by M/s Tirupati Developers · Dombivli East, Thane 421201Also near Kalyan, Chikanghar, ParnakaRegistered on MahaRERA as “BALAJI HEIGHTS”

What’s in the report? →

Possession date of Tirupati Balaji Heights (MahaRERA P51700027019): 30 June 2026, moved from 30 June 2025 (12 months later), and it has already passed. It has 41 homes, 97% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700027019. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700027019, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Tirupati Balaji Heights?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Tirupati Balaji Heights has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA03112518227)

    Reason the builder gave MahaRERA:
    “Please accept our apologies for the delay in project completion and in submitting this extension request. The delay was primarily due to the unexpected and unavoidable effects of the COVID-19 pandemic, which caused labour shortages and disr…” Read the full reason“Please accept our apologies for the delay in project completion and in submitting this extension request. The delay was primarily due to the unexpected and unavoidable effects of the COVID-19 pandemic, which caused labour shortages and disrupted supply chains, thereby impacting our ability to meet the original deadline. We continue to work diligently to resolve the remaining issues and are fully committed to completing the project at the earliest opportunity. In view of these circumstances, we request your approval to extend the project timeline until 30th June 2026, to allow us to comply w…”

Source: Tirupati Balaji Heights’s extension records on MahaRERA (P51700027019), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tirupati Balaji Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700027019
Status
Lapsed (registration period ended)
Builder
M/s Tirupati Developers
Location
Dombivli East, Thane · 421201
Project type
Residential / Group Housing
Registered on
10 Nov 2020
Completion date at registration
June 2025
Latest completion date
June 2026
Delay so far
12 months
Homes
41
Sold or booked
97%
Towers
1
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found

Construction progress of Tirupati Balaji Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Balaji Heights100%100%100%80%

Commencement certificate (CC), as filed on MahaRERA

  • Balaji Heights: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tirupati Balaji Heights every 1–2 months.

Tirupati Balaji Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Balaji Heights (16 floors, 75 units)
  • Land: 1,604 sq m (about 0.4 acres) · sanctioned built-up 1,585 sq m
  • Boundaries filed include: CHITTARANJAN DAS ROAD, ROAD AND OPP BODAS HALL
  • Land, as filed: CTS NO 7982 TO7993
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Tirupati Balaji Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tirupati Balaji Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Tirupati Balaji Heights

What is the possession date of Tirupati Balaji Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tirupati Balaji Heights in Dombivli East, Thane is 30 June 2026 — 12 months later than 30 June 2025, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Tirupati Balaji Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tirupati Balaji Heights's builder has filed on MahaRERA, the official one, is 30 June 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Tirupati Balaji Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Please accept our apologies for the delay in project completion and in submitting this extension request. The delay was primarily due to the unexpected and unavoidable effects of the COVID-19 pandemic, which caused labour shortages and disrupted supply chains, thereby impacting our ability to meet the original deadline. We continue to work diligently to resolve the remaining issues and are fully committed to completing the project at the earliest opportunity. In view of these circumstances, we request your approval to extend the project timeline until 30th June 2026, to allow us to comply w…".

What is the RERA number of Tirupati Balaji Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tirupati Balaji Heights in Dombivli East, Thane is P51700027019.

Is Tirupati Balaji Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights is registered as P51700027019 and its status is "Lapsed (registration period ended)".

What is the current construction status of Tirupati Balaji Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Balaji Heights is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Tirupati Balaji Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Tirupati Balaji Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights is registered on MahaRERA as P51700027019, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Tirupati Balaji Heights?

Tirupati Balaji Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Tirupati Balaji Heights?

For a flat in Tirupati Balaji Heights (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Tirupati Balaji Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Tirupati Balaji Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Tirupati Balaji Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tirupati Balaji Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Tirupati Balaji Heights's possession date changes?

The latest dates are on Tirupati Balaji Heights's MahaRERA page (P51700027019). GharKundli's Kundli Watch sends a free WhatsApp update on Tirupati Balaji Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tirupati Balaji Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights has one building filed: Balaji Heights with 16 floors and 75 units.

How big is the land of Tirupati Balaji Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights stands on 1,604 sq m of land (about 0.4 acres), with 1,585 sq m of sanctioned built-up area.

What are the reviews of Tirupati Balaji Heights?

Google Maps has reviews of Tirupati Balaji Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Tirupati Balaji Heights?

Tirupati Balaji Heights by M/s Tirupati Developers is in Dombivli East, Thane, pincode 421201 (near Kalyan, Chikanghar, Parnaka), Maharashtra, and is registered on MahaRERA as P51700027019, per GharKundli's check of MahaRERA records. Its boundaries filed there include CHITTARANJAN DAS ROAD, ROAD AND OPP BODAS HALL. Its land is filed as CTS NO 7982 TO7993. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Tirupati Balaji Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights has 41 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.

When was Tirupati Balaji Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Balaji Heights was registered on MahaRERA on 10 November 2020. GharKundli did not find a title report on the land on file there.

Does Tirupati Balaji Heights have any legal issues or court cases?

2 court cases are listed for Tirupati Balaji Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Tirupati Balaji Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s Tirupati Developers.

All projects with possession due in 2026 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.