by Oscar Infrastructure Pvt Ltd (Bhagwati) · Ram Nagar, ThaneAlso near Dombivli, Ramnagar, Ayre

Possession date of Om Maitri: 30 October 2026, moved from 30 June 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700030770, and currently active. Its completion date has moved from June 2025 to October 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Om Maitri?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Om Maitri has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EA28062501839)

    Reason the builder gave MahaRERA: “Due to earlier litigation at the Kalyan Court, we faced significant difficulties in completing the project, as we were unable to sell the inventory or raise the necessary funds”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA31102518217)

    Reason the builder gave MahaRERA:
    “We, M/s Oscar Infrastructure Pvt. Ltd., promoter of the project “Om Maitri” (Reg. No. P51700030770), request an extension of the project registration beyond 31/12/2025 due to delays caused by the prolonged monsoon affecting external works s…” Read the full reason“We, M/s Oscar Infrastructure Pvt. Ltd., promoter of the project “Om Maitri” (Reg. No. P51700030770), request an extension of the project registration beyond 31/12/2025 due to delays caused by the prolonged monsoon affecting external works such as plastering, waterproofing, painting, and related finishing activities. The RCC structure is completed as certified by the Architect on 30/09/2025. We seek an extension up to 30/06/2026 to complete the remaining work and ensure timely possession in full compliance with RERA provisions.”
  4. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Om Maitri’s extension records on MahaRERA (P51700030770), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Om Maitri

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints and 1 court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700030770
Status
Registered and active
Builder
Oscar Infrastructure Pvt Ltd
Location
Ram Nagar, Thane · 421201
Project type
Residential / Group Housing
Registered on
13 Sep 2021
Completion date at registration
June 2025
Latest completion date
October 2026
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
15
Sold or booked
85%
Towers
1
Complaints on MahaRERA
6
Court cases listed
1
Title report on file
Not found

Construction progress of Om Maitri, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Om Maitri100%100%80%95%

Commencement certificate (CC), as filed on MahaRERA

  • Om Maitri: covers 13 floors

Latest CC order on MahaRERA: dated 27/12/2020.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Om Maitri every month.

Om Maitri: buildings, flats and land, as filed on MahaRERA

  • Buildings: Om Maitri (13 floors, 41 units)
  • Car parking: 28 covered
  • Land: 1,498 sq m (about 0.4 acres) · sanctioned built-up 2,554 sq m
  • Boundaries filed include: Kelkar Road, Chiplunkar Road, Tondon Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Oscar Infrastructure (a group of 9 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 12 months); 9 still being built, 5 past the promised date (typically 12 months late); 2 lapsed. 6 complaints on MahaRERA across 1 project.

Read Google reviews of Om Maitri →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Om Maitri: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Om Maitri

What is the possession date of Om Maitri?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Om Maitri in Ram Nagar, Thane is 30 October 2026 — 12 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Om Maitri?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Om Maitri's builder has filed on MahaRERA, the official one, is 30 October 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Om Maitri extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Due to earlier litigation at the Kalyan Court, we faced significant difficulties in completing the project, as we were unable to sell the inventory or raise the necessary funds"; to 30 June 2026, giving the reason "We, M/s Oscar Infrastructure Pvt. Ltd., promoter of the project “Om Maitri” (Reg. No. P51700030770), request an extension of the project registration beyond 31/12/2025 due to delays caused by the prolonged monsoon affecting external works such as plastering, waterproofing, painting, and related finishing activities. The RCC structure is completed as certified by the Architect on 30/09/2025. We seek an extension up to 30/06/2026 to complete the remaining work and ensure timely possession in full compliance with RERA provisions.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Om Maitri?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Om Maitri in Ram Nagar, Thane is P51700030770.

Is Om Maitri registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri is registered as P51700030770 and its status is "Registered and active".

What is the construction status of Om Maitri?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Om Maitri is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Om Maitri have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Om Maitri safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri is registered on MahaRERA as P51700030770, its completion date has moved 12 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Om Maitri's possession date changes?

The latest dates are on Om Maitri's MahaRERA page (P51700030770). GharKundli's Kundli Watch sends a free WhatsApp update on Om Maitri every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Om Maitri have?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri has one building filed: Om Maitri with 13 floors and 41 units.

How much parking does Om Maitri have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 covered car parking spaces for Om Maitri.

How big is the land of Om Maitri?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri stands on 1,498 sq m of land (about 0.4 acres), with 2,554 sq m of sanctioned built-up area.

What is the track record of Om Maitri's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Oscar Infrastructure (a group of 9 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 12 months); 9 still being built, 5 past the promised date (typically 12 months late); 2 lapsed. 6 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Om Maitri?

Google Maps has reviews of Om Maitri written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Om Maitri?

Om Maitri by Oscar Infrastructure Pvt Ltd (Bhagwati) is in Ram Nagar, Thane (pincode 421201), near Dombivli, Ramnagar, Ayre, Maharashtra, and is registered on MahaRERA as P51700030770, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kelkar Road, Chiplunkar Road, Tondon Road.

How many homes are in Om Maitri?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri has 15 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.

When was Om Maitri registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Maitri was registered on MahaRERA on 13 September 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Om Maitri?

1 court case is listed for Om Maitri on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Om Maitri?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Oscar Infrastructure Pvt Ltd, the company Bhagwati files this project under.

All projects with possession due in 2026 in Thane →

Other projects in pincode 421201

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.