Aadinath Nagar Phase - II

by Arihant Vastu Nirman Pvt. Ltd · Main Road, Near Megh Malhar Hotel, Ratnagiri 415639

What’s in the report? →

Possession date of Aadinath Nagar Phase - II (MahaRERA P52800020423): 30 April 2027. It has 138 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800020423, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P52800020423, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aadinath Nagar Phase - II?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aadinath Nagar Phase - II has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Aadinath Nagar Phase - II’s extension records on MahaRERA (P52800020423), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aadinath Nagar Phase - II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52800020423
Status
Registered and active
Builder
Arihant Vastu Nirman Pvt. Ltd
Location
Main Road, Near Megh Malhar Hotel, Ratnagiri · 415639
Project type
Residential / Group Housing
Registered on
9 Apr 2019
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
138
Towers
5
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
12

Construction progress of Aadinath Nagar Phase - II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
E WING0%0%0%0%
F WING0%0%0%0%
G WING0%0%0%0%
H WING0%0%0%0%
I WING0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aadinath Nagar Phase - II every 1–2 months.

Aadinath Nagar Phase - II: buildings, flats and land, as filed on MahaRERA

  • Buildings: E WING (6 floors) · F WING (6 floors) · G WING (6 floors) · H WING (6 floors) · I WING (6 floors)
  • Land: 11,300 sq m (about 2.8 acres) · sanctioned built-up 12,198 sq m · recreational space 670 sq m
  • Land, as filed: Hissa No 2/3A and Survey No 397
  • Map: Get directions

The builder’s record and reviews

Arihant Vastu Nirman (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 6 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Aadinath Nagar Phase - II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aadinath Nagar Phase - II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aadinath Nagar Phase - II

What is the possession date of Aadinath Nagar Phase - II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aadinath Nagar Phase - II in Main Road, Near Megh Malhar Hotel, Ratnagiri is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Aadinath Nagar Phase - II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aadinath Nagar Phase - II's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aadinath Nagar Phase - II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aadinath Nagar Phase - II in Main Road, Near Megh Malhar Hotel, Ratnagiri is P52800020423.

Is Aadinath Nagar Phase - II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II is registered as P52800020423 and its status is "Registered and active".

What is the current construction status of Aadinath Nagar Phase - II? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Aadinath Nagar Phase - II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aadinath Nagar Phase - II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II is registered on MahaRERA as P52800020423, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aadinath Nagar Phase - II?

Aadinath Nagar Phase - II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aadinath Nagar Phase - II?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aadinath Nagar Phase - II: gharkundli.com/tools/property-cost-calculator

Has Aadinath Nagar Phase - II received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aadinath Nagar Phase - II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aadinath Nagar Phase - II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Aadinath Nagar Phase - II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Aadinath Nagar Phase - I (P52800000156, possession 1 Apr 2021). Check that your agreement names the registration of your own wing.

How can I get updates if Aadinath Nagar Phase - II's possession date changes?

The latest dates are on Aadinath Nagar Phase - II's MahaRERA page (P52800020423). GharKundli's Kundli Watch sends a free WhatsApp update on Aadinath Nagar Phase - II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aadinath Nagar Phase - II have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II has 5 buildings filed: E WING with 6 floors; F WING with 6 floors; G WING with 6 floors; H WING with 6 floors; I WING with 6 floors.

How big is the land of Aadinath Nagar Phase - II?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II stands on 11,300 sq m of land (about 2.8 acres), with 12,198 sq m of sanctioned built-up area and 670 sq m of recreational open space.

What is the track record of Aadinath Nagar Phase - II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Arihant Vastu Nirman (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 6 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aadinath Nagar Phase - II?

Google Maps has reviews of Aadinath Nagar Phase - II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aadinath Nagar Phase - II?

Aadinath Nagar Phase - II by Arihant Vastu Nirman Pvt. Ltd is in Main Road, Near Megh Malhar Hotel, Ratnagiri, pincode 415639, Maharashtra, and is registered on MahaRERA as P52800020423, per GharKundli's check of MahaRERA records. Its land is filed as Hissa No 2/3A and Survey No 397. GharKundli lists all 150 MahaRERA projects in RTG (415639).

How many flats are in Aadinath Nagar Phase - II?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II has 138 homes in 5 towers registered on MahaRERA.

When was Aadinath Nagar Phase - II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aadinath Nagar Phase - II was registered on MahaRERA on 9 April 2019. GharKundli did not find a title report on the land on file there.

Does Aadinath Nagar Phase - II have any legal issues or court cases?

No court cases are listed for Aadinath Nagar Phase - II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Aadinath Nagar Phase - II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Arihant Vastu Nirman Pvt. Ltd, which has 12 other projects registered on MahaRERA.

All projects with possession due in 2027 in Ratnagiri →