Possession date of KMC SKYLINE: 30 October 2028, moved from 31 December 2025 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700033584, and currently active. Its completion date has moved from December 2025 to October 2028: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about KMC SKYLINE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KMC SKYLINE has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2028

    Extended at the builder's request (MahaRERA application EA09112518286)

    Reason the builder gave MahaRERA: “The project could not be completed earlier due to internal issues between the partners. These issues have now been resolved, and the project will be completed within the given timeline.”
  3. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KMC SKYLINE’s extension records on MahaRERA (P51700033584), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KMC SKYLINE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700033584
Status
Registered and active
Builder
PRIME PROPERTIES
Location
Kanchangaon Thakurli, Thane · 421201
Project type
Residential / Group Housing
Registered on
2 Mar 2022
Completion date at registration
December 2025
Latest completion date
October 2028
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
37
Sold or booked
41%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of KMC SKYLINE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KMC SKYLINE100%40%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • KMC SKYLINE: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KMC SKYLINE every month.

KMC SKYLINE: buildings, flats and land, as filed on MahaRERA

  • Buildings: KMC SKYLINE (20 floors, 44 units)
  • Land: 1,470 sq m (about 0.4 acres) · sanctioned built-up 2,035 sq m
  • Boundaries filed include: VIGHANAHARTA SOCIETY, SARVODAYA TRILOK SOCIETY
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KMC SKYLINE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KMC SKYLINE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KMC SKYLINE

What is the possession date of KMC SKYLINE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KMC SKYLINE in Kanchangaon Thakurli, Thane is 30 October 2028 — 30 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for KMC SKYLINE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KMC SKYLINE's builder has filed on MahaRERA, the official one, is 30 October 2028, already 30 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KMC SKYLINE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE's builder applied to MahaRERA to extend the completion date once: to 30 June 2028, giving the reason "The project could not be completed earlier due to internal issues between the partners. These issues have now been resolved, and the project will be completed within the given timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of KMC SKYLINE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KMC SKYLINE in Kanchangaon Thakurli, Thane is P51700033584.

Is KMC SKYLINE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE is registered as P51700033584 and its status is "Registered and active".

What is the construction status of KMC SKYLINE?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KMC SKYLINE is 40% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does KMC SKYLINE have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is KMC SKYLINE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE is registered on MahaRERA as P51700033584, its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KMC SKYLINE's possession date changes?

The latest dates are on KMC SKYLINE's MahaRERA page (P51700033584). GharKundli's Kundli Watch sends a free WhatsApp update on KMC SKYLINE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KMC SKYLINE have?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE has one building filed: KMC SKYLINE with 20 floors and 44 units.

How big is the land of KMC SKYLINE?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE stands on 1,470 sq m of land (about 0.4 acres), with 2,035 sq m of sanctioned built-up area.

Where can I read reviews of KMC SKYLINE?

Google Maps has reviews of KMC SKYLINE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KMC SKYLINE?

KMC SKYLINE by PRIME PROPERTIES is in Kanchangaon Thakurli, Thane (pincode 421201), near Dombivli, Thakurli East, Maharashtra, and is registered on MahaRERA as P51700033584, per GharKundli's check of MahaRERA records. Its boundaries filed there include VIGHANAHARTA SOCIETY, SARVODAYA TRILOK SOCIETY.

How many homes are in KMC SKYLINE?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE has 37 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.

When was KMC SKYLINE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KMC SKYLINE was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on KMC SKYLINE?

No court cases are listed for KMC SKYLINE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KMC SKYLINE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRIME PROPERTIES, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Kalyan

All 408 projects in Tilaknagar (421201) →

Other projects by PRIME PROPERTIES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.