Kartik Homes
by KARTIK ENTERPRISES · Shirgaon Badlapur East, Thane 421503
What’s in the report? →Possession date of Kartik Homes (MahaRERA P51700029229): 30 April 2027, moved from 31 December 2024 (24 months later). It has 84 homes, 33% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700029229, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700029229, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kartik Homes?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kartik Homes has moved
31 December 2024
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700025511)
Reason the builder gave MahaRERA:
“Due to Unexpected economic downturns, financial crises, and credit crunches we have not received the minimum expected bookings which have made it difficult for Us (developers) to access funding or secure necessary investments to complete th…” Read the full reason
“Due to Unexpected economic downturns, financial crises, and credit crunches we have not received the minimum expected bookings which have made it difficult for Us (developers) to access funding or secure necessary investments to complete the project within the Original Due date.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kartik Homes’s extension records on MahaRERA (P51700029229), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kartik Homes
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700029229
- Status
- Registered and active
- Builder
- KARTIK ENTERPRISES
- Location
- Shirgaon Badlapur East, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 10 May 2021
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 84
- Sold or booked
- 33%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kartik Homes, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 100% | 47% | 0% |
| B WING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A WING: covers 8 floors
- B WING: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kartik Homes every 1–2 months.
Kartik Homes: buildings, flats and land, as filed on MahaRERA
- Buildings: A WING (11 floors, 74 units) · B WING (7 floors, 30 units)
- Car parking: 15 open
- Land: 1,702 sq m (about 0.4 acres) · sanctioned built-up 4,400 sq m
- Land, as filed: S NO 74 H NO 2 S NO 74 H NO 3
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kartik Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kartik Homes: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kartik Homes
What is the possession date of Kartik Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kartik Homes in Shirgaon Badlapur East, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kartik Homes?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kartik Homes's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kartik Homes extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to Unexpected economic downturns, financial crises, and credit crunches we have not received the minimum expected bookings which have made it difficult for Us (developers) to access funding or secure necessary investments to complete the project within the Original Due date.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kartik Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kartik Homes in Shirgaon Badlapur East, Thane is P51700029229.
Is Kartik Homes registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes is registered as P51700029229 and its status is "Registered and active".
What is the current construction status of Kartik Homes? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Kartik Homes have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kartik Homes safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes is registered on MahaRERA as P51700029229, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kartik Homes?
Kartik Homes is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kartik Homes?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kartik Homes: gharkundli.com/tools/property-cost-calculator
Has Kartik Homes received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Kartik Homes uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kartik Homes was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kartik Homes's possession date changes?
The latest dates are on Kartik Homes's MahaRERA page (P51700029229). GharKundli's Kundli Watch sends a free WhatsApp update on Kartik Homes every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kartik Homes have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes has 2 buildings filed: A WING with 11 floors and 74 units; B WING with 7 floors and 30 units.
How much parking does Kartik Homes have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 open car parking spaces for Kartik Homes.
How big is the land of Kartik Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes stands on 1,702 sq m of land (about 0.4 acres), with 4,400 sq m of sanctioned built-up area.
What are the reviews of Kartik Homes?
Google Maps has reviews of Kartik Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kartik Homes?
Kartik Homes by KARTIK ENTERPRISES is in Shirgaon Badlapur East, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700029229, per GharKundli's check of MahaRERA records. Its land is filed as S NO 74 H NO 2 S NO 74 H NO 3. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Kartik Homes, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes has 84 homes in 2 towers registered on MahaRERA, and 33% of them are sold or booked.
When was Kartik Homes registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kartik Homes was registered on MahaRERA on 10 May 2021. GharKundli did not find a title report on the land on file there.
Does Kartik Homes have any legal issues or court cases?
No court cases are listed for Kartik Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Kartik Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KARTIK ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of Kartik Homes
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ambarnath
- Nature Vista Building - 1
- Midtown B and C Wing
- Mery Villa CHSL
- Sai Universe
- Dattatray Residency
- Mahadev Heights
- Chadha Residency
- New Neelgagan CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.