Blossom Height
by Shiv Sai Constructions · Badlapur East, Thane 421503Also near Kulgaon
What’s in the report? →Possession date of Blossom Height (MahaRERA P51700034602): 30 April 2029, moved from 31 December 2024 (48 months later). It has 44 homes, 84% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700034602, and currently active. Its completion date has moved from December 2024 to April 2029: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700034602, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Blossom Height?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Blossom Height has moved
31 December 2024
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EXT51700027557)
Reason the builder gave MahaRERA:
“The promoter faced financial constraints causing delay but has already completed the project w.r.t building way back and obtained part oc dated 06-01-2025 However with respect to Bungalow in the project the promoter requires time to constru…” Read the full reason
“The promoter faced financial constraints causing delay but has already completed the project w.r.t building way back and obtained part oc dated 06-01-2025 However with respect to Bungalow in the project the promoter requires time to construct the saleable bungalow. It is important to note that there has been no sale made for the bungalow.”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Blossom Height’s extension records on MahaRERA (P51700034602), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Blossom Height
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700034602
- Status
- Registered and active
- Builder
- Shiv Sai Constructions
- Location
- Badlapur East, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 11 Apr 2022
- Completion date at registration
- December 2024
- Latest completion date
- April 2029
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 44
- Sold or booked
- 84%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Blossom Height, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLOSSOM HEIGHT | 100% | 100% | 100% | 100% |
| BUNGLOW | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLOSSOM HEIGHT: covers 9 floors
- BUNGLOW: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Blossom Height every 1–2 months.
Blossom Height: buildings, flats and land, as filed on MahaRERA
- Buildings: BLOSSOM HEIGHT (9 floors, 42 units) · BUNGLOW (2 floors, 2 units)
- Land: 1,060 sq m (about 0.3 acres) · sanctioned built-up 1,864 sq m
- Land, as filed: S NO 5/25/A
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Blossom Height →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Blossom Height: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Blossom Height
What is the possession date of Blossom Height?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Blossom Height in Badlapur East, Thane is 30 April 2029 — 48 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Blossom Height?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Blossom Height's builder has filed on MahaRERA, the official one, is 30 April 2029, already 48 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Blossom Height extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "The promoter faced financial constraints causing delay but has already completed the project w.r.t building way back and obtained part oc dated 06-01-2025 However with respect to Bungalow in the project the promoter requires time to construct the saleable bungalow. It is important to note that there has been no sale made for the bungalow.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Blossom Height?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Blossom Height in Badlapur East, Thane is P51700034602.
Is Blossom Height registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height is registered as P51700034602 and its status is "Registered and active".
What is the current construction status of Blossom Height? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Blossom Height have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Blossom Height safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height is registered on MahaRERA as P51700034602, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Blossom Height?
Blossom Height is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Blossom Height?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Blossom Height: gharkundli.com/tools/property-cost-calculator
Has Blossom Height received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Blossom Height uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Blossom Height was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Blossom Height's possession date changes?
The latest dates are on Blossom Height's MahaRERA page (P51700034602). GharKundli's Kundli Watch sends a free WhatsApp update on Blossom Height every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Blossom Height have?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height has 2 buildings filed: BLOSSOM HEIGHT with 9 floors and 42 units; BUNGLOW with 2 floors and 2 units.
How big is the land of Blossom Height?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height stands on 1,060 sq m of land (about 0.3 acres), with 1,864 sq m of sanctioned built-up area.
What are the reviews of Blossom Height?
Google Maps has reviews of Blossom Height written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Blossom Height?
Blossom Height by Shiv Sai Constructions is in Badlapur East, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700034602, per GharKundli's check of MahaRERA records. Its land is filed as S NO 5/25/A. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Blossom Height, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height has 44 homes in 2 towers registered on MahaRERA, and 84% of them are sold or booked.
When was Blossom Height registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Blossom Height was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.
Does Blossom Height have any legal issues or court cases?
No court cases are listed for Blossom Height on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Blossom Height?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shiv Sai Constructions, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Blossom Height
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in Kulgaon (421503)
- Sai Universe
- Mery Villa CHSL
- Mahavir Heritage
- Infinity Meadows
- Gokul Heights
- Shiv Tirth B Wing
- Hari Shrushti Wing A Phase II
- Dattatray Residency
Other projects by Shiv Sai Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.