What’s in the report? →Possession date of Aastha Omkar (MahaRERA P51700035044): 30 April 2029, moved from 31 December 2026 (24 months later). It has 294 homes, 37% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700035044, and currently active. Its completion date has moved from December 2026 to April 2029: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700035044, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Aastha Omkar?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aastha Omkar has moved
31 December 2026
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EXT51700027755)
Reason the builder gave MahaRERA: “DUE TO CHANGE IN THE PLAN AND INCREASE OF FSI, THE PROJECT EXTENSION IS REQUIRED. REQUIRED DETAILS ARE ATTACHED HEREWITH”
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Aastha Omkar’s extension records on MahaRERA (P51700035044), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aastha Omkar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700035044
- Status
- Registered and active
- Builder
- Aastha Realtors
- Location
- Balyani, Thane · 421605
- Project type
- Others
- Registered on
- 29 Apr 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2029
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 294
- Sold or booked
- 37%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Aastha Omkar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing B | 100% | 65% | 10% | 0% |
| Wing A | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing B: covers 17 floors
- Wing A: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aastha Omkar every 1–2 months.
Aastha Omkar: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing B (17 floors, 165 units) · Wing A (14 floors, 150 units)
- Car parking: 48 covered, 94 open
- Land: 4,481 sq m (about 1.1 acres) · sanctioned built-up 17,079 sq m · recreational space 450 sq m
- Land, as filed: S. No. 56, H. No. 35/D/2B/1 TO 35/D/2B/14 AND H. NO. 35/D/2B/15/1
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Aastha Realtors has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 34 months late). No complaints on MahaRERA.
Read Google reviews of Aastha Omkar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aastha Omkar: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aastha Omkar
What is the possession date of Aastha Omkar?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aastha Omkar in Balyani, Thane is 30 April 2029 — 24 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Aastha Omkar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aastha Omkar's builder has filed on MahaRERA, the official one, is 30 April 2029, already 24 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aastha Omkar extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "DUE TO CHANGE IN THE PLAN AND INCREASE OF FSI, THE PROJECT EXTENSION IS REQUIRED. REQUIRED DETAILS ARE ATTACHED HEREWITH". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Aastha Omkar?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aastha Omkar in Balyani, Thane is P51700035044.
Is Aastha Omkar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar is registered as P51700035044 and its status is "Registered and active".
What is the current construction status of Aastha Omkar? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 65% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Aastha Omkar have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Aastha Omkar safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar is registered on MahaRERA as P51700035044, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aastha Omkar?
Aastha Omkar is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aastha Omkar?
For a flat in Aastha Omkar (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Aastha Omkar received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Aastha Omkar uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aastha Omkar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aastha Omkar's possession date changes?
The latest dates are on Aastha Omkar's MahaRERA page (P51700035044). GharKundli's Kundli Watch sends a free WhatsApp update on Aastha Omkar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aastha Omkar have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar has 2 buildings filed: Wing B with 17 floors and 165 units; Wing A with 14 floors and 150 units.
How much parking does Aastha Omkar have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 48 covered and 94 open car parking spaces for Aastha Omkar.
How big is the land of Aastha Omkar?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar stands on 4,481 sq m of land (about 1.1 acres), with 17,079 sq m of sanctioned built-up area and 450 sq m of recreational open space.
What is the track record of Aastha Omkar's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Realtors has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 34 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Aastha Omkar?
Google Maps has reviews of Aastha Omkar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aastha Omkar?
Aastha Omkar by Aastha Realtors is in Balyani, Thane, pincode 421605 (near Titwala), Maharashtra, and is registered on MahaRERA as P51700035044, per GharKundli's check of MahaRERA records. Its land is filed as S. No. 56, H. No. 35/D/2B/1 TO 35/D/2B/14 AND H. NO. 35/D/2B/15/1. GharKundli lists all 174 MahaRERA projects in Titwala (421605).
How many flats are in Aastha Omkar, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar has 294 homes in 2 towers registered on MahaRERA, and 37% of them are sold or booked.
When was Aastha Omkar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aastha Omkar was registered on MahaRERA on 29 April 2022. GharKundli did not find a title report on the land on file there.
Does Aastha Omkar have any legal issues or court cases?
No court cases are listed for Aastha Omkar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Aastha Omkar?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aastha Realtors.
Check it yourself on MahaRERA
- How to check the possession date of Aastha Omkar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in Kalyan
- Pearl Galaxy
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Om Trimurti Darshan
- Balaji Govind
- Swami Elite
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.