Venkateshwara Heights
by SHREE VENKATESHWARA DEVELOPERS · Badlapur, Thane 421503Also near Kulgaon
What’s in the report? →Possession date of Venkateshwara Heights (MahaRERA P51700053286): 30 October 2026, moved from 31 December 2025 (6 months later), and it has already passed. It has 12 homes, 83% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053286, and currently active. Its completion date has moved from December 2025 to October 2026: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700053286, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Venkateshwara Heights?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Venkateshwara Heights has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA31012619657)
Reason the builder gave MahaRERA: “Due to delay in construction and applied for extension only for more 6 months.”
30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Venkateshwara Heights’s extension records on MahaRERA (P51700053286), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Venkateshwara Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700053286
- Status
- Registered and active
- Builder
- SHREE VENKATESHWARA DEVELOPERS
- Location
- Badlapur, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2023
- Completion date at registration
- December 2025
- Latest completion date
- October 2026
- Delay so far
- 6 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Sold or booked
- 83%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Venkateshwara Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VENKATESHWARA HEIGHTS | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- VENKATESHWARA HEIGHTS: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Venkateshwara Heights every 1–2 months.
Venkateshwara Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: VENKATESHWARA HEIGHTS (6 floors, 12 units)
- Land: 300 sq m (about 0.1 acres) · sanctioned built-up 671 sq m
- Land, as filed: SURVEY NO 58 HISSA NO 1/1/Y PLOT NO 1
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Venkateshwara Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Venkateshwara Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Venkateshwara Heights
What is the possession date of Venkateshwara Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Venkateshwara Heights in Badlapur, Thane is 30 October 2026 — 6 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Venkateshwara Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Venkateshwara Heights's builder has filed on MahaRERA, the official one, is 30 October 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Venkateshwara Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Due to delay in construction and applied for extension only for more 6 months.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Venkateshwara Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Venkateshwara Heights in Badlapur, Thane is P51700053286.
Is Venkateshwara Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights is registered as P51700053286 and its status is "Registered and active".
What is the current construction status of Venkateshwara Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VENKATESHWARA HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Venkateshwara Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Venkateshwara Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights is registered on MahaRERA as P51700053286, its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Venkateshwara Heights?
Venkateshwara Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Venkateshwara Heights?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Venkateshwara Heights: gharkundli.com/tools/property-cost-calculator
Has Venkateshwara Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Venkateshwara Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Venkateshwara Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Venkateshwara Heights's possession date changes?
The latest dates are on Venkateshwara Heights's MahaRERA page (P51700053286). GharKundli's Kundli Watch sends a free WhatsApp update on Venkateshwara Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Venkateshwara Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights has one building filed: VENKATESHWARA HEIGHTS with 6 floors and 12 units.
How big is the land of Venkateshwara Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights stands on 300 sq m of land (about 0.1 acres), with 671 sq m of sanctioned built-up area.
What are the reviews of Venkateshwara Heights?
Google Maps has reviews of Venkateshwara Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Venkateshwara Heights?
Venkateshwara Heights by SHREE VENKATESHWARA DEVELOPERS is in Badlapur, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700053286, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 58 HISSA NO 1/1/Y PLOT NO 1. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Venkateshwara Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights has 12 homes in 1 tower registered on MahaRERA, and 83% of them are sold or booked.
When was Venkateshwara Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Heights was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Does Venkateshwara Heights have any legal issues or court cases?
No court cases are listed for Venkateshwara Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Venkateshwara Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE VENKATESHWARA DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Venkateshwara Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kulgaon (421503)
- Sai Universe
- Mery Villa CHSL
- Mahavir Heritage
- Infinity Meadows
- Gokul Heights
- Shiv Tirth B Wing
- Prabhu Darshan Co-operative Housing Society Limited
- Dattatray Residency
Other projects by SHREE VENKATESHWARA DEVELOPERS