Deepali Deep Dhara
by M/s. Deepali Infracon LLP · At Village - Kharvai, Badlapur, Thane 421503Registered on MahaRERA as “Deep Dhara”
What’s in the report? →Possession date of Deepali Deep Dhara (MahaRERA P51700048280): 30 April 2027, moved from 31 December 2025 (12 months later). It has 112 homes, 4% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048280, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700048280, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Deepali Deep Dhara?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Deepali Deep Dhara has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA25092517936)
Reason the builder gave MahaRERA:
“The project is under construction & we have completed more than 70% work on the project. However due to Scarcity of labour contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while register…” Read the full reason
“The project is under construction & we have completed more than 70% work on the project. However due to Scarcity of labour contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to above circumstances it is getting delayed.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Deepali Deep Dhara’s extension records on MahaRERA (P51700048280), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Deepali Deep Dhara
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048280
- Status
- Registered and active
- Builder
- M/s. Deepali Infracon LLP
- Location
- At Village - Kharvai, Badlapur, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 22 Dec 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 112
- Sold or booked
- 4%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Deepali Deep Dhara, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing-A | 100% | 100% | 100% | 90% |
| Wing-B | 100% | 100% | 100% | 90% |
| Wing-C | 100% | 100% | 100% | 90% |
| Wing-D | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Wing-A: covers 7 floors
- Wing-B: covers 7 floors
- Wing-C: covers 7 floors
- Wing-D: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Deepali Deep Dhara every 1–2 months.
Deepali Deep Dhara: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing-A (8 floors, 28 units) · Wing-B (8 floors, 28 units) · Wing-C (8 floors, 28 units) · Wing-D (8 floors, 28 units)
- Car parking: 36 open
- Land: 3,820 sq m (about 0.9 acres) · sanctioned built-up 4,916 sq m
- Land, as filed: Survey No 79 Hissa No 3
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Deepali Deep Dhara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Deepali Deep Dhara: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Deepali Deep Dhara
What is the possession date of Deepali Deep Dhara?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Deepali Deep Dhara in At Village - Kharvai, Badlapur, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Deepali Deep Dhara?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Deepali Deep Dhara's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Deepali Deep Dhara extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project is under construction & we have completed more than 70% work on the project. However due to Scarcity of labour contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to above circumstances it is getting delayed.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Deepali Deep Dhara?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Deepali Deep Dhara in At Village - Kharvai, Badlapur, Thane is P51700048280.
Is Deepali Deep Dhara registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara is registered as P51700048280 and its status is "Registered and active".
What is the current construction status of Deepali Deep Dhara? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Deepali Deep Dhara have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Deepali Deep Dhara safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara is registered on MahaRERA as P51700048280, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Deepali Deep Dhara?
Deepali Deep Dhara is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Deepali Deep Dhara?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Deepali Deep Dhara: gharkundli.com/tools/property-cost-calculator
Has Deepali Deep Dhara received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Deepali Deep Dhara uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Deepali Deep Dhara was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Deepali Deep Dhara's possession date changes?
The latest dates are on Deepali Deep Dhara's MahaRERA page (P51700048280). GharKundli's Kundli Watch sends a free WhatsApp update on Deepali Deep Dhara every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Deepali Deep Dhara have?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara has 4 buildings filed: Wing-A with 8 floors and 28 units; Wing-B with 8 floors and 28 units; Wing-C with 8 floors and 28 units; Wing-D with 8 floors and 28 units.
How much parking does Deepali Deep Dhara have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 open car parking spaces for Deepali Deep Dhara.
How big is the land of Deepali Deep Dhara?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara stands on 3,820 sq m of land (about 0.9 acres), with 4,916 sq m of sanctioned built-up area.
What are the reviews of Deepali Deep Dhara?
Google Maps has reviews of Deepali Deep Dhara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Deepali Deep Dhara?
Deepali Deep Dhara by M/s. Deepali Infracon LLP is in At Village - Kharvai, Badlapur, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700048280, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 79 Hissa No 3. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Deepali Deep Dhara, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara has 112 homes in 4 towers registered on MahaRERA, and 4% of them are sold or booked.
When was Deepali Deep Dhara registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepali Deep Dhara was registered on MahaRERA on 22 December 2022. GharKundli did not find a title report on the land on file there.
Does Deepali Deep Dhara have any legal issues or court cases?
No court cases are listed for Deepali Deep Dhara on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Deepali Deep Dhara?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Deepali Infracon LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Deepali Deep Dhara
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ambarnath
- Nature Vista Building - 1
- Midtown B and C Wing
- Mery Villa CHSL
- Sai Universe
- Dattatray Residency
- Mahadev Heights
- Chadha Residency
- New Neelgagan CHS
Other projects by M/s. Deepali Infracon LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.