by AARTI BUILDERS · Khadavali, Thane 421605Also near Manda

What’s in the report? →

Possession date of Aarti Park (MahaRERA P51700080241): 30 April 2029. It has 48 homes, 1% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700080241, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700080241, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aarti Park?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aarti Park has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Aarti Park’s extension records on MahaRERA (P51700080241), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aarti Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700080241
Status
Registered and active
Builder
AARTI BUILDERS
Location
Khadavali, Thane · 421605
Project type
Others
Registered on
13 May 2025
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Sold or booked
1%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aarti Park, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING AND B WING0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aarti Park every 1–2 months.

Aarti Park: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING AND B WING (9 floors)
  • Land: 1,295 sq m (about 0.3 acres) · sanctioned built-up 3,056 sq m
  • Boundaries filed include: PRAKASH KIDS SCHOOL, FALEGAON ROAD
  • Land, as filed: SURVEY NO 27/B PLOT NO 7 AND SURVEY NO 27/B PLOT NO 8
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Aarti Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aarti Park: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aarti Park

What is the possession date of Aarti Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aarti Park in Khadavali, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Aarti Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aarti Park's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aarti Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aarti Park in Khadavali, Thane is P51700080241.

Is Aarti Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park is registered as P51700080241 and its status is "Registered and active".

What is the current construction status of Aarti Park? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A WING AND B WING is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Aarti Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aarti Park safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park is registered on MahaRERA as P51700080241, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aarti Park?

Aarti Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aarti Park?

For a flat in Aarti Park (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Aarti Park received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aarti Park uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aarti Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aarti Park's possession date changes?

The latest dates are on Aarti Park's MahaRERA page (P51700080241). GharKundli's Kundli Watch sends a free WhatsApp update on Aarti Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aarti Park have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park has one building filed: A WING AND B WING with 9 floors.

How big is the land of Aarti Park?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park stands on 1,295 sq m of land (about 0.3 acres), with 3,056 sq m of sanctioned built-up area.

What are the reviews of Aarti Park?

Google Maps has reviews of Aarti Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aarti Park?

Aarti Park by AARTI BUILDERS is in Khadavali, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700080241, per GharKundli's check of MahaRERA records. Its boundaries filed there include PRAKASH KIDS SCHOOL, FALEGAON ROAD. Its land is filed as SURVEY NO 27/B PLOT NO 7 AND SURVEY NO 27/B PLOT NO 8. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Aarti Park, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park has 48 homes in 1 tower registered on MahaRERA, and 1% of them are sold or booked.

When was Aarti Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aarti Park was registered on MahaRERA on 13 May 2025. GharKundli did not find a title report on the land on file there.

Does Aarti Park have any legal issues or court cases?

No court cases are listed for Aarti Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aarti Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AARTI BUILDERS.

All projects with possession due in 2029 in Thane →

Other projects in Titwala (421605)

All 174 projects in Titwala (421605) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.