by TOP FLOOR REALTY LLP · Wagle I.E., Thane 400604Also near Panchpakhadi, Naupada, CharaiRegistered on MahaRERA as “ONE ARTHASYA”

What’s in the report? →

Possession date of TOP One Arthasya (MahaRERA PC1330002500892): 30 April 2032, moved from 31 December 2030 (12 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PC1330002500892, and currently active. Its completion date has moved from December 2030 to April 2032: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for PC1330002500892, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about TOP One Arthasya?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of TOP One Arthasya has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 31 December 2031

    Extended at the builder's request (MahaRERA application EA23062621478)

    Reason the builder gave MahaRERA: “At time of registration, we mistakenly mentioned incorrect date and now we wish to correct the same via correction application. Please note that there are zero sold/booked inventory in the project.”
  3. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: TOP One Arthasya’s extension records on MahaRERA (PC1330002500892), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TOP One Arthasya

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PC1330002500892
Status
Registered and active
Builder
TOP FLOOR REALTY LLP
Location
Wagle I.E., Thane · 400604
Project type
Commercial
Registered on
22 Sep 2025
Completion date at registration
December 2030
Latest completion date
April 2032
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of TOP One Arthasya, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A (ELEMENTS)0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • A (ELEMENTS): covers BASEMENT + GROUND + 30 UPPER FLOOR

Latest CC order on MahaRERA: dated 01/04/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TOP One Arthasya every 1–2 months.

TOP One Arthasya: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TOP One Arthasya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TOP One Arthasya: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about TOP One Arthasya

What is the possession date of TOP One Arthasya?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TOP One Arthasya in Wagle I.E., Thane is 30 April 2032 — 12 months later than 31 December 2030, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for TOP One Arthasya?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TOP One Arthasya's builder has filed on MahaRERA, the official one, is 30 April 2032, already 12 months later than the 31 December 2030 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TOP One Arthasya extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "At time of registration, we mistakenly mentioned incorrect date and now we wish to correct the same via correction application. Please note that there are zero sold/booked inventory in the project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of TOP One Arthasya?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TOP One Arthasya in Wagle I.E., Thane is PC1330002500892.

Is TOP One Arthasya registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya is registered as PC1330002500892 and its status is "Registered and active".

What is the current construction status of TOP One Arthasya? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A (ELEMENTS) is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does TOP One Arthasya have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is TOP One Arthasya safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya is registered on MahaRERA as PC1330002500892, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in TOP One Arthasya?

TOP One Arthasya is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in TOP One Arthasya?

For a flat in TOP One Arthasya (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has TOP One Arthasya received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya is still under construction, with 30 April 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has TOP One Arthasya uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for TOP One Arthasya was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if TOP One Arthasya's possession date changes?

The latest dates are on TOP One Arthasya's MahaRERA page (PC1330002500892). GharKundli's Kundli Watch sends a free WhatsApp update on TOP One Arthasya every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TOP One Arthasya have?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya has one building filed: A (ELEMENTS) with 32 floors and 575 units.

How much parking does TOP One Arthasya have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 872 covered car parking spaces for TOP One Arthasya.

How big is the land of TOP One Arthasya?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya stands on 10,209 sq m of land (about 2.5 acres), with 55,087 sq m of sanctioned built-up area.

What are the reviews of TOP One Arthasya?

Google Maps has reviews of TOP One Arