Patel Mount

by Patel Group & Co · Chikanghar, Kalyan West, Thane

Possession date of Patel Mount: 30 April 2027, moved from 30 June 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700048299, and currently active. Its completion date has moved from June 2024 to April 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Patel Mount?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Patel Mount has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 29 June 2025

    Extended at the builder's request (MahaRERA application EXT51700024054)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA02072501927)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2026”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Patel Mount’s extension records on MahaRERA (P51700048299), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Patel Mount

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700048299
Status
Registered and active
Builder
Patel Group & Co
Location
Chikanghar, Kalyan West, Thane · 421301
Project type
Others
Registered on
26 Dec 2022
Completion date at registration
June 2024
Latest completion date
April 2027
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
69
Sold or booked
32%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Patel Mount, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building B195%62%60%10%

Commencement certificate (CC), as filed on MahaRERA

  • Building B1: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Patel Mount every month.

Patel Mount: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building B1 (11 floors, 81 units)
  • Land: 651 sq m (about 0.2 acres) · sanctioned built-up 4,699 sq m

The builder’s record and reviews

Patel Group & has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 24 months late); 3 lapsed. 40 complaints on MahaRERA across 4 projects.

Read Google reviews of Patel Mount →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Patel Mount: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Patel Mount

What is the possession date of Patel Mount?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Patel Mount in Chikanghar, Kalyan West, Thane is 30 April 2027 — 30 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Patel Mount?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Patel Mount's builder has filed on MahaRERA, the official one, is 30 April 2027, already 30 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Patel Mount extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2026". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Patel Mount?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Patel Mount in Chikanghar, Kalyan West, Thane is P51700048299.

Is Patel Mount registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount is registered as P51700048299 and its status is "Registered and active".

What is the construction status of Patel Mount?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building B1 is 62% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Patel Mount have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Patel Mount safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount is registered on MahaRERA as P51700048299, its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Patel Mount's possession date changes?

The latest dates are on Patel Mount's MahaRERA page (P51700048299). GharKundli's Kundli Watch sends a free WhatsApp update on Patel Mount every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Patel Mount have?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount has one building filed: Building B1 with 11 floors and 81 units.

How big is the land of Patel Mount?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount stands on 651 sq m of land (about 0.2 acres), with 4,699 sq m of sanctioned built-up area.

What is the track record of Patel Mount's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Group & has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 24 months late); 3 lapsed. 40 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Patel Mount?

Google Maps has reviews of Patel Mount written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Patel Mount?

Patel Mount by Patel Group & Co is in Chikanghar, Kalyan West, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700048299, per GharKundli's check of MahaRERA records.

How many homes are in Patel Mount?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount has 69 homes in 1 tower registered on MahaRERA, and 32% of them are sold or booked.

When was Patel Mount registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Patel Mount was registered on MahaRERA on 26 December 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Patel Mount?

No court cases are listed for Patel Mount on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Patel Mount?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Patel Group & Co, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 582 projects in Kalyan (421301) →

Other projects by Patel Group & Co

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.