The Nature
by Uma Infratech · Titawala, ThaneAlso near Manda
Possession date of The Nature: 30 October 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700077155, and currently active. Its completion date is now October 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about The Nature?
How the possession date of The Nature has moved
30 June 2030
Completion date given when the project was registered
30 October 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: The Nature’s extension records on MahaRERA (P51700077155), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Nature
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the October 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700077155
- Status
- Registered and active
- Builder
- Uma Infratech
- Location
- Titawala, Thane · 421605
- Project type
- Others
- Registered on
- 29 Jul 2024
- Completion date at registration
- June 2030
- Latest completion date
- October 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 325
- Sold or booked
- 32%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of The Nature, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 100% | 64.25% | 0% |
| Wing B | 100% | 100% | 30.25% | 0% |
| Wing D EWS | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A: covers 15 (G + 14)
- Wing B: covers 15 (G + 14)
- Wing D EWS: covers 8 (G + 7)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Nature every month.
The Nature: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A (15 floors, 124 units) · Wing B (15 floors, 207 units) · Wing D EWS (8 floors, 35 units)
- Land: 9,992 sq m (about 2.5 acres) · sanctioned built-up 19,851 sq m · recreational space 1,009 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Nature →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Nature: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Nature
What is the possession date of The Nature?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Nature in Titawala, Thane is 30 October 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for The Nature?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Nature's builder has filed on MahaRERA, the official one, is 30 October 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of The Nature?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Nature in Titawala, Thane is P51700077155.
Is The Nature registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature is registered as P51700077155 and its status is "Registered and active".
What is the construction status of The Nature?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does The Nature have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is The Nature safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature is registered on MahaRERA as P51700077155, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if The Nature's possession date changes?
The latest dates are on The Nature's MahaRERA page (P51700077155). GharKundli's Kundli Watch sends a free WhatsApp update on The Nature every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Nature have?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature has 3 buildings filed: Wing A with 15 floors and 124 units; Wing B with 15 floors and 207 units; Wing D EWS with 8 floors and 35 units.
How big is the land of The Nature?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature stands on 9,992 sq m of land (about 2.5 acres), with 19,851 sq m of sanctioned built-up area and 1,009 sq m of recreational open space.
Where can I read reviews of The Nature?
Google Maps has reviews of The Nature written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Nature?
The Nature by Uma Infratech is in Titawala, Thane (pincode 421605), near Manda, Maharashtra, and is registered on MahaRERA as P51700077155, per GharKundli's check of MahaRERA records.
How many homes are in The Nature?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature has 325 homes in 3 towers registered on MahaRERA, and 32% of them are sold or booked.
When was The Nature registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Nature was registered on MahaRERA on 29 July 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on The Nature?
No court cases are listed for The Nature on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of The Nature?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Uma Infratech, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of The Nature
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in pincode 421605
- CHARMS CITY PHASE II
- MARATHE TOWER
- GANPATI HEIGHTS
- SHREE GAJANAN PLAZA
- SARNOBAT RESIDENCY
- PITAMBARE TOWER
- MANGALMURTI HEIGHTS
- SAI VRINDAVAN
Other projects by Uma Infratech
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.