Patel Colossus - Phase III
by Patel Group & Co · Birla College, Thane
Possession date of Patel Colossus - Phase III: 30 December 2023. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700009981. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about Patel Colossus - Phase III?
GharKundli’s full report on Patel Colossus - Phase III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Patel Colossus Phase 1P51700010242 · possession 30 Dec 2022
- Patel Colossus Phase IIP51700008709 · possession 30 Dec 2023
- MahaRERA registration
- P51700009981
- Status
- Lapsed (registration period ended)
- Builder
- Patel Group & Co
- Location
- Birla College, Thane · 421301
- Project type
- Others
- Registered on
- 23 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2023
- Homes
- 104
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Patel Colossus - Phase III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower A4 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Patel Colossus - Phase III every month.
Patel Colossus - Phase III: buildings, flats and land, as filed on MahaRERA
- Buildings: Tower A4 (31 floors)
- Land: 19,141 sq m (about 4.7 acres) · sanctioned built-up 62,506 sq m · recreational space 1,355 sq m
- Boundaries filed include: 30 mts wide Murbad Road, 6 mts wide Layout Road
The builder’s record and reviews
Patel Group & has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 24 months late); 3 lapsed. 40 complaints on MahaRERA across 4 projects.
Read Google reviews of Patel Colossus - Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Patel Colossus - Phase III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Patel Colossus - Phase III
What is the possession date of Patel Colossus - Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Patel Colossus - Phase III in Birla College, Thane is 30 December 2023. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Patel Colossus - Phase III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Patel Colossus - Phase III's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Patel Colossus - Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Patel Colossus - Phase III in Birla College, Thane is P51700009981.
Is Patel Colossus - Phase III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III is registered as P51700009981 and its status is "Lapsed (registration period ended)".
What is the construction status of Patel Colossus - Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Tower A4 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Patel Colossus - Phase III have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Patel Colossus - Phase III safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III is registered on MahaRERA as P51700009981, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Patel Colossus - Phase III have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Patel Colossus Phase 1 (P51700010242, possession 30 Dec 2022); Patel Colossus Phase II (P51700008709, possession 30 Dec 2023). Check that your agreement names the registration of your own wing.
How can I get updates if Patel Colossus - Phase III's possession date changes?
The latest dates are on Patel Colossus - Phase III's MahaRERA page (P51700009981). GharKundli's Kundli Watch sends a free WhatsApp update on Patel Colossus - Phase III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Patel Colossus - Phase III have?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III has one building filed: Tower A4 with 31 floors.
How big is the land of Patel Colossus - Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III stands on 19,141 sq m of land (about 4.7 acres), with 62,506 sq m of sanctioned built-up area and 1,355 sq m of recreational open space.
What is the track record of Patel Colossus - Phase III's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Group & has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 24 months late); 3 lapsed. 40 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Patel Colossus - Phase III?
Google Maps has reviews of Patel Colossus - Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Patel Colossus - Phase III?
Patel Colossus - Phase III by Patel Group & Co is in Birla College, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700009981, per GharKundli's check of MahaRERA records. Its boundaries filed there include 30 mts wide Murbad Road, 6 mts wide Layout Road.
How many homes are in Patel Colossus - Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III has 104 homes in 1 tower registered on MahaRERA.
When was Patel Colossus - Phase III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel Colossus - Phase III was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Patel Colossus - Phase III?
2 court cases are listed for Patel Colossus - Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Patel Colossus - Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Patel Group & Co, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Patel Colossus - Phase III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kalyan
- Patel Colossus Phase II
- Royal Hills
- MAJESTY HEIGHTS
- Mangeshi Dhara
- VIDHI IMPRESSION
- Balaji Govind
- OM TRIMURTI DARSHAN
- SWAMI ELITE
Other projects by Patel Group & Co
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.