The Vaidiki Crown

by SHREE JARI MARI REALTY LLP · Katemanevali, Thane 421306

What’s in the report? →

Possession date of The Vaidiki Crown (MahaRERA PR1330002500732): 30 April 2030. It has 20 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1330002500732, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1330002500732, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Vaidiki Crown?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Vaidiki Crown has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Vaidiki Crown’s extension records on MahaRERA (PR1330002500732), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Vaidiki Crown

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1330002500732
Status
Registered and active
Builder
SHREE JARI MARI REALTY LLP
Location
Katemanevali, Thane · 421306
Project type
Residential / Group Housing
Registered on
10 Sep 2025
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of The Vaidiki Crown, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
THE VAIDIKI CROWN100%10%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • THE VAIDIKI CROWN: covers 4 floors

Latest CC order on MahaRERA: dated 07/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Vaidiki Crown every 1–2 months.

The Vaidiki Crown: buildings, flats and land, as filed on MahaRERA

  • Buildings: THE VAIDIKI CROWN (4 floors, 34 units)
  • Car parking: 22 open
  • Land: 1,882 sq m (about 0.5 acres) · sanctioned built-up 2,200 sq m
  • Map: Get directions

The builder’s record and reviews

Shree Jari Mari Developers (a group of 4 linked companies) has 6 projects on MahaRERA since 2022, this one included. Of the 6 GharKundli has checked: 5 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of The Vaidiki Crown →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Vaidiki Crown: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Vaidiki Crown

What is the possession date of The Vaidiki Crown?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Vaidiki Crown in Katemanevali, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for The Vaidiki Crown?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Vaidiki Crown's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of The Vaidiki Crown?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Vaidiki Crown in Katemanevali, Thane is PR1330002500732.

Is The Vaidiki Crown registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown is registered as PR1330002500732 and its status is "Registered and active".

What is the current construction status of The Vaidiki Crown? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown's status on MahaRERA is "Registered and active". As filed by the builder, slab work on THE VAIDIKI CROWN is 10% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does The Vaidiki Crown have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The Vaidiki Crown safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown is registered on MahaRERA as PR1330002500732, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Vaidiki Crown?

The Vaidiki Crown is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Vaidiki Crown?

For a flat in The Vaidiki Crown (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The Vaidiki Crown received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is The Vaidiki Crown a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown is a redevelopment: 9 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has The Vaidiki Crown uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Vaidiki Crown was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Vaidiki Crown's possession date changes?

The latest dates are on The Vaidiki Crown's MahaRERA page (PR1330002500732). GharKundli's Kundli Watch sends a free WhatsApp update on The Vaidiki Crown every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Vaidiki Crown have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown has one building filed: THE VAIDIKI CROWN with 4 floors and 34 units.

How much parking does The Vaidiki Crown have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 open car parking spaces for The Vaidiki Crown.

How big is the land of The Vaidiki Crown?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown stands on 1,882 sq m of land (about 0.5 acres), with 2,200 sq m of sanctioned built-up area.

What is the track record of The Vaidiki Crown's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Jari Mari Developers (a group of 4 linked companies) has 6 projects on MahaRERA since 2022, this one included. Of the 6 GharKundli has checked: 5 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Vaidiki Crown?

Google Maps has reviews of The Vaidiki Crown written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Vaidiki Crown?

The Vaidiki Crown by SHREE JARI MARI REALTY LLP is in Katemanevali, Thane, pincode 421306, Maharashtra, and is registered on MahaRERA as PR1330002500732, per GharKundli's check of MahaRERA records. GharKundli lists all 270 MahaRERA projects in Kalyan East (421306).

How many flats are in The Vaidiki Crown, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown has 20 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was The Vaidiki Crown registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Vaidiki Crown was registered on MahaRERA on 10 September 2025. GharKundli did not find a title report on the land on file there.

Does The Vaidiki Crown have any legal issues or court cases?

No court cases are listed for The Vaidiki Crown on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The Vaidiki Crown?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE JARI MARI REALTY LLP.

All projects with possession due in 2030 in Thane →

Other projects in Kalyan East (421306)

All 270 projects in Kalyan East (421306) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.