by GLS INFRASTRUCTURES · Dombivli East, Thane 421201Also near Vishnunagar, ManpadaRegistered on MahaRERA as “SAI DREAM ONE”

What’s in the report? →

Possession date of GLS Sai Dream One (MahaRERA P51700052958): 31 December 2027, moved from 31 December 2025 (24 months later). It has 110 homes, 54% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700052958, and currently active.

Source: MahaRERA website — records for P51700052958, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about GLS Sai Dream One?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of GLS Sai Dream One has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51700028347)

    Reason the builder gave MahaRERA: “Project has been revised and No. of floors has been increased from 6 to 11 with consent of allotees. Accordingly we require revised timeline for the project. Consent of the allotees is attached herewith”

Source: GLS Sai Dream One’s extension records on MahaRERA (P51700052958), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GLS Sai Dream One

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700052958
Status
Registered and active
Builder
GLS INFRASTRUCTURES
Location
Dombivli East, Thane · 421201
Project type
Residential / Group Housing
Registered on
6 Oct 2023
Completion date at registration
December 2025
Latest completion date
December 2027
Delay so far
24 months
Homes
110
Sold or booked
54%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GLS Sai Dream One, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sunflower100%30%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GLS Sai Dream One every 1–2 months.

GLS Sai Dream One: buildings, flats and land, as filed on MahaRERA

  • Buildings: Sunflower (12 floors)
  • Land: 2,610 sq m (about 0.6 acres) · sanctioned built-up 6,774 sq m
  • Land, as filed: S No.88, H No 6 & 7
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GLS Sai Dream One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GLS Sai Dream One: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about GLS Sai Dream One

What is the possession date of GLS Sai Dream One?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GLS Sai Dream One in Dombivli East, Thane is 31 December 2027 — 24 months later than 31 December 2025, the date given at registration.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for GLS Sai Dream One?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GLS Sai Dream One's builder has filed on MahaRERA, the official one, is 31 December 2027, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GLS Sai Dream One extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Project has been revised and No. of floors has been increased from 6 to 11 with consent of allotees. Accordingly we require revised timeline for the project. Consent of the allotees is attached herewith".

What is the RERA number of GLS Sai Dream One?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GLS Sai Dream One in Dombivli East, Thane is P51700052958.

Is GLS Sai Dream One registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One is registered as P51700052958 and its status is "Registered and active".

What is the current construction status of GLS Sai Dream One? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sunflower is 30% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does GLS Sai Dream One have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GLS Sai Dream One safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One is registered on MahaRERA as P51700052958, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in GLS Sai Dream One?

GLS Sai Dream One is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in GLS Sai Dream One?

For a flat in GLS Sai Dream One (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has GLS Sai Dream One received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has GLS Sai Dream One uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for GLS Sai Dream One was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if GLS Sai Dream One's possession date changes?

The latest dates are on GLS Sai Dream One's MahaRERA page (P51700052958). GharKundli's Kundli Watch sends a free WhatsApp update on GLS Sai Dream One every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GLS Sai Dream One have?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One has one building filed: Sunflower with 12 floors.

How big is the land of GLS Sai Dream One?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One stands on 2,610 sq m of land (about 0.6 acres), with 6,774 sq m of sanctioned built-up area.

What are the reviews of GLS Sai Dream One?

Google Maps has reviews of GLS Sai Dream One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of GLS Sai Dream One?

GLS Sai Dream One by GLS INFRASTRUCTURES is in Dombivli East, Thane, pincode 421201 (near Vishnunagar, Manpada), Maharashtra, and is registered on MahaRERA as P51700052958, per GharKundli's check of MahaRERA records. Its land is filed as S No.88, H No 6 & 7. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in GLS Sai Dream One, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One has 110 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.

When was GLS Sai Dream One registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GLS Sai Dream One was registered on MahaRERA on 6 October 2023. GharKundli did not find a title report on the land on file there.

Does GLS Sai Dream One have any legal issues or court cases?

No court cases are listed for GLS Sai Dream One on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of GLS Sai Dream One?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GLS INFRASTRUCTURES.

All projects with possession due in 2027 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.