Lodha IL Palazzo, Hanging Gardens Palava
by Lodha Developers Limited · Khoni, Thane 421204Also near Manpada, VishnunagarRegistered on MahaRERA as “IL Palazzo, Hanging Gardens Palava”
What’s in the report? →Possession date of Lodha IL Palazzo, Hanging Gardens Palava (MahaRERA P51700077356): 31 July 2030, moved from 31 March 2029 (12 months later). It has 122 homes, 57% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700077356, and currently active. Its completion date has moved from March 2029 to July 2030: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700077356, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Lodha IL Palazzo, Hanging Gardens Palava?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Lodha IL Palazzo, Hanging Gardens Palava has moved
31 March 2029
Completion date given when the project was registered
31 March 2030
Extended at the builder's request (MahaRERA application EXT51700027404)
Reason the builder gave MahaRERA:
“Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now ,at the time of extension request no allotees in this…” Read the full reason
“Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now ,at the time of extension request no allotees in this project.”31 July 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Lodha IL Palazzo, Hanging Gardens Palava’s extension records on MahaRERA (P51700077356), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lodha IL Palazzo, Hanging Gardens Palava
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the July 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700077356
- Status
- Registered and active
- Builder
- Lodha Developers Limited
- Location
- Khoni, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2024
- Completion date at registration
- March 2029
- Latest completion date
- July 2030
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 122
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Construction progress of Lodha IL Palazzo, Hanging Gardens Palava, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing B Z Cluster 6 Point 03 Sector F | 100% | 4% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing B Z Cluster 6 Point 03 Sector F: covers 37 floors
Latest CC order on MahaRERA: dated 17/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha IL Palazzo, Hanging Gardens Palava every 1–2 months.
Lodha IL Palazzo, Hanging Gardens Palava: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing B Z Cluster 6 Point 03 Sector F (37 floors, 122 units)
- Car parking: 102 covered
- Land: 3,532 sq m (about 0.9 acres) · sanctioned built-up 27,823 sq m · recreational space 353 sq m
- Land, as filed: 35/4A Part,35/6 Part,35/7 Part,35/9 Part,172/1 Part,172/2 Part,172/3 Part,173 Part
- Map: Get directions
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 602 complaints on MahaRERA across 163 projects.
Read Google reviews of Lodha IL Palazzo, Hanging Gardens Palava →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lodha IL Palazzo, Hanging Gardens Palava: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Lodha IL Palazzo, Hanging Gardens Palava
What is the possession date of Lodha IL Palazzo, Hanging Gardens Palava?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha IL Palazzo, Hanging Gardens Palava in Khoni, Thane is 31 July 2030 — 12 months later than 31 March 2029, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Lodha IL Palazzo, Hanging Gardens Palava?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha IL Palazzo, Hanging Gardens Palava's builder has filed on MahaRERA, the official one, is 31 July 2030, already 12 months later than the 31 March 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lodha IL Palazzo, Hanging Gardens Palava extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava's builder applied to MahaRERA to extend the completion date once: to 31 March 2030, giving the reason "Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now ,at the time of extension request no allotees in this project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Lodha IL Palazzo, Hanging Gardens Palava?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha IL Palazzo, Hanging Gardens Palava in Khoni, Thane is P51700077356.
Is Lodha IL Palazzo, Hanging Gardens Palava registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava is registered as P51700077356 and its status is "Registered and active".
What is the current construction status of Lodha IL Palazzo, Hanging Gardens Palava? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing B Z Cluster 6 Point 03 Sector F is 4% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Lodha IL Palazzo, Hanging Gardens Palava have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Lodha IL Palazzo, Hanging Gardens Palava safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava is registered on MahaRERA as P51700077356, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Lodha IL Palazzo, Hanging Gardens Palava?
Lodha IL Palazzo, Hanging Gardens Palava is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Lodha IL Palazzo, Hanging Gardens Palava?
For a flat in Lodha IL Palazzo, Hanging Gardens Palava (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Lodha IL Palazzo, Hanging Gardens Palava received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava is still under construction, with 31 July 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Lodha IL Palazzo, Hanging Gardens Palava uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha IL Palazzo, Hanging Gardens Palava was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Lodha IL Palazzo, Hanging Gardens Palava's possession date changes?
The latest dates are on Lodha IL Palazzo, Hanging Gardens Palava's MahaRERA page (P51700077356). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha IL Palazzo, Hanging Gardens Palava every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lodha IL Palazzo, Hanging Gardens Palava have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava has one building filed: Wing B Z Cluster 6 Point 03 Sector F with 37 floors and 122 units.
How much parking does Lodha IL Palazzo, Hanging Gardens Palava have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 102 covered car parking spaces for Lodha IL Palazzo, Hanging Gardens Palava.
How big is the land of Lodha IL Palazzo, Hanging Gardens Palava?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava stands on 3,532 sq m of land (about 0.9 acres), with 27,823 sq m of sanctioned built-up area and 353 sq m of recreational open space.
What is the track record of Lodha IL Palazzo, Hanging Gardens Palava's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Lodha IL Palazzo, Hanging Gardens Palava?
Google Maps has reviews of Lodha IL Palazzo, Hanging Gardens Palava written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Lodha IL Palazzo, Hanging Gardens Palava?
Lodha IL Palazzo, Hanging Gardens Palava by Lodha Developers Limited is in Khoni, Thane, pincode 421204 (near Manpada, Vishnunagar), Maharashtra, and is registered on MahaRERA as P51700077356, per GharKundli's check of MahaRERA records. Its land is filed as 35/4A Part,35/6 Part,35/7 Part,35/9 Part,172/1 Part,172/2 Part,172/3 Part,173 Part. GharKundli lists all 252 MahaRERA projects in Manpada (421204).
How many flats are in Lodha IL Palazzo, Hanging Gardens Palava, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava has 122 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was Lodha IL Palazzo, Hanging Gardens Palava registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha IL Palazzo, Hanging Gardens Palava was registered on MahaRERA on 9 August 2024. GharKundli did not find a title report on the land on file there.
Does Lodha IL Palazzo, Hanging Gardens Palava have any legal issues or court cases?
1 court case is listed for Lodha IL Palazzo, Hanging Gardens Palava on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Lodha IL Palazzo, Hanging Gardens Palava?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Lodha IL Palazzo, Hanging Gardens Palava
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Manpada (421204)
- Runwal Gardens Phase 4 Bldg No. 33-34
- Shree Krishna Heights
- Shanti Luxuria
- Palava Fresca J-K
- Chanakya C wing
- Chanakya A wing
- Yesu Anand Heights
- Arista Skyline
Other projects by Lodha Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.