Baliram Tare Residency

by TARE GROUP BUILDERS AND DEVELOPERS · Chinchpada Gaon, Thane 421306

What’s in the report? →

Possession date of Baliram Tare Residency (MahaRERA P51700047951): 30 April 2029, moved from 31 December 2025 (36 months later). It has 56 homes, 68% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700047951, and currently active. Its completion date has moved from December 2025 to April 2029: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700047951, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Baliram Tare Residency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Baliram Tare Residency has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA29052621158)

    Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Baliram Tare Residency’s extension records on MahaRERA (P51700047951), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Baliram Tare Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700047951
Status
Registered and active
Builder
TARE GROUP BUILDERS AND DEVELOPERS
Location
Chinchpada Gaon, Thane · 421306
Project type
Residential / Group Housing
Registered on
2 Dec 2022
Completion date at registration
December 2025
Latest completion date
April 2029
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
56
Sold or booked
68%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Baliram Tare Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Baliram Tare Residency - 1100%100%100%100%
Baliram Tare Residency -20%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Baliram Tare Residency - 1: covers 8 floors
  • Baliram Tare Residency -2: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Baliram Tare Residency every 1–2 months.

Baliram Tare Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: Baliram Tare Residency - 1 (8 floors, 42 units) · Baliram Tare Residency -2 (3 floors, 14 units)
  • Car parking: 13 covered
  • Land: 1,900 sq m (about 0.5 acres) · sanctioned built-up 3,278 sq m
  • Land, as filed: S. No. 1, H. No. 3/2
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Baliram Tare Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Baliram Tare Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Baliram Tare Residency

What is the possession date of Baliram Tare Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Baliram Tare Residency in Chinchpada Gaon, Thane is 30 April 2029 — 36 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Baliram Tare Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Baliram Tare Residency's builder has filed on MahaRERA, the official one, is 30 April 2029, already 36 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Baliram Tare Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Baliram Tare Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Baliram Tare Residency in Chinchpada Gaon, Thane is P51700047951.

Is Baliram Tare Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency is registered as P51700047951 and its status is "Registered and active".

What is the current construction status of Baliram Tare Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Baliram Tare Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Baliram Tare Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency is registered on MahaRERA as P51700047951, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Baliram Tare Residency?

Baliram Tare Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Baliram Tare Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Baliram Tare Residency: gharkundli.com/tools/property-cost-calculator

Has Baliram Tare Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Baliram Tare Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Baliram Tare Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Baliram Tare Residency's possession date changes?

The latest dates are on Baliram Tare Residency's MahaRERA page (P51700047951). GharKundli's Kundli Watch sends a free WhatsApp update on Baliram Tare Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Baliram Tare Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency has 2 buildings filed: Baliram Tare Residency - 1 with 8 floors and 42 units; Baliram Tare Residency -2 with 3 floors and 14 units.

How much parking does Baliram Tare Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 13 covered car parking spaces for Baliram Tare Residency.

How big is the land of Baliram Tare Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency stands on 1,900 sq m of land (about 0.5 acres), with 3,278 sq m of sanctioned built-up area.

What are the reviews of Baliram Tare Residency?

Google Maps has reviews of Baliram Tare Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Baliram Tare Residency?

Baliram Tare Residency by TARE GROUP BUILDERS AND DEVELOPERS is in Chinchpada Gaon, Thane, pincode 421306, Maharashtra, and is registered on MahaRERA as P51700047951, per GharKundli's check of MahaRERA records. Its land is filed as S. No. 1, H. No. 3/2. GharKundli lists all 270 MahaRERA projects in Kalyan East (421306).

How many flats are in Baliram Tare Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency has 56 homes in 2 towers registered on MahaRERA, and 68% of them are sold or booked.

When was Baliram Tare Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Baliram Tare Residency was registered on MahaRERA on 2 December 2022. GharKundli did not find a title report on the land on file there.

Does Baliram Tare Residency have any legal issues or court cases?

No court cases are listed for Baliram Tare Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Baliram Tare Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TARE GROUP BUILDERS AND DEVELOPERS.

All projects with possession due in 2029 in Thane →

Other projects in Ambarnath

All 270 projects in Kalyan East (421306) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.