Neelpadma Geetai Smruti
by NEELPADMA DEVELOPERS · Near DNC School, Thane 421201Also near Dombivli East, Ramnagar, Ram NagarRegistered on MahaRERA as “GEETAI SMRUTI”
What’s in the report? →Possession date of Neelpadma Geetai Smruti (MahaRERA P51700032519): 31 December 2026, moved from 31 December 2023 (36 months later). It has 28 homes, 53% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700032519, and currently active.
Source: MahaRERA website — records for P51700032519, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Neelpadma Geetai Smruti?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Neelpadma Geetai Smruti has moved
31 December 2023
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700019109)
Reason the builder gave MahaRERA: “Delay is due to Legal and Financial reasons.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025910)
Reason the builder gave MahaRERA:
“We previously secured approval for the construction up to the seventh floor however, there has been a delay in obtaining authorization for the eighth floor from the local authority, KDMC. Consequently, this has resulted in a setback for the…” Read the full reason
“We previously secured approval for the construction up to the seventh floor however, there has been a delay in obtaining authorization for the eighth floor from the local authority, KDMC. Consequently, this has resulted in a setback for the project. We hereby respectfully request an extension of one year, until 31/12/2025, to enable the completion of the project and to ensure that we can provide possession to the members as planned, thereby preventing any undue hardship due to this delay. We have obtained 100% consent from all members involved. Additionally, we have included the necessary d…”31 December 2026
Extended at the builder's request (MahaRERA application EA07012619329)
Reason the builder gave MahaRERA: “Construction progress was impacted due to traffic restrictions, road widening works, and access limitations imposed by local authorities, causing disruption in movement of construction materials and machinery”
Source: Neelpadma Geetai Smruti’s extension records on MahaRERA (P51700032519), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Neelpadma Geetai Smruti
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700032519
- Status
- Registered and active
- Builder
- NEELPADMA DEVELOPERS
- Location
- Near DNC School, Thane · 421201
- Project type
- Others
- Registered on
- 10 Jan 2022
- Completion date at registration
- December 2023
- Latest completion date
- December 2026
- Delay so far
- 36 months
- Homes
- 28
- Sold or booked
- 53%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Neelpadma Geetai Smruti, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Geetai | 100% | 90% | 40% | 0% |
| Smruti | 100% | 90% | 40% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Geetai: covers 6 floors
- Smruti: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neelpadma Geetai Smruti every 1–2 months.
Neelpadma Geetai Smruti: buildings, flats and land, as filed on MahaRERA
- Buildings: Geetai (6 floors, 10 units) · Smruti (7 floors, 18 units)
- Car parking: 7 covered
- Land: 869 sq m (about 0.2 acres) · sanctioned built-up 2,226 sq m
- Boundaries filed include: Internal Layout Road
- Land, as filed: 93/A/Part, Plot No 82 And 83
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Neelpadma Associates (a group of 8 linked companies) has 12 projects on MahaRERA since 2019, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 18 months late); 3 lapsed. No complaints on MahaRERA.
Read Google reviews of Neelpadma Geetai Smruti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Neelpadma Geetai Smruti: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Neelpadma Geetai Smruti
What is the possession date of Neelpadma Geetai Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neelpadma Geetai Smruti in Near DNC School, Thane is 31 December 2026 — 36 months later than 31 December 2023, the date given at registration.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Neelpadma Geetai Smruti?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Neelpadma Geetai Smruti's builder has filed on MahaRERA, the official one, is 31 December 2026, already 36 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Neelpadma Geetai Smruti extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2024, giving the reason "Delay is due to Legal and Financial reasons."; to 31 December 2025, giving the reason "We previously secured approval for the construction up to the seventh floor however, there has been a delay in obtaining authorization for the eighth floor from the local authority, KDMC. Consequently, this has resulted in a setback for the project. We hereby respectfully request an extension of one year, until 31/12/2025, to enable the completion of the project and to ensure that we can provide possession to the members as planned, thereby preventing any undue hardship due to this delay. We have obtained 100% consent from all members involved. Additionally, we have included the necessary d…"; to 31 December 2026, giving the reason "Construction progress was impacted due to traffic restrictions, road widening works, and access limitations imposed by local authorities, causing disruption in movement of construction materials and machinery".
What is the RERA number of Neelpadma Geetai Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neelpadma Geetai Smruti in Near DNC School, Thane is P51700032519.
Is Neelpadma Geetai Smruti registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti is registered as P51700032519 and its status is "Registered and active".
What is the current construction status of Neelpadma Geetai Smruti? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 90% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Neelpadma Geetai Smruti have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Neelpadma Geetai Smruti safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti is registered on MahaRERA as P51700032519, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Neelpadma Geetai Smruti?
Neelpadma Geetai Smruti is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Neelpadma Geetai Smruti?
For a flat in Neelpadma Geetai Smruti (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Neelpadma Geetai Smruti received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Neelpadma Geetai Smruti uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Neelpadma Geetai Smruti was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Neelpadma Geetai Smruti's possession date changes?
The latest dates are on Neelpadma Geetai Smruti's MahaRERA page (P51700032519). GharKundli's Kundli Watch sends a free WhatsApp update on Neelpadma Geetai Smruti every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Neelpadma Geetai Smruti have?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti has 2 buildings filed: Geetai with 6 floors and 10 units; Smruti with 7 floors and 18 units.
How much parking does Neelpadma Geetai Smruti have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered car parking spaces for Neelpadma Geetai Smruti.
How big is the land of Neelpadma Geetai Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti stands on 869 sq m of land (about 0.2 acres), with 2,226 sq m of sanctioned built-up area.
What is the track record of Neelpadma Geetai Smruti's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Associates (a group of 8 linked companies) has 12 projects on MahaRERA since 2019, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 18 months late); 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Neelpadma Geetai Smruti?
Google Maps has reviews of Neelpadma Geetai Smruti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Neelpadma Geetai Smruti?
Neelpadma Geetai Smruti by NEELPADMA DEVELOPERS is in Near DNC School, Thane, pincode 421201 (near Dombivli East, Ramnagar, Ram Nagar), Maharashtra, and is registered on MahaRERA as P51700032519, per GharKundli's check of MahaRERA records. Its boundaries filed there include Internal Layout Road. Its land is filed as 93/A/Part, Plot No 82 And 83. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Neelpadma Geetai Smruti, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti has 28 homes in 2 towers registered on MahaRERA, and 53% of them are sold or booked.
When was Neelpadma Geetai Smruti registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Geetai Smruti was registered on MahaRERA on 10 January 2022. GharKundli did not find a title report on the land on file there.
Does Neelpadma Geetai Smruti have any legal issues or court cases?
No court cases are listed for Neelpadma Geetai Smruti on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Neelpadma Geetai Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEELPADMA DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Neelpadma Geetai Smruti
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.