What’s in the report? →Possession date of Bhagirathi Smruti (MahaRERA P51700079436): 30 April 2028. It has 50 homes, 90% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700079436, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700079436, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Bhagirathi Smruti?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Bhagirathi Smruti has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Bhagirathi Smruti’s extension records on MahaRERA (P51700079436), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhagirathi Smruti
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700079436
- Status
- Registered and active
- Builder
- Sahil Vinayak Patil
- Location
- Chole, Dombivali East, Thane · 421201
- Project type
- Others
- Registered on
- 6 Mar 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 50
- Sold or booked
- 90%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Bhagirathi Smruti, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Krupa Saidham CHS Ltd | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Krupa Saidham CHS Ltd: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhagirathi Smruti every 1–2 months.
Bhagirathi Smruti: buildings, flats and land, as filed on MahaRERA
- Buildings: Krupa Saidham CHS Ltd (9 floors, 57 units)
- Land: 710 sq m (about 0.2 acres) · sanctioned built-up 2,812 sq m
- Land, as filed: C.T.S. No. 456, 457, 461, 462, 641 to 650, 662/C
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Bhagirathi Smruti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhagirathi Smruti: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Bhagirathi Smruti
What is the possession date of Bhagirathi Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhagirathi Smruti in Chole, Dombivali East, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Bhagirathi Smruti?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhagirathi Smruti's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Bhagirathi Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhagirathi Smruti in Chole, Dombivali East, Thane is P51700079436.
Is Bhagirathi Smruti registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti is registered as P51700079436 and its status is "Registered and active".
What is the current construction status of Bhagirathi Smruti? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Krupa Saidham CHS Ltd is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Bhagirathi Smruti have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Bhagirathi Smruti safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti is registered on MahaRERA as P51700079436, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Bhagirathi Smruti?
Bhagirathi Smruti is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Bhagirathi Smruti?
For a flat in Bhagirathi Smruti (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Bhagirathi Smruti received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Bhagirathi Smruti a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti is a redevelopment: 30 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Bhagirathi Smruti uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Bhagirathi Smruti was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Bhagirathi Smruti's possession date changes?
The latest dates are on Bhagirathi Smruti's MahaRERA page (P51700079436). GharKundli's Kundli Watch sends a free WhatsApp update on Bhagirathi Smruti every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhagirathi Smruti have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti has one building filed: Krupa Saidham CHS Ltd with 9 floors and 57 units.
How big is the land of Bhagirathi Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti stands on 710 sq m of land (about 0.2 acres), with 2,812 sq m of sanctioned built-up area.
What are the reviews of Bhagirathi Smruti?
Google Maps has reviews of Bhagirathi Smruti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Bhagirathi Smruti?
Bhagirathi Smruti by Sahil Vinayak Patil is in Chole, Dombivali East, Thane, pincode 421201 (near Dombivli East, Kalyan, Sagaon), Maharashtra, and is registered on MahaRERA as P51700079436, per GharKundli's check of MahaRERA records. Its land is filed as C.T.S. No. 456, 457, 461, 462, 641 to 650, 662/C. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Bhagirathi Smruti, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti has 50 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.
When was Bhagirathi Smruti registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagirathi Smruti was registered on MahaRERA on 6 March 2025. GharKundli did not find a title report on the land on file there.
Does Bhagirathi Smruti have any legal issues or court cases?
No court cases are listed for Bhagirathi Smruti on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Bhagirathi Smruti?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sahil Vinayak Patil.
Check it yourself on MahaRERA
- How to check the possession date of Bhagirathi Smruti
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.