JAY Biroba Darshan
by JAY SADGURU BIROBA MAHARAJ DEVELOPERS · Near Classic Hotel, Thane 421201Registered on MahaRERA as “Biroba Darshan”
What’s in the report? →Possession date of JAY Biroba Darshan (MahaRERA P51700033106): 30 April 2027, moved from 31 December 2024 (24 months later). It has 112 homes, 59% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700033106, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700033106, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about JAY Biroba Darshan?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of JAY Biroba Darshan has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025871)
Reason the builder gave MahaRERA:
“We are facing financial challenges due to slow customer bookings and a resultant shortage of funds. Also we have received revised commencement certificate on 23/05/2023. Therefore, we request a 12-month extension under Section 7 to ensure t…” Read the full reason
“We are facing financial challenges due to slow customer bookings and a resultant shortage of funds. Also we have received revised commencement certificate on 23/05/2023. Therefore, we request a 12-month extension under Section 7 to ensure the project's timely and proper completion.”31 December 2026
Extended at the builder's request (MahaRERA application EA27122519056)
Reason the builder gave MahaRERA: “financial constraints, supply chain disruptions and same was effecting booking since last 6 months”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: JAY Biroba Darshan’s extension records on MahaRERA (P51700033106), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on JAY Biroba Darshan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700033106
- Status
- Registered and active
- Builder
- JAY SADGURU BIROBA MAHARAJ DEVELOPERS
- Location
- Near Classic Hotel, Thane · 421201
- Project type
- Others
- Registered on
- 9 Feb 2022
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 112
- Sold or booked
- 59%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of JAY Biroba Darshan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BIROBA DARSHAN 1 | 100% | 100% | 100% | 100% |
| Biroba Darshan 2 | 100% | 100% | 95% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- BIROBA DARSHAN 1: covers 8 floors
- Biroba Darshan 2: covers 8 floors
Latest CC order on MahaRERA: dated 23/05/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on JAY Biroba Darshan every 1–2 months.
JAY Biroba Darshan: buildings, flats and land, as filed on MahaRERA
- Buildings: BIROBA DARSHAN 1 (8 floors, 65 units) · Biroba Darshan 2 (8 floors, 64 units)
- Car parking: 37 open
- Land: 2,630 sq m (about 0.6 acres) · sanctioned built-up 5,994 sq m
- Land, as filed: 7/1/3/1
- Map: Get directions
The builder’s record and reviews
JAY Sadguru Biroba Maharaj Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of JAY Biroba Darshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
JAY Biroba Darshan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about JAY Biroba Darshan
What is the possession date of JAY Biroba Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JAY Biroba Darshan in Near Classic Hotel, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for JAY Biroba Darshan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date JAY Biroba Darshan's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of JAY Biroba Darshan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "We are facing financial challenges due to slow customer bookings and a resultant shortage of funds. Also we have received revised commencement certificate on 23/05/2023. Therefore, we request a 12-month extension under Section 7 to ensure the project's timely and proper completion."; to 31 December 2026, giving the reason "financial constraints, supply chain disruptions and same was effecting booking since last 6 months". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of JAY Biroba Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JAY Biroba Darshan in Near Classic Hotel, Thane is P51700033106.
Is JAY Biroba Darshan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan is registered as P51700033106 and its status is "Registered and active".
What is the current construction status of JAY Biroba Darshan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does JAY Biroba Darshan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is JAY Biroba Darshan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan is registered on MahaRERA as P51700033106, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in JAY Biroba Darshan?
JAY Biroba Darshan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in JAY Biroba Darshan?
For a flat in JAY Biroba Darshan (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has JAY Biroba Darshan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has JAY Biroba Darshan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for JAY Biroba Darshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if JAY Biroba Darshan's possession date changes?
The latest dates are on JAY Biroba Darshan's MahaRERA page (P51700033106). GharKundli's Kundli Watch sends a free WhatsApp update on JAY Biroba Darshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does JAY Biroba Darshan have?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan has 2 buildings filed: BIROBA DARSHAN 1 with 8 floors and 65 units; Biroba Darshan 2 with 8 floors and 64 units.
How much parking does JAY Biroba Darshan have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 37 open car parking spaces for JAY Biroba Darshan.
How big is the land of JAY Biroba Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan stands on 2,630 sq m of land (about 0.6 acres), with 5,994 sq m of sanctioned built-up area.
What is the track record of JAY Biroba Darshan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Sadguru Biroba Maharaj Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of JAY Biroba Darshan?
Google Maps has reviews of JAY Biroba Darshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of JAY Biroba Darshan?
JAY Biroba Darshan by JAY SADGURU BIROBA MAHARAJ DEVELOPERS is in Near Classic Hotel, Thane, pincode 421201, Maharashtra, and is registered on MahaRERA as P51700033106, per GharKundli's check of MahaRERA records. Its land is filed as 7/1/3/1. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in JAY Biroba Darshan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan has 112 homes in 2 towers registered on MahaRERA, and 59% of them are sold or booked.
When was JAY Biroba Darshan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), JAY Biroba Darshan was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.
Does JAY Biroba Darshan have any legal issues or court cases?
No court cases are listed for JAY Biroba Darshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of JAY Biroba Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAY SADGURU BIROBA MAHARAJ DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of JAY Biroba Darshan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.