by VILAS ASHOK CHAUDHARI · Dadar West, Mumbai 400028Also near Shivaji Park, Mahim, Matunga West

What’s in the report? →

Possession date of Shree Siddhi (MahaRERA P51900056074): 30 April 2027, moved from 31 March 2025 (21 months later). It has 27 homes (1 Room Kitchen, 2 BHK and 3 BHK, 216–1179 sq ft carpet), 75% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900056074, and currently active. Its completion date has moved from March 2025 to April 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51900056074, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shree Siddhi?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shree Siddhi has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EA03072501937)

    Reason the builder gave MahaRERA: “Extension required for taking bank loan for project completion”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA27032620401)

    Reason the builder gave MahaRERA:
    “The delay in completion of the project has occurred due to procedural delays in obtaining requisite approvals and clearances from concerned authorities, along with certain unforeseen practical constraints during construction and project exe…” Read the full reason“The delay in completion of the project has occurred due to procedural delays in obtaining requisite approvals and clearances from concerned authorities, along with certain unforeseen practical constraints during construction and project execution. The project is now at an advanced stage of completion, and the Occupancy Certificate is under process with the concerned authority and expected shortly. The delay is unintentional and occurred due to genuine circumstances beyond the control of the promoter. The promoter undertakes to complete the project within the extended timeline sought.”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shree Siddhi’s extension records on MahaRERA (P51900056074), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shree Siddhi

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900056074
Status
Registered and active
Builder
VILAS ASHOK CHAUDHARI
Location
Dadar West, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
10 May 2024
Completion date at registration
March 2025
Latest completion date
April 2027
Delay so far
21 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
27
Sold or booked
75%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Shree Siddhi, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE SIDDHI100%100%100%75%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE SIDDHI: covers C.C. is further extended up to top of 21st Floor

Latest CC order on MahaRERA: dated 03/04/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Siddhi every 1–2 months.

Shree Siddhi: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,103 – 1,17916
1 Room Kitchen216 – 43710
2 BHK9611

The builder’s record and reviews

Vilas Ashok Chaudhari has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Shree Siddhi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Siddhi: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shree Siddhi

What is the possession date of Shree Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Siddhi in Dadar West, Mumbai is 30 April 2027 — 21 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 21 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shree Siddhi?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Siddhi's builder has filed on MahaRERA, the official one, is 30 April 2027, already 21 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shree Siddhi extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "Extension required for taking bank loan for project completion"; to 31 December 2026, giving the reason "The delay in completion of the project has occurred due to procedural delays in obtaining requisite approvals and clearances from concerned authorities, along with certain unforeseen practical constraints during construction and project execution. The project is now at an advanced stage of completion, and the Occupancy Certificate is under process with the concerned authority and expected shortly. The delay is unintentional and occurred due to genuine circumstances beyond the control of the promoter. The promoter undertakes to complete the project within the extended timeline sought.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shree Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Siddhi in Dadar West, Mumbai is P51900056074.

Is Shree Siddhi registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi is registered as P51900056074 and its status is "Registered and active".

What is the current construction status of Shree Siddhi? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE SIDDHI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shree Siddhi have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shree Siddhi safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi is registered on MahaRERA as P51900056074, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shree Siddhi?

Shree Siddhi is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shree Siddhi are 216 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shree Siddhi?

For a flat in Shree Siddhi (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shree Siddhi received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shree Siddhi a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi is a redevelopment: 19 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Shree Siddhi uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Siddhi was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shree Siddhi's possession date changes?

The latest dates are on Shree Siddhi's MahaRERA page (P51900056074). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Siddhi every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Siddhi have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi has one building filed: SHREE SIDDHI with 21 floors and 27 units.

What are the flat sizes (carpet area) in Shree Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shree Siddhi: 3 BHK: 1103 to 1179 sq ft carpet (16 homes); 1 Room Kitchen: 216 to 437 sq ft carpet (10 homes); 2 BHK: 961 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Shree Siddhi have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 covered car parking spaces for Shree Siddhi.

How big is the land of Shree Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi stands on 465 sq m of land (about 0.1 acres), with 1,558 sq m of sanctioned built-up area.

What is the track record of Shree Siddhi's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vilas Ashok Chaudhari has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shree Siddhi?

Google Maps has reviews of Shree Siddhi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shree Siddhi?

Shree Siddhi by VILAS ASHOK CHAUDHARI is in Dadar West, Mumbai, pincode 400028 (near Shivaji Park, Mahim, Matunga West), Maharashtra, and is registered on MahaRERA as P51900056074, per GharKundli's check of MahaRERA records. Its land is filed as 1759. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).

How many flats are in Shree Siddhi, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi has 27 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.

When was Shree Siddhi registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi was registered on MahaRERA on 10 May 2024. GharKundli did not find a title report on the land on file there.

Does Shree Siddhi have any legal issues or court cases?

No court cases are listed for Shree Siddhi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shree Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VILAS ASHOK CHAUDHARI, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai City →

Other projects in Ward GNorth

All 148 projects in Dadar West (400028) →

Other projects by VILAS ASHOK CHAUDHARI

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.