Amrut Raj Regalia Phase-2
by AMRUT LAXMI DEVELOPERS · Nxt To Reliance Residency, Thane 421501Also near Ulhasnagar, Ambernath West, O.E.AmbernathRegistered on MahaRERA as “RAJ REGALIA PHASE-2”
What’s in the report? →Possession date of Amrut Raj Regalia Phase-2 (MahaRERA P51700034369): 30 June 2027, moved from 30 June 2025 (24 months later). It has 211 homes, 70% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700034369, and currently active.
Source: MahaRERA website — records for P51700034369, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Amrut Raj Regalia Phase-2?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Amrut Raj Regalia Phase-2 has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EXT51700024383)
Reason the builder gave MahaRERA:
“Name of the Developer:- M/s Amrutlaxmi Developers Sub:- Application for Extension of RERA Project " Raj Regalia Phase-2 " Respected Sir, We, M/s Amrutlaxmi Developers, have registered for our real estate project "Raj Regalia Phase-2" bearin…” Read the full reason
“Name of the Developer:- M/s Amrutlaxmi Developers Sub:- Application for Extension of RERA Project " Raj Regalia Phase-2 " Respected Sir, We, M/s Amrutlaxmi Developers, have registered for our real estate project "Raj Regalia Phase-2" bearing registration no. P51700034369. The date of completion of the project was given as 30.06.2025 at the time of registration. However, we couldn’t complete said project within the stipulated period due to the finishing work, fire-fighting NOC, electricity main line connection and solar work are yet to be completed. We request to kindly accept our applicatio…”30 June 2027
Extended at the builder's request (MahaRERA application EA23042620712)
Reason the builder gave MahaRERA:
“Dear Sir/Madam, We, Amrut Laxmi Developers, ("AMRUT"), and we are writing you with regards to our application for extension of time till 30th June, 2027; 1. As you are aware that the company is engaged in the constructing a real estate proj…” Read the full reason
“Dear Sir/Madam, We, Amrut Laxmi Developers, ("AMRUT"), and we are writing you with regards to our application for extension of time till 30th June, 2027; 1. As you are aware that the company is engaged in the constructing a real estate project at Ambernath, Maharashtra on its plot of land comprising of 1 Building Wings having 13 floors.” [hereinafter collectively referred to as "the Project"). 2. We say that we obtained the Rera registration number for Project RAJ REGALIA PHASE-2 at Ambernath, Thane bearing number P51700034369. 3. We say that our project 80% completed in March-2026. Due to…”
Source: Amrut Raj Regalia Phase-2’s extension records on MahaRERA (P51700034369), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Amrut Raj Regalia Phase-2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- RAJ REGALIA PHASE-1AP51700024748 · possession 29 Jun 2024
- RAJ REGALIA - PHASE IP51700017364 · possession 30 Dec 2022
- MahaRERA registration
- P51700034369
- Status
- Registered and active
- Builder
- AMRUT LAXMI DEVELOPERS
- Location
- Nxt To Reliance Residency, Thane · 421501
- Project type
- Others
- Registered on
- 4 Apr 2022
- Completion date at registration
- June 2025
- Latest completion date
- June 2027
- Delay so far
- 24 months
- Homes
- 211
- Sold or booked
- 70%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Amrut Raj Regalia Phase-2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1 | 100% | 100% | 100% | 97% |
| BUILDING NO 2 | 100% | 100% | 100% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1: covers 13 floors
- BUILDING NO 2: covers 13 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Amrut Raj Regalia Phase-2 every 1–2 months.
