Skip to content
GharKundli

New Shiv-shakti CHS

by SHREE LAXMI DEVELOPERS · Shiv Ganga, Thane 421501

What’s in the report? →

Possession date of New Shiv-shakti CHS (MahaRERA P51700025478): 31 December 2025, moved from 30 March 2023 (33 months later), and it has already passed. It has 25 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700025478. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700025478, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about New Shiv-shakti CHS?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of New Shiv-shakti CHS has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 29 March 2024

    Extended at the builder's request (MahaRERA application EXT51700015179)

    Reason the builder gave MahaRERA: “Due to revision of plan of the project. Plan copy attached for reference”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700025400)

    Reason the builder gave MahaRERA: “Completion Certificate applied but not received hence extension required for flat registration”

Source: New Shiv-shakti CHS’s extension records on MahaRERA (P51700025478), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on New Shiv-shakti CHS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700025478
Status
Lapsed (registration period ended)
Builder
SHREE LAXMI DEVELOPERS
Location
Shiv Ganga, Thane · 421501
Project type
Others
Registered on
6 Jun 2020
Completion date at registration
March 2023
Latest completion date
December 2025
Delay so far
33 months
Homes
25
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of New Shiv-shakti CHS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
New Shiv Shakti CHS100%100%100%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Shiv-shakti CHS every 1–2 months.

New Shiv-shakti CHS: buildings, flats and land, as filed on MahaRERA

  • Buildings: New Shiv Shakti CHS (7 floors)
  • Land: 450 sq m (about 0.1 acres) · sanctioned built-up 601 sq m
  • Land, as filed: PLOT 83 S NO 70
  • Map: Get directions

The builder’s record and reviews

Heramb Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 lapsed. No complaints on MahaRERA.

Read Google reviews of New Shiv-shakti CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

New Shiv-shakti CHS: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about New Shiv-shakti CHS

What is the possession date of New Shiv-shakti CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Shiv-shakti CHS in Shiv Ganga, Thane is 31 December 2025 — 33 months later than 30 March 2023, the date given at registration. That date has already passed.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for New Shiv-shakti CHS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date New Shiv-shakti CHS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 33 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of New Shiv-shakti CHS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS's builder applied to MahaRERA to extend the completion date 2 times: to 29 March 2024, giving the reason "Due to revision of plan of the project. Plan copy attached for reference"; to 31 December 2025, giving the reason "Completion Certificate applied but not received hence extension required for flat registration".

What is the RERA number of New Shiv-shakti CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Shiv-shakti CHS in Shiv Ganga, Thane is P51700025478.

Is New Shiv-shakti CHS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS is registered as P51700025478 and its status is "Lapsed (registration period ended)".

What is the current construction status of New Shiv-shakti CHS? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on New Shiv Shakti CHS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does New Shiv-shakti CHS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is New Shiv-shakti CHS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS is registered on MahaRERA as P51700025478, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in New Shiv-shakti CHS?

New Shiv-shakti CHS isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in New Shiv-shakti CHS?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in New Shiv-shakti CHS: gharkundli.com/tools/property-cost-calculator

Has New Shiv-shakti CHS received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for New Shiv-shakti CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has New Shiv-shakti CHS uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for New Shiv-shakti CHS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if New Shiv-shakti CHS's possession date changes?

The latest dates are on New Shiv-shakti CHS's MahaRERA page (P51700025478). GharKundli's Kundli Watch sends a free WhatsApp update on New Shiv-shakti CHS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does New Shiv-shakti CHS have?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS has one building filed: New Shiv Shakti CHS with 7 floors.

How big is the land of New Shiv-shakti CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS stands on 450 sq m of land (about 0.1 acres), with 601 sq m of sanctioned built-up area.

What is the track record of New Shiv-shakti CHS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Heramb Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of New Shiv-shakti CHS?

Google Maps has reviews of New Shiv-shakti CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of New Shiv-shakti CHS?

New Shiv-shakti CHS by SHREE LAXMI DEVELOPERS is in Shiv Ganga, Thane, pincode 421501, Maharashtra, and is registered on MahaRERA as P51700025478, per GharKundli's check of MahaRERA records. Its land is filed as PLOT 83 S NO 70. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).

How many flats are in New Shiv-shakti CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS has 25 homes in 1 tower registered on MahaRERA.

When was New Shiv-shakti CHS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Shiv-shakti CHS was registered on MahaRERA on 6 June 2020. GharKundli did not find a title report on the land on file there.

Does New Shiv-shakti CHS have any legal issues or court cases?

No court cases are listed for New Shiv-shakti CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of New Shiv-shakti CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE LAXMI DEVELOPERS, which has 2 other projects registered on MahaRERA.

Other projects in Ambarnath

All 486 projects in Ambernath (421501) →

Other projects by SHREE LAXMI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.