Venkateshwara Ganesh Residency
by SHREE VENKATESHWARA DEVELOPERS · Ghatkopar East, Mumbai 400077Registered on MahaRERA as “GANESH RESIDENCY”
What’s in the report? →Possession date of Venkateshwara Ganesh Residency (MahaRERA P51800021114): 25 November 2026, moved from 25 July 2023 (36 months later), and it has already passed. It has 38 homes (1 BHK and 2 BHK, 380–696 sq ft carpet), 21% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800021114, and currently active. Its completion date has moved from July 2023 to November 2026: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800021114, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (November 2026) has passed.
What do you want to know about Venkateshwara Ganesh Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Venkateshwara Ganesh Residency has moved
25 July 2023
Completion date given when the project was registered
25 July 2026
Extended at the builder's request (MahaRERA application EXT51800017773)
Reason the builder gave MahaRERA:
“. We were going through the tough phase as DHFL NBFC bank has stopped Financing and all our planning came to hold in 2021 and we were not having funds to complete the project. Then we somehow manage to Settle DHFL in June 2022 and Took the…” Read the full reason
“. We were going through the tough phase as DHFL NBFC bank has stopped Financing and all our planning came to hold in 2021 and we were not having funds to complete the project. Then we somehow manage to Settle DHFL in June 2022 and Took the project ahead with alternate funding and Selling inventory. Now from last 6 months we have again Started the project with Contractor on Long Credit basis and now we think we will be able to complete the project in next 15 months if everything goes as per the plan.”25 November 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Venkateshwara Ganesh Residency’s extension records on MahaRERA (P51800021114), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Venkateshwara Ganesh Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800021114
- Status
- Registered and active
- Builder
- SHREE VENKATESHWARA DEVELOPERS
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 31 May 2019
- Completion date at registration
- July 2023
- Latest completion date
- November 2026
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 38
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Venkateshwara Ganesh Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GANESH RESIDENCY | 100% | 92% | 44% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GANESH RESIDENCY: covers Full CC
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Venkateshwara Ganesh Residency every 1–2 months.
Venkateshwara Ganesh Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 610 – 696 | 26 |
| 1 BHK | 380 – 426 | 12 |
- Buildings: GANESH RESIDENCY (16 floors, 38 units)
- Land: 847 sq m (about 0.2 acres) · sanctioned built-up 835 sq m · recreational space 1,017 sq m
- Boundaries filed include: BHOJRAJ DAMJI PATEL MARG
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Venkateshwara Ganesh Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Venkateshwara Ganesh Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Venkateshwara Ganesh Residency
What is the possession date of Venkateshwara Ganesh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Venkateshwara Ganesh Residency in Ghatkopar East, Mumbai is 25 November 2026 — 36 months later than 25 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Venkateshwara Ganesh Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Venkateshwara Ganesh Residency's builder has filed on MahaRERA, the official one, is 25 November 2026, already 36 months later than the 25 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Venkateshwara Ganesh Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency's builder applied to MahaRERA to extend the completion date once: to 25 July 2026, giving the reason ". We were going through the tough phase as DHFL NBFC bank has stopped Financing and all our planning came to hold in 2021 and we were not having funds to complete the project. Then we somehow manage to Settle DHFL in June 2022 and Took the project ahead with alternate funding and Selling inventory. Now from last 6 months we have again Started the project with Contractor on Long Credit basis and now we think we will be able to complete the project in next 15 months if everything goes as per the plan.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Venkateshwara Ganesh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Venkateshwara Ganesh Residency in Ghatkopar East, Mumbai is P51800021114.
Is Venkateshwara Ganesh Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency is registered as P51800021114 and its status is "Registered and active".
What is the current construction status of Venkateshwara Ganesh Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GANESH RESIDENCY is 92% done and internal work 44%. GharKundli's full report compares construction progress with the deadline.
Does Venkateshwara Ganesh Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Venkateshwara Ganesh Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency is registered on MahaRERA as P51800021114, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Venkateshwara Ganesh Residency?
Venkateshwara Ganesh Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Venkateshwara Ganesh Residency are 380 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Venkateshwara Ganesh Residency?
For a flat in Venkateshwara Ganesh Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Venkateshwara Ganesh Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency is still under construction, with 25 November 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Venkateshwara Ganesh Residency a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency is a redevelopment: 24 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Venkateshwara Ganesh Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Venkateshwara Ganesh Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Venkateshwara Ganesh Residency's possession date changes?
The latest dates are on Venkateshwara Ganesh Residency's MahaRERA page (P51800021114). GharKundli's Kundli Watch sends a free WhatsApp update on Venkateshwara Ganesh Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Venkateshwara Ganesh Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency has one building filed: GANESH RESIDENCY with 16 floors and 38 units.
What are the flat sizes (carpet area) in Venkateshwara Ganesh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Venkateshwara Ganesh Residency: 2 BHK: 610 to 696 sq ft carpet (26 homes); 1 BHK: 380 to 426 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Venkateshwara Ganesh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency stands on 847 sq m of land (about 0.2 acres), with 835 sq m of sanctioned built-up area and 1,017 sq m of recreational open space.
What are the reviews of Venkateshwara Ganesh Residency?
Google Maps has reviews of Venkateshwara Ganesh Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Venkateshwara Ganesh Residency?
Venkateshwara Ganesh Residency by SHREE VENKATESHWARA DEVELOPERS is in Ghatkopar East, Mumbai, pincode 400077, Maharashtra, and is registered on MahaRERA as P51800021114, per GharKundli's check of MahaRERA records. Its boundaries filed there include BHOJRAJ DAMJI PATEL MARG. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).
How many flats are in Venkateshwara Ganesh Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency has 38 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was Venkateshwara Ganesh Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Venkateshwara Ganesh Residency was registered on MahaRERA on 31 May 2019. GharKundli did not find a title report on the land on file there.
Does Venkateshwara Ganesh Residency have any legal issues or court cases?
No court cases are listed for Venkateshwara Ganesh Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Venkateshwara Ganesh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE VENKATESHWARA DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Venkateshwara Ganesh Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Ghatkopar East (400077)
- RDK Belvedere
- Poonam Celeste
- Senghani Paradise
- Alag Ananta
- Rushabh Kiran
- Vikas Ornate
- Shree Matru Krupa
- Orient Odyssey
Other projects by SHREE VENKATESHWARA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.