by ASHAPURA CORPORATION · Dombivli, Thane 421201Also near Ramnagar, Village- G.B Patharli, Ram NagarRegistered on MahaRERA as “ARYA ARIANA”

What’s in the report? →

Possession date of Ashapura Arya Ariana (MahaRERA P51700025165): 30 January 2027, moved from 30 March 2024 (30 months later). It has 2 homes, 61% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700025165, and currently active. Its completion date has moved from March 2024 to January 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700025165, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ashapura Arya Ariana?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ashapura Arya Ariana has moved

  1. 30 March 2024

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA25052621092)

    Reason the builder gave MahaRERA: “CORONA AND SHIRTAGE OF LABOIUR PAPER WORK”
  3. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ashapura Arya Ariana’s extension records on MahaRERA (P51700025165), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ashapura Arya Ariana

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700025165
Status
Registered and active
Builder
ASHAPURA CORPORATION
Location
Dombivli, Thane · 421201
Project type
Others
Registered on
20 Mar 2020
Completion date at registration
March 2024
Latest completion date
January 2027
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
2
Sold or booked
61%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Ashapura Arya Ariana, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ARYA ARIANA90%100%90%80%

Commencement certificate (CC), as filed on MahaRERA

  • ARYA ARIANA: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ashapura Arya Ariana every 1–2 months.

Ashapura Arya Ariana: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Ashapura Arya Ariana →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ashapura Arya Ariana: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ashapura Arya Ariana

What is the possession date of Ashapura Arya Ariana?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ashapura Arya Ariana in Dombivli, Thane is 30 January 2027 — 30 months later than 30 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 30 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ashapura Arya Ariana?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ashapura Arya Ariana's builder has filed on MahaRERA, the official one, is 30 January 2027, already 30 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ashapura Arya Ariana extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "CORONA AND SHIRTAGE OF LABOIUR PAPER WORK". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ashapura Arya Ariana?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ashapura Arya Ariana in Dombivli, Thane is P51700025165.

Is Ashapura Arya Ariana registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana is registered as P51700025165 and its status is "Registered and active".

What is the current construction status of Ashapura Arya Ariana? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ARYA ARIANA is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Ashapura Arya Ariana have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ashapura Arya Ariana safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana is registered on MahaRERA as P51700025165, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ashapura Arya Ariana?

Ashapura Arya Ariana is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ashapura Arya Ariana?

For a flat in Ashapura Arya Ariana (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ashapura Arya Ariana received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Ashapura Arya Ariana uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ashapura Arya Ariana was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ashapura Arya Ariana's possession date changes?

The latest dates are on Ashapura Arya Ariana's MahaRERA page (P51700025165). GharKundli's Kundli Watch sends a free WhatsApp update on Ashapura Arya Ariana every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ashapura Arya Ariana have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana has one building filed: ARYA ARIANA with 9 floors and 51 units.

How big is the land of Ashapura Arya Ariana?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana stands on 786 sq m of land (about 0.2 acres), with 1,639 sq m of sanctioned built-up area.

What are the reviews of Ashapura Arya Ariana?

Google Maps has reviews of Ashapura Arya Ariana written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ashapura Arya Ariana?

Ashapura Arya Ariana by ASHAPURA CORPORATION is in Dombivli, Thane, pincode 421201 (near Ramnagar, Village- G.B Patharli, Ram Nagar), Maharashtra, and is registered on MahaRERA as P51700025165, per GharKundli's check of MahaRERA records. Its boundaries filed there include NARAYAN RAO PATKAR ROAD. Its land is filed as 5664/A. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Ashapura Arya Ariana, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana has 2 homes in 1 tower registered on MahaRERA, and 61% of them are sold or booked.

When was Ashapura Arya Ariana registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Arya Ariana was registered on MahaRERA on 20 March 2020. GharKundli did not find a title report on the land on file there.

Does Ashapura Arya Ariana have any legal issues or court cases?

No court cases are listed for Ashapura Arya Ariana on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Ashapura Arya Ariana?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASHAPURA CORPORATION.

All projects with possession due in 2027 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.