Adimaya Adishakti

by ADIMAYA ENTERPRISE · Dombivli East, Thane 421201Also near Ramnagar, Village- G.B Patharli, Ram NagarRegistered on MahaRERA as “ADISHAKTI”

What’s in the report? →

Possession date of Adimaya Adishakti (MahaRERA P51700031649): 31 May 2027, moved from 3 June 2023 (43 months later). It has 34 homes, 42% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031649, and currently active. Its completion date has moved from June 2023 to May 2027: 43 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700031649, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Adimaya Adishakti?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Adimaya Adishakti has moved

  1. 3 June 2023

    Completion date given when the project was registered

  2. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT51700016900)

    Reason the builder gave MahaRERA: “Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis”
  3. 31 May 2025

    Extended at the builder's request (MahaRERA application EXT51700024889)

    Reason the builder gave MahaRERA: “We applied for an Occupancy Certificate but have not yet received it from the Municipal Corporation. Therefore, we need an extension for the project until May 31, 2025.”
  4. 31 January 2027

    Extended at the builder's request (MahaRERA application EA11062501548)

    Reason the builder gave MahaRERA:
    “We have applied for the Occupancy Certificate, but it has not yet been issued by the Municipal Corporation. Therefore, we are requesting a third extension for the project until January 31, 2027. We have proposed this extended date as a prec…” Read the full reason“We have applied for the Occupancy Certificate, but it has not yet been issued by the Municipal Corporation. Therefore, we are requesting a third extension for the project until January 31, 2027. We have proposed this extended date as a precaution, considering the uncertainty regarding the time it may take to obtain the Occupancy Certificate from the corporation. We would be sincerely grateful to RERA for granting this extension.”
  5. 31 May 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Adimaya Adishakti’s extension records on MahaRERA (P51700031649), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Adimaya Adishakti

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700031649
Status
Registered and active
Builder
ADIMAYA ENTERPRISE
Location
Dombivli East, Thane · 421201
Project type
Residential / Group Housing
Registered on
3 Nov 2021
Completion date at registration
June 2023
Latest completion date
May 2027
Delay so far
43 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
34
Sold or booked
42%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Adimaya Adishakti, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ADISHAKTI100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • ADISHAKTI: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Adimaya Adishakti every 1–2 months.

Adimaya Adishakti: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Adimaya Adishakti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Adimaya Adishakti: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Adimaya Adishakti

What is the possession date of Adimaya Adishakti?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Adimaya Adishakti in Dombivli East, Thane is 31 May 2027 — 43 months later than 3 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 43 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Adimaya Adishakti?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Adimaya Adishakti's builder has filed on MahaRERA, the official one, is 31 May 2027, already 43 months later than the 3 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Adimaya Adishakti extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti's builder applied to MahaRERA to extend the completion date 3 times: to 31 August 2024, giving the reason "Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis"; to 31 May 2025, giving the reason "We applied for an Occupancy Certificate but have not yet received it from the Municipal Corporation. Therefore, we need an extension for the project until May 31, 2025."; to 31 January 2027, giving the reason "We have applied for the Occupancy Certificate, but it has not yet been issued by the Municipal Corporation. Therefore, we are requesting a third extension for the project until January 31, 2027. We have proposed this extended date as a precaution, considering the uncertainty regarding the time it may take to obtain the Occupancy Certificate from the corporation. We would be sincerely grateful to RERA for granting this extension.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Adimaya Adishakti?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Adimaya Adishakti in Dombivli East, Thane is P51700031649.

Is Adimaya Adishakti registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti is registered as P51700031649 and its status is "Registered and active".

What is the current construction status of Adimaya Adishakti? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ADISHAKTI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Adimaya Adishakti have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Adimaya Adishakti safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti is registered on MahaRERA as P51700031649, its completion date has moved 43 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Adimaya Adishakti?

Adimaya Adishakti is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Adimaya Adishakti?

For a flat in Adimaya Adishakti (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Adimaya Adishakti received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti is still under construction, with 31 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Adimaya Adishakti uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Adimaya Adishakti was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Adimaya Adishakti's possession date changes?

The latest dates are on Adimaya Adishakti's MahaRERA page (P51700031649). GharKundli's Kundli Watch sends a free WhatsApp update on Adimaya Adishakti every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Adimaya Adishakti have?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti has one building filed: ADISHAKTI with 9 floors and 43 units.

How big is the land of Adimaya Adishakti?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti stands on 856 sq m of land (about 0.2 acres), with 2,660 sq m of sanctioned built-up area.

What are the reviews of Adimaya Adishakti?

Google Maps has reviews of Adimaya Adishakti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Adimaya Adishakti?

Adimaya Adishakti by ADIMAYA ENTERPRISE is in Dombivli East, Thane, pincode 421201 (near Ramnagar, Village- G.B Patharli, Ram Nagar), Maharashtra, and is registered on MahaRERA as P51700031649, per GharKundli's check of MahaRERA records. Its land is filed as 11049 TO 11057. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Adimaya Adishakti, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti has 34 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.

When was Adimaya Adishakti registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Adimaya Adishakti was registered on MahaRERA on 3 November 2021. GharKundli did not find a title report on the land on file there.

Does Adimaya Adishakti have any legal issues or court cases?

No court cases are listed for Adimaya Adishakti on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Adimaya Adishakti?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADIMAYA ENTERPRISE.

All projects with possession due in 2027 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.