Renuka CHS
by NEELPADMA CONSTRUCTIONS · Dombivli, Thane 421201Also near Vishnunagar, Manpada
What’s in the report? →Possession date of Renuka CHS (MahaRERA P51700050607): 30 April 2027, moved from 31 December 2024 (24 months later). It has 8 homes, 33% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050607, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700050607, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Renuka CHS?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Renuka CHS has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025625)
Reason the builder gave MahaRERA:
“We previously secured approval for the construction up to the seventh floor however, there has been a delay in obtaining authorization for the eighth floor from the local authority, KDMC. Consequently, this has resulted in a setback for the…” Read the full reason
“We previously secured approval for the construction up to the seventh floor however, there has been a delay in obtaining authorization for the eighth floor from the local authority, KDMC. Consequently, this has resulted in a setback for the project. We hereby respectfully request an extension of one year, until 31/12/2025, to enable the completion of the project and to ensure that we can provide possession to the members as planned, thereby preventing any undue hardship due to this delay. We have obtained 100% consent from all members involved. Additionally, we have included the necessary d…”31 December 2026
Extended at the builder's request (MahaRERA application EA02012619244)
Reason the builder gave MahaRERA:
“The project experienced significant delays beyond the originally declared completion period, attributable to uncontrollable external factors such as 1 Monsoon disruptions that halted site access and material deliveries (Municipal work was n…” Read the full reason
“The project experienced significant delays beyond the originally declared completion period, attributable to uncontrollable external factors such as 1 Monsoon disruptions that halted site access and material deliveries (Municipal work was near site) 2 Acute shortages of critical construction materials (e.g., cement, steel) and skilled/unskilled labor unable to commute progress These ‘force majeure’ events necessitated formal extensions, with mitigation steps like alternate sourcing and temporary site shelters already implemented. All corrective steps and directions taken to assure early com…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Renuka CHS’s extension records on MahaRERA (P51700050607), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Renuka CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050607
- Status
- Registered and active
- Builder
- NEELPADMA CONSTRUCTIONS
- Location
- Dombivli, Thane · 421201
- Project type
- Residential / Group Housing
- Registered on
- 21 Apr 2023
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 8
- Sold or booked
- 33%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Renuka CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RENUKA CHS | 100% | 100% | 65% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- RENUKA CHS: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Renuka CHS every 1–2 months.
Renuka CHS: buildings, flats and land, as filed on MahaRERA
- Buildings: RENUKA CHS (5 floors, 8 units)
- Car parking: 5 covered, 4 open
- Land: 468 sq m (about 0.1 acres) · sanctioned built-up 468 sq m
- Boundaries filed include: VARDLAXMI SOCIETY
- Land, as filed: 4806,4807
- Map: Get directions
The builder’s record and reviews
Neelpadma Associates (a group of 8 linked companies) has 12 projects on MahaRERA since 2019, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 18 months late); 3 lapsed. No complaints on MahaRERA.
Read Google reviews of Renuka CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Renuka CHS: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Renuka CHS
What is the possession date of Renuka CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Renuka CHS in Dombivli, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Renuka CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Renuka CHS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Renuka CHS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "We previously secured approval for the construction up to the seventh floor however, there has been a delay in obtaining authorization for the eighth floor from the local authority, KDMC. Consequently, this has resulted in a setback for the project. We hereby respectfully request an extension of one year, until 31/12/2025, to enable the completion of the project and to ensure that we can provide possession to the members as planned, thereby preventing any undue hardship due to this delay. We have obtained 100% consent from all members involved. Additionally, we have included the necessary d…"; to 31 December 2026, giving the reason "The project experienced significant delays beyond the originally declared completion period, attributable to uncontrollable external factors such as 1 Monsoon disruptions that halted site access and material deliveries (Municipal work was near site) 2 Acute shortages of critical construction materials (e.g., cement, steel) and skilled/unskilled labor unable to commute progress These ‘force majeure’ events necessitated formal extensions, with mitigation steps like alternate sourcing and temporary site shelters already implemented. All corrective steps and directions taken to assure early com…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Renuka CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Renuka CHS in Dombivli, Thane is P51700050607.
Is Renuka CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS is registered as P51700050607 and its status is "Registered and active".
What is the current construction status of Renuka CHS? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RENUKA CHS is 100% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does Renuka CHS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Renuka CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS is registered on MahaRERA as P51700050607, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Renuka CHS?
Renuka CHS is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Renuka CHS?
For a flat in Renuka CHS (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Renuka CHS received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Renuka CHS uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Renuka CHS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Renuka CHS's possession date changes?
The latest dates are on Renuka CHS's MahaRERA page (P51700050607). GharKundli's Kundli Watch sends a free WhatsApp update on Renuka CHS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Renuka CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS has one building filed: RENUKA CHS with 5 floors and 8 units.
How much parking does Renuka CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 5 covered and 4 open car parking spaces for Renuka CHS.
How big is the land of Renuka CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS stands on 468 sq m of land (about 0.1 acres), with 468 sq m of sanctioned built-up area.
What is the track record of Renuka CHS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Associates (a group of 8 linked companies) has 12 projects on MahaRERA since 2019, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 18 months late); 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Renuka CHS?
Google Maps has reviews of Renuka CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Renuka CHS?
Renuka CHS by NEELPADMA CONSTRUCTIONS is in Dombivli, Thane, pincode 421201 (near Vishnunagar, Manpada), Maharashtra, and is registered on MahaRERA as P51700050607, per GharKundli's check of MahaRERA records. Its boundaries filed there include VARDLAXMI SOCIETY. Its land is filed as 4806,4807. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Renuka CHS, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS has 8 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.
When was Renuka CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Renuka CHS was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.
Does Renuka CHS have any legal issues or court cases?
No court cases are listed for Renuka CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Renuka CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEELPADMA CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of Renuka CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Tilaknagar (421201)
- Swami Elite
- Mangeshi Dazzle II
- Sagar Kunj Highland
- Om Trimurti Darshan
- Balaji Govind
- Vastu Heritage
- Mangeshi Dhara
- Nav Samidha Co-op HSG Soc LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.