Amrut Raj Regalia Phase-2: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 1 (14 floors, 128 units) · BUILDING NO 2 (14 floors, 117 units)
- Land: 4,518 sq m (about 1.1 acres) · sanctioned built-up 16,183 sq m · recreational space 452 sq m
- Boundaries filed include: 24 MTR WDP ROAD
- Land, as filed: PLOT NO 3 S NO 54 3 E
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Amrut Raj Regalia Phase-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Amrut Raj Regalia Phase-2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Amrut Raj Regalia Phase-2
What is the possession date of Amrut Raj Regalia Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Amrut Raj Regalia Phase-2 in Nxt To Reliance Residency, Thane is 30 June 2027 — 24 months later than 30 June 2025, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Amrut Raj Regalia Phase-2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Amrut Raj Regalia Phase-2's builder has filed on MahaRERA, the official one, is 30 June 2027, already 24 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Amrut Raj Regalia Phase-2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "Name of the Developer:- M/s Amrutlaxmi Developers Sub:- Application for Extension of RERA Project " Raj Regalia Phase-2 " Respected Sir, We, M/s Amrutlaxmi Developers, have registered for our real estate project "Raj Regalia Phase-2" bearing registration no. P51700034369. The date of completion of the project was given as 30.06.2025 at the time of registration. However, we couldn’t complete said project within the stipulated period due to the finishing work, fire-fighting NOC, electricity main line connection and solar work are yet to be completed. We request to kindly accept our applicatio…"; to 30 June 2027, giving the reason "Dear Sir/Madam, We, Amrut Laxmi Developers, ("AMRUT"), and we are writing you with regards to our application for extension of time till 30th June, 2027; 1. As you are aware that the company is engaged in the constructing a real estate project at Ambernath, Maharashtra on its plot of land comprising of 1 Building Wings having 13 floors.” [hereinafter collectively referred to as "the Project"). 2. We say that we obtained the Rera registration number for Project RAJ REGALIA PHASE-2 at Ambernath, Thane bearing number P51700034369. 3. We say that our project 80% completed in March-2026. Due to…".
What is the RERA number of Amrut Raj Regalia Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Amrut Raj Regalia Phase-2 in Nxt To Reliance Residency, Thane is P51700034369.
Is Amrut Raj Regalia Phase-2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 is registered as P51700034369 and its status is "Registered and active".
What is the current construction status of Amrut Raj Regalia Phase-2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Amrut Raj Regalia Phase-2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Amrut Raj Regalia Phase-2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 is registered on MahaRERA as P51700034369, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Amrut Raj Regalia Phase-2?
Amrut Raj Regalia Phase-2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Amrut Raj Regalia Phase-2?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Amrut Raj Regalia Phase-2: gharkundli.com/tools/property-cost-calculator
Has Amrut Raj Regalia Phase-2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 is still under construction, with 30 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Amrut Raj Regalia Phase-2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Amrut Raj Regalia Phase-2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Amrut Raj Regalia Phase-2 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: RAJ REGALIA PHASE-1A (P51700024748, possession 29 Jun 2024); RAJ REGALIA - PHASE I (P51700017364, possession 30 Dec 2022). Check that your agreement names the registration of your own wing.
How can I get updates if Amrut Raj Regalia Phase-2's possession date changes?
The latest dates are on Amrut Raj Regalia Phase-2's MahaRERA page (P51700034369). GharKundli's Kundli Watch sends a free WhatsApp update on Amrut Raj Regalia Phase-2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Amrut Raj Regalia Phase-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 has 2 buildings filed: BUILDING NO 1 with 14 floors and 128 units; BUILDING NO 2 with 14 floors and 117 units.
How big is the land of Amrut Raj Regalia Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 stands on 4,518 sq m of land (about 1.1 acres), with 16,183 sq m of sanctioned built-up area and 452 sq m of recreational open space.
What are the reviews of Amrut Raj Regalia Phase-2?
Google Maps has reviews of Amrut Raj Regalia Phase-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Amrut Raj Regalia Phase-2?
Amrut Raj Regalia Phase-2 by AMRUT LAXMI DEVELOPERS is in Nxt To Reliance Residency, Thane, pincode 421501 (near Ulhasnagar, Ambernath West, O.E.Ambernath), Maharashtra, and is registered on MahaRERA as P51700034369, per GharKundli's check of MahaRERA records. Its boundaries filed there include 24 MTR WDP ROAD. Its land is filed as PLOT NO 3 S NO 54 3 E. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Amrut Raj Regalia Phase-2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 has 211 homes in 2 towers registered on MahaRERA, and 70% of them are sold or booked.
When was Amrut Raj Regalia Phase-2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Raj Regalia Phase-2 was registered on MahaRERA on 4 April 2022. GharKundli did not find a title report on the land on file there.
Does Amrut Raj Regalia Phase-2 have any legal issues or court cases?
No court cases are listed for Amrut Raj Regalia Phase-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Amrut Raj Regalia Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AMRUT LAXMI DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Amrut Raj Regalia Phase-2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ambarnath
- Nature Vista Building - 1
- Midtown B and C Wing
- Mery Villa CHSL
- Sai Universe
- Dattatray Residency
- Mahadev Heights
- Chadha Residency
- New Neelgagan CHS
Other projects by AMRUT LAXMI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.