Omkar Trishan Enclave
by OMKAR ENTERPRISES · Umbarde Village, Kalyan West, Thane 421301Registered on MahaRERA as “TRISHAN ENCLAVE”
What’s in the report? →Possession date of Omkar Trishan Enclave (MahaRERA P51700052828): 30 April 2029, moved from 25 December 2025 (36 months later). It has 28 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700052828, and currently active. Its completion date has moved from December 2025 to April 2029: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700052828, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Omkar Trishan Enclave?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Omkar Trishan Enclave has moved
25 December 2025
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EA11122518626)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, We, Omkar Enterprises, the Promoter of the Real Estate Project titled “TRISHAN ENCLAVE”, bearing MahaRERA Registration No. P51700052828, situated at Survey No. 134, Hissa No. 5, Kalyan, District Thane – 421301, respectf…” Read the full reason
“Respected Sir/Madam, We, Omkar Enterprises, the Promoter of the Real Estate Project titled “TRISHAN ENCLAVE”, bearing MahaRERA Registration No. P51700052828, situated at Survey No. 134, Hissa No. 5, Kalyan, District Thane – 421301, respectfully submit this application seeking extension of project registration under Section 6 of the Real Estate (Regulation & Development) Act, 2016. 1. Reason for Extension We request an extension of the project registration till 31/12/2028, due to the following genuine and unavoidable circumstances: a) Project is still under construction The development work…”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Omkar Trishan Enclave’s extension records on MahaRERA (P51700052828), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Omkar Trishan Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700052828
- Status
- Registered and active
- Builder
- OMKAR ENTERPRISES
- Location
- Umbarde Village, Kalyan West, Thane · 421301
- Project type
- Others
- Registered on
- 5 Oct 2023
- Completion date at registration
- December 2025
- Latest completion date
- April 2029
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 28
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of Omkar Trishan Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TRISHAN ENCLAVE | 100% | 100% | 65% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- TRISHAN ENCLAVE: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Omkar Trishan Enclave every 1–2 months.
Omkar Trishan Enclave: buildings, flats and land, as filed on MahaRERA
- Buildings: TRISHAN ENCLAVE (8 floors, 35 units)
- Car parking: 1 covered, 5 open
- Land: 1,270 sq m (about 0.3 acres) · sanctioned built-up 1,677 sq m
- Land, as filed: SURVEY NO. 134 HISSA NO. 5
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Omkar Trishan Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Omkar Trishan Enclave: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Omkar Trishan Enclave
What is the possession date of Omkar Trishan Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Omkar Trishan Enclave in Umbarde Village, Kalyan West, Thane is 30 April 2029 — 36 months later than 25 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Omkar Trishan Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Omkar Trishan Enclave's builder has filed on MahaRERA, the official one, is 30 April 2029, already 36 months later than the 25 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Omkar Trishan Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "Respected Sir/Madam, We, Omkar Enterprises, the Promoter of the Real Estate Project titled “TRISHAN ENCLAVE”, bearing MahaRERA Registration No. P51700052828, situated at Survey No. 134, Hissa No. 5, Kalyan, District Thane – 421301, respectfully submit this application seeking extension of project registration under Section 6 of the Real Estate (Regulation & Development) Act, 2016. 1. Reason for Extension We request an extension of the project registration till 31/12/2028, due to the following genuine and unavoidable circumstances: a) Project is still under construction The development work…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Omkar Trishan Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Omkar Trishan Enclave in Umbarde Village, Kalyan West, Thane is P51700052828.
Is Omkar Trishan Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave is registered as P51700052828 and its status is "Registered and active".
What is the current construction status of Omkar Trishan Enclave? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TRISHAN ENCLAVE is 100% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does Omkar Trishan Enclave have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Omkar Trishan Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave is registered on MahaRERA as P51700052828, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Omkar Trishan Enclave?
Omkar Trishan Enclave is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Omkar Trishan Enclave?
For a flat in Omkar Trishan Enclave (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Omkar Trishan Enclave received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Omkar Trishan Enclave uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Omkar Trishan Enclave was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Omkar Trishan Enclave's possession date changes?
The latest dates are on Omkar Trishan Enclave's MahaRERA page (P51700052828). GharKundli's Kundli Watch sends a free WhatsApp update on Omkar Trishan Enclave every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Omkar Trishan Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave has one building filed: TRISHAN ENCLAVE with 8 floors and 35 units.
How much parking does Omkar Trishan Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 5 open car parking spaces for Omkar Trishan Enclave.
How big is the land of Omkar Trishan Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave stands on 1,270 sq m of land (about 0.3 acres), with 1,677 sq m of sanctioned built-up area.
What are the reviews of Omkar Trishan Enclave?
Google Maps has reviews of Omkar Trishan Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Omkar Trishan Enclave?
Omkar Trishan Enclave by OMKAR ENTERPRISES is in Umbarde Village, Kalyan West, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700052828, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO. 134 HISSA NO. 5. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Omkar Trishan Enclave, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave has 28 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Omkar Trishan Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Omkar Trishan Enclave was registered on MahaRERA on 5 October 2023. GharKundli did not find a title report on the land on file there.
Does Omkar Trishan Enclave have any legal issues or court cases?
No court cases are listed for Omkar Trishan Enclave on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Omkar Trishan Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OMKAR ENTERPRISES, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Omkar Trishan Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Other projects by OMKAR ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.