Sheela Shilp Serenity
by SHEELA SHILPAKAR LLP · Bhawani Shankar, Mumbai 400028Also near Dadar West, Shivaji Park, Mahim WestRegistered on MahaRERA as “Shilp Serenity”
What’s in the report? →Possession date of Sheela Shilp Serenity (MahaRERA P51900056028): 30 April 2028. It has 34 homes (1 BHK, 2 BHK and 3 BHK, 418–1431 sq ft carpet), 29% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900056028, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51900056028, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sheela Shilp Serenity?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sheela Shilp Serenity has moved
30 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sheela Shilp Serenity’s extension records on MahaRERA (P51900056028), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sheela Shilp Serenity
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900056028
- Status
- Registered and active
- Builder
- SHEELA SHILPAKAR LLP
- Location
- Bhawani Shankar, Mumbai · 400028
- Project type
- Residential / Group Housing
- Registered on
- 6 May 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 34
- Sold or booked
- 29%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sheela Shilp Serenity, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHILP SERENITY - COMBINED REDEVELOPMENT OF PAN CHS AND JAI JEEVAN CHS | 100% | 17% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHILP SERENITY - COMBINED REDEVELOPMENT OF PAN CHS AND JAI JEEVAN CHS: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sheela Shilp Serenity every 1–2 months.
Sheela Shilp Serenity: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 418 – 504 | 13 |
| 3 BHK | 959 – 1,431 | 12 |
| 2 BHK | 549 – 851 | 9 |
- Buildings: SHILP SERENITY - COMBINED REDEVELOPMENT OF PAN CHS AND JAI JEEVAN CHS (16 floors, 34 units)
- Land: 744 sq m (about 0.2 acres) · sanctioned built-up 2,617 sq m
- Boundaries filed include: DR VASANT RATH ROAD, SHANKARRAO H PARELKAR MARG
- Land, as filed: 657
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sheela Shilp Serenity →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sheela Shilp Serenity: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sheela Shilp Serenity
What is the possession date of Sheela Shilp Serenity?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sheela Shilp Serenity in Bhawani Shankar, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sheela Shilp Serenity?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sheela Shilp Serenity's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sheela Shilp Serenity?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sheela Shilp Serenity in Bhawani Shankar, Mumbai is P51900056028.
Is Sheela Shilp Serenity registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity is registered as P51900056028 and its status is "Registered and active".
What is the current construction status of Sheela Shilp Serenity? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHILP SERENITY - COMBINED REDEVELOPMENT OF PAN CHS AND JAI JEEVAN CHS is 17% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Sheela Shilp Serenity have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sheela Shilp Serenity safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity is registered on MahaRERA as P51900056028, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sheela Shilp Serenity?
Sheela Shilp Serenity is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sheela Shilp Serenity are 418 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sheela Shilp Serenity?
For a flat in Sheela Shilp Serenity (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sheela Shilp Serenity received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Sheela Shilp Serenity a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Sheela Shilp Serenity uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sheela Shilp Serenity was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sheela Shilp Serenity's possession date changes?
The latest dates are on Sheela Shilp Serenity's MahaRERA page (P51900056028). GharKundli's Kundli Watch sends a free WhatsApp update on Sheela Shilp Serenity every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sheela Shilp Serenity have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity has one building filed: SHILP SERENITY - COMBINED REDEVELOPMENT OF PAN CHS AND JAI JEEVAN CHS with 16 floors and 34 units.
What are the flat sizes (carpet area) in Sheela Shilp Serenity?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sheela Shilp Serenity: 1 BHK: 418 to 504 sq ft carpet (13 homes); 3 BHK: 959 to 1431 sq ft carpet (12 homes); 2 BHK: 549 to 851 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Sheela Shilp Serenity?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity stands on 744 sq m of land (about 0.2 acres), with 2,617 sq m of sanctioned built-up area.
What are the reviews of Sheela Shilp Serenity?
Google Maps has reviews of Sheela Shilp Serenity written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sheela Shilp Serenity?
Sheela Shilp Serenity by SHEELA SHILPAKAR LLP is in Bhawani Shankar, Mumbai, pincode 400028 (near Dadar West, Shivaji Park, Mahim West), Maharashtra, and is registered on MahaRERA as P51900056028, per GharKundli's check of MahaRERA records. Its boundaries filed there include DR VASANT RATH ROAD, SHANKARRAO H PARELKAR MARG. Its land is filed as 657. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).
How many flats are in Sheela Shilp Serenity, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity has 34 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.
When was Sheela Shilp Serenity registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheela Shilp Serenity was registered on MahaRERA on 6 May 2024. GharKundli did not find a title report on the land on file there.
Does Sheela Shilp Serenity have any legal issues or court cases?
No court cases are listed for Sheela Shilp Serenity on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sheela Shilp Serenity?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHEELA SHILPAKAR LLP.
Check it yourself on MahaRERA
- How to check the possession date of Sheela Shilp Serenity
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data