Haware Leela Homes

by Pravin Kashinath Haware · Nr. Greater Valley International School, Thane 421605

What’s in the report? →

Possession date of Haware Leela Homes (MahaRERA P51700046165): 30 April 2029, moved from 31 January 2026 (35 months later). It has 1,423 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700046165, and currently active. Its completion date has moved from January 2026 to April 2029: 35 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700046165, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Haware Leela Homes?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Haware Leela Homes has moved

  1. 31 January 2026

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT51700024770)

    Reason the builder gave MahaRERA: “I was planning to expand the project but there was delay in receiving sanction plan from the authority. This Setback has postpone our project timeline as we need the official approval to proceed with expansion”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Haware Leela Homes’s extension records on MahaRERA (P51700046165), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Haware Leela Homes

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700046165
Status
Registered and active
Builder
Pravin Kashinath Haware
Location
Nr. Greater Valley International School, Thane · 421605
Project type
Residential / Group Housing
Registered on
20 Jun 2022
Completion date at registration
January 2026
Latest completion date
April 2029
Delay so far
35 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
1,423
Towers
30
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Haware Leela Homes, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing0%0%0%0%
B Wing0%0%0%0%
C Wing0%0%0%0%
D Wing0%0%0%0%
E Wing0%0%0%0%
F Wing0%0%0%0%
G Wing0%0%0%0%
H Wing0%0%0%0%
I Wing0%0%0%0%
J Wing0%0%0%0%
K Wing0%0%0%0%
L Wing0%0%0%0%
M Wing0%0%0%0%
N Wing0%0%0%0%
O Wing0%0%0%0%
P Wing0%0%0%0%
Q Wing0%0%0%0%
R Wing0%0%0%0%
S Wing0%0%0%0%
T Wing0%0%0%0%
U wing0%0%0%0%
V Wing0%0%0%0%
W Wing0%0%0%0%
X Wing0%0%0%0%
Y wing0%0%0%0%
Z Wing0%0%0%0%
AA0%0%0%0%
BB Wing0%0%0%0%
CC Wing0%0%0%0%
DD Wing0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Haware Leela Homes every 1–2 months.

Haware Leela Homes: buildings, flats and land, as filed on MahaRERA

  • Buildings: A Wing (8 floors) · B Wing (9 floors) · C Wing (9 floors) · D Wing (9 floors) · E Wing (9 floors) · F Wing (9 floors) · G Wing (9 floors) · H Wing (9 floors) · and 22 more
  • Land: 35,385 sq m (about 8.7 acres) · sanctioned built-up 50,399 sq m · recreational space 3,561 sq m
  • Land, as filed: 145/11/12/13 149/1
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Pravin Kashinath Haware has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 5 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Haware Leela Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Haware Leela Homes: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Haware Leela Homes

What is the possession date of Haware Leela Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Haware Leela Homes in Nr. Greater Valley International School, Thane is 30 April 2029 — 35 months later than 31 January 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 35 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Haware Leela Homes?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Haware Leela Homes's builder has filed on MahaRERA, the official one, is 30 April 2029, already 35 months later than the 31 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Haware Leela Homes extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "I was planning to expand the project but there was delay in receiving sanction plan from the authority. This Setback has postpone our project timeline as we need the official approval to proceed with expansion". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Haware Leela Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Haware Leela Homes in Nr. Greater Valley International School, Thane is P51700046165.

Is Haware Leela Homes registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes is registered as P51700046165 and its status is "Registered and active".

What is the current construction status of Haware Leela Homes? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does Haware Leela Homes have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Haware Leela Homes safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes is registered on MahaRERA as P51700046165, its completion date has moved 35 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Haware Leela Homes?

Haware Leela Homes is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Haware Leela Homes?

For a flat in Haware Leela Homes (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Haware Leela Homes received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Haware Leela Homes uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Haware Leela Homes was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Haware Leela Homes's possession date changes?

The latest dates are on Haware Leela Homes's MahaRERA page (P51700046165). GharKundli's Kundli Watch sends a free WhatsApp update on Haware Leela Homes every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Haware Leela Homes have?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes has 30 buildings filed: A Wing with 8 floors; B Wing with 9 floors; C Wing with 9 floors; D Wing with 9 floors; E Wing with 9 floors; F Wing with 9 floors; and 24 more.

How big is the land of Haware Leela Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes stands on 35,385 sq m of land (about 8.7 acres), with 50,399 sq m of sanctioned built-up area and 3,561 sq m of recreational open space.

What is the track record of Haware Leela Homes's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Pravin Kashinath Haware has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 5 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Haware Leela Homes?

Google Maps has reviews of Haware Leela Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Haware Leela Homes?

Haware Leela Homes by Pravin Kashinath Haware is in Nr. Greater Valley International School, Thane, pincode 421605, Maharashtra, and is registered on MahaRERA as P51700046165, per GharKundli's check of MahaRERA records. Its land is filed as 145/11/12/13 149/1. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Haware Leela Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes has 1,423 homes in 30 towers registered on MahaRERA.

When was Haware Leela Homes registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Haware Leela Homes was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.

Does Haware Leela Homes have any legal issues or court cases?

No court cases are listed for Haware Leela Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Haware Leela Homes?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pravin Kashinath Haware, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in Kalyan

All 174 projects in Titwala (421605) →

Other projects by Pravin Kashinath Haware

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.