 sq m
- Boundaries filed include: Dawadi Road
- Land, as filed: New Survey No 84/4C, Old Survey No 119/4C
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Empire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Empire: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shree Empire
What is the possession date of Shree Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Empire in Dombivli East, Thane is 30 April 2028 — 60 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 60 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shree Empire?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Empire's builder has filed on MahaRERA, the official one, is 30 April 2028, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Empire extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "Reason for Delay, due to price escalation and a bit shortage of funds and labour"; to 31 December 2027, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shree Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Empire in Dombivli East, Thane is P51700024947.
Is Shree Empire registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire is registered as P51700024947 and its status is "Registered and active".
What is the current construction status of Shree Empire? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Shree Empire have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shree Empire safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire is registered on MahaRERA as P51700024947, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shree Empire?
Shree Empire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shree Empire?
For a flat in Shree Empire (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shree Empire received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shree Empire uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Empire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shree Empire's possession date changes?
The latest dates are on Shree Empire's MahaRERA page (P51700024947). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Empire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Empire have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire has 2 buildings filed: SHREE EMPIRE A WING with 14 floors and 25 units; SHREE EMPIRE B WING with 14 floors and 45 units.
How big is the land of Shree Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire stands on 2,900 sq m of land (about 0.7 acres), with 1,932 sq m of sanctioned built-up area.
What are the reviews of Shree Empire?
Google Maps has reviews of Shree Empire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shree Empire?
Shree Empire by SHREE GURUKRUPA DEVELOPERS is in Dombivli East, Thane, pincode 421201 (near Vishnunagar, Manpada), Maharashtra, and is registered on MahaRERA as P51700024947, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dawadi Road. Its land is filed as New Survey No 84/4C, Old Survey No 119/4C. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Shree Empire, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire has 43 homes in 2 towers registered on MahaRERA, and 60% of them are sold or booked.
When was Shree Empire registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Empire was registered on MahaRERA on 12 March 2020. GharKundli did not find a title report on the land on file there.
Does Shree Empire have any legal issues or court cases?
No court cases are listed for Shree Empire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shree Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE GURUKRUPA DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shree Empire
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Tilaknagar (421201)
- Swami Elite
- Mangeshi Dazzle II
- Sagar Kunj Highland
- Om Trimurti Darshan
- Balaji Govind
- Vastu Heritage
- Mangeshi Dhara
- Nav Samidha Co-op HSG Soc LTD
Other projects by SHREE GURUKRUPA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.