Swaminarayan City Phase 1D
by Swaminarayan Life Space LLP · Mothagon, Mauje, Thakurli, ThaneAlso near Dombivli West, Shastri Nagar, Manpada
Possession date of Swaminarayan City Phase 1D: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055644, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Swaminarayan City Phase 1D?
How the possession date of Swaminarayan City Phase 1D has moved
31 December 2030
Completion date given when the project was registered
30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Swaminarayan City Phase 1D’s extension records on MahaRERA (P51700055644), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Swaminarayan City Phase 1D
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Swaminarayan City Phase 1AP51700019326 · possession 30 Apr 2030
- Swaminarayan City Phase 1BP51700031749 · possession 30 Apr 2029
- Swaminarayan City Phase 1CP51700049570 · possession 30 Apr 2030
- Swaminarayan City Phase IP51700018305 · possession 30 Apr 2028
- Swaminarayan City Phase IIPR1331012601194 · possession 30 Apr 2034
- MahaRERA registration
- P51700055644
- Status
- Registered and active
- Builder
- Swaminarayan Life Space LLP
- Location
- Mothagon, Mauje, Thakurli, Thane · 421202
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2024
- Completion date at registration
- December 2030
- Latest completion date
- April 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 272
- Sold or booked
- 68%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Swaminarayan City Phase 1D, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Calista | 100% | 25% | 2% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Calista: covers 27 floors
Latest CC order on MahaRERA: dated 07/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swaminarayan City Phase 1D every month.
Swaminarayan City Phase 1D: buildings, flats and land, as filed on MahaRERA
- Buildings: Calista (27 floors, 272 units)
- Car parking: 152 covered
- Land: 4,577 sq m (about 1.1 acres) · sanctioned built-up 12,805 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Swaminarayan Life Space (a group of 5 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, all within the promised date; 8 still being built, none past the promised date yet. 5 complaints on MahaRERA across 3 projects.
Read Google reviews of Swaminarayan City Phase 1D →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Swaminarayan City Phase 1D: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Swaminarayan City Phase 1D
What is the possession date of Swaminarayan City Phase 1D?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Swaminarayan City Phase 1D in Mothagon, Mauje, Thakurli, Thane is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Swaminarayan City Phase 1D?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Swaminarayan City Phase 1D's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Swaminarayan City Phase 1D?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Swaminarayan City Phase 1D in Mothagon, Mauje, Thakurli, Thane is P51700055644.
Is Swaminarayan City Phase 1D registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D is registered as P51700055644 and its status is "Registered and active".
What is the construction status of Swaminarayan City Phase 1D?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Calista is 25% done and internal work 2%. GharKundli's full report compares construction progress with the deadline.
Does Swaminarayan City Phase 1D have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Swaminarayan City Phase 1D safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D is registered on MahaRERA as P51700055644, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Swaminarayan City Phase 1D have other wings or phases?
Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Swaminarayan City Phase 1A (P51700019326, possession 30 Apr 2030); Swaminarayan City Phase 1B (P51700031749, possession 30 Apr 2029); Swaminarayan City Phase 1C (P51700049570, possession 30 Apr 2030); Swaminarayan City Phase I (P51700018305, possession 30 Apr 2028); Swaminarayan City Phase II (PR1331012601194, possession 30 Apr 2034). Check that your agreement names the registration of your own wing.
How can I get updates if Swaminarayan City Phase 1D's possession date changes?
The latest dates are on Swaminarayan City Phase 1D's MahaRERA page (P51700055644). GharKundli's Kundli Watch sends a free WhatsApp update on Swaminarayan City Phase 1D every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Swaminarayan City Phase 1D have?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D has one building filed: Calista with 27 floors and 272 units.
How much parking does Swaminarayan City Phase 1D have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 152 covered car parking spaces for Swaminarayan City Phase 1D.
How big is the land of Swaminarayan City Phase 1D?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D stands on 4,577 sq m of land (about 1.1 acres), with 12,805 sq m of sanctioned built-up area.
What is the track record of Swaminarayan City Phase 1D's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan Life Space (a group of 5 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, all within the promised date; 8 still being built, none past the promised date yet. 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Swaminarayan City Phase 1D?
Google Maps has reviews of Swaminarayan City Phase 1D written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Swaminarayan City Phase 1D?
Swaminarayan City Phase 1D by Swaminarayan Life Space LLP is in Mothagon, Mauje, Thakurli, Thane (pincode 421202), near Dombivli West, Shastri Nagar, Manpada, Maharashtra, and is registered on MahaRERA as P51700055644, per GharKundli's check of MahaRERA records.
How many homes are in Swaminarayan City Phase 1D?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D has 272 homes in 1 tower registered on MahaRERA, and 68% of them are sold or booked.
When was Swaminarayan City Phase 1D registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Swaminarayan City Phase 1D was registered on MahaRERA on 5 April 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Swaminarayan City Phase 1D?
No court cases are listed for Swaminarayan City Phase 1D on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Swaminarayan City Phase 1D?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Swaminarayan Life Space LLP, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Swaminarayan City Phase 1D
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in Kalyan
- Swaminarayan City Phase 1C
- MAJESTY HEIGHTS
- Royal Hills
- VIDHI IMPRESSION
- Mangeshi Dhara
- SWAMI ELITE
- Balaji Govind
- OM TRIMURTI DARSHAN
Other projects by Swaminarayan Life Space LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.