Om Bhagwati

by OM BHAGWATI BUILDERS AND DEVELOPERS · KDMC, Thane 421201

What’s in the report? →

Possession date of Om Bhagwati (MahaRERA P51700033354): 30 April 2027, moved from 31 December 2023 (36 months later). It has 37 homes, 23% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700033354, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700033354, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Om Bhagwati?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Om Bhagwati has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 30 November 2024

    Extended at the builder's request (MahaRERA application EXT51700018571)

    Reason the builder gave MahaRERA: “due to change in RCC consultant”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700027097)

    Reason the builder gave MahaRERA:
    “We are in the process of purchasing TDR for our project. However, due to recent changes in government policy, some decisions are pending from KDMC. As a result, we need to extend our project timeline. We kindly request your approval for thi…” Read the full reason“We are in the process of purchasing TDR for our project. However, due to recent changes in government policy, some decisions are pending from KDMC. As a result, we need to extend our project timeline. We kindly request your approval for this extension without consent of members.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA04122518535)

    Reason the builder gave MahaRERA:
    “We are in the process of purchasing TDR for our project. However, due to recent changes in government policy, some decisions are pending from KDMC. and due to the uncertain rain situation external part of the building and painting was pendi…” Read the full reason“We are in the process of purchasing TDR for our project. However, due to recent changes in government policy, some decisions are pending from KDMC. and due to the uncertain rain situation external part of the building and painting was pending and As a result, we need to extend our project timeline. We kindly request your approval for this extension without consent of members.”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Om Bhagwati’s extension records on MahaRERA (P51700033354), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Om Bhagwati

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700033354
Status
Registered and active
Builder
OM BHAGWATI BUILDERS AND DEVELOPERS
Location
KDMC, Thane · 421201
Project type
Residential / Group Housing
Registered on
16 Feb 2022
Completion date at registration
December 2023
Latest completion date
April 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
37
Sold or booked
23%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Om Bhagwati, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OM BHAGWATI0%100%80%50%

Commencement certificate (CC), as filed on MahaRERA

  • OM BHAGWATI: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Om Bhagwati every 1–2 months.

Om Bhagwati: buildings, flats and land, as filed on MahaRERA

  • Buildings: OM BHAGWATI (9 floors, 37 units)
  • Car parking: 14 covered
  • Land: 542 sq m (about 0.1 acres) · sanctioned built-up 2,008 sq m
  • Boundaries filed include: PUBLIC ROAD
  • Land, as filed: 5845,6244
  • Map: Get directions

The builder’s record and reviews

Oscar Infrastructure (a group of 6 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 7 still being built, 5 past the promised date (typically 18 months late); 2 lapsed. 21 complaints on MahaRERA across 2 projects.

Read Google reviews of Om Bhagwati →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Om Bhagwati: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Om Bhagwati

What is the possession date of Om Bhagwati?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Om Bhagwati in KDMC, Thane is 30 April 2027 — 36 months later than 31 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Om Bhagwati?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Om Bhagwati's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Om Bhagwati extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati's builder applied to MahaRERA to extend the completion date 3 times: to 30 November 2024, giving the reason "due to change in RCC consultant"; to 31 December 2025, giving the reason "We are in the process of purchasing TDR for our project. However, due to recent changes in government policy, some decisions are pending from KDMC. As a result, we need to extend our project timeline. We kindly request your approval for this extension without consent of members."; to 31 December 2026, giving the reason "We are in the process of purchasing TDR for our project. However, due to recent changes in government policy, some decisions are pending from KDMC. and due to the uncertain rain situation external part of the building and painting was pending and As a result, we need to extend our project timeline. We kindly request your approval for this extension without consent of members.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Om Bhagwati?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Om Bhagwati in KDMC, Thane is P51700033354.

Is Om Bhagwati registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati is registered as P51700033354 and its status is "Registered and active".

What is the current construction status of Om Bhagwati? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati's status on MahaRERA is "Registered and active". As filed by the builder, slab work on OM BHAGWATI is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Om Bhagwati have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Om Bhagwati safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati is registered on MahaRERA as P51700033354, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Om Bhagwati?

Om Bhagwati is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Om Bhagwati?

For a flat in Om Bhagwati (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Om Bhagwati received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Om Bhagwati a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati is a redevelopment: 7 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Om Bhagwati uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Om Bhagwati was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Om Bhagwati's possession date changes?

The latest dates are on Om Bhagwati's MahaRERA page (P51700033354). GharKundli's Kundli Watch sends a free WhatsApp update on Om Bhagwati every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Om Bhagwati have?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati has one building filed: OM BHAGWATI with 9 floors and 37 units.

How much parking does Om Bhagwati have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for Om Bhagwati.

How big is the land of Om Bhagwati?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati stands on 542 sq m of land (about 0.1 acres), with 2,008 sq m of sanctioned built-up area.

What is the track record of Om Bhagwati's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Oscar Infrastructure (a group of 6 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 7 still being built, 5 past the promised date (typically 18 months late); 2 lapsed. 21 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Om Bhagwati?

Google Maps has reviews of Om Bhagwati written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Om Bhagwati?

Om Bhagwati by OM BHAGWATI BUILDERS AND DEVELOPERS is in KDMC, Thane, pincode 421201, Maharashtra, and is registered on MahaRERA as P51700033354, per GharKundli's check of MahaRERA records. Its boundaries filed there include PUBLIC ROAD. Its land is filed as 5845,6244. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Om Bhagwati, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati has 37 homes in 1 tower registered on MahaRERA, and 23% of them are sold or booked.

When was Om Bhagwati registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Bhagwati was registered on MahaRERA on 16 February 2022. GharKundli did not find a title report on the land on file there.

Does Om Bhagwati have any legal issues or court cases?

No court cases are listed for Om Bhagwati on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Om Bhagwati?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OM BHAGWATI BUILDERS AND DEVELOPERS.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.