Govind Sadan

by Sugee Developers Pvt Ltd · Shivaji Park, MumbaiAlso near Dadar West, Mahim West, Mari Nagar Mahim

Possession: Govind Sadan is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900000834. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Govind Sadan?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Govind Sadan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900000834
Status
Completed
Builder
Sugee Developers Pvt Ltd
Location
Shivaji Park, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
23 Jul 2017
Completion date at registration
December 2020
Latest completion date
December 2020
Homes
6
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Govind Sadan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Govind Sadan100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Govind Sadan every month.

Govind Sadan: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sugee Developers (a group of 14 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 9 months); 11 still being built, none past the promised date yet; 4 lapsed. 5 complaints on MahaRERA across 4 projects.

Read Google reviews of Govind Sadan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Govind Sadan: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Govind Sadan

What is the possession date of Govind Sadan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Govind Sadan in Shivaji Park, Mumbai is 30 December 2020.

Is the builder's possession date different from the MahaRERA date for Govind Sadan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Govind Sadan's builder has filed on MahaRERA, the official one, is 30 December 2020, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Govind Sadan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Govind Sadan in Shivaji Park, Mumbai is P51900000834.

Is Govind Sadan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan is registered as P51900000834 and its status is "Completed".

What is the construction status of Govind Sadan?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan's status on MahaRERA is "Completed". As filed by the builder, slab work on Govind Sadan is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Govind Sadan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Govind Sadan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan is registered on MahaRERA as P51900000834, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Govind Sadan's possession date changes?

The latest dates are on Govind Sadan's MahaRERA page (P51900000834). GharKundli's Kundli Watch sends a free WhatsApp update on Govind Sadan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Govind Sadan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan has one building filed: Govind Sadan with 19 floors.

How big is the land of Govind Sadan?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan stands on 430 sq m of land (about 0.1 acres), with 1,486 sq m of sanctioned built-up area.

What is the track record of Govind Sadan's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sugee Developers (a group of 14 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 9 months); 11 still being built, none past the promised date yet; 4 lapsed. 5 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Govind Sadan?

Google Maps has reviews of Govind Sadan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Govind Sadan?

Govind Sadan by Sugee Developers Pvt Ltd is in Shivaji Park, Mumbai (pincode 400028), near Dadar West, Mahim West, Mari Nagar Mahim, Maharashtra, and is registered on MahaRERA as P51900000834, per GharKundli's check of MahaRERA records.

How many homes are in Govind Sadan?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan has 6 homes in 1 tower registered on MahaRERA.

When was Govind Sadan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Govind Sadan was registered on MahaRERA on 23 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Govind Sadan?

No court cases are listed for Govind Sadan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Govind Sadan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sugee Developers Pvt Ltd, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400028

All 148 projects in Dadar West (400028) →

Other projects by Sugee Developers Pvt Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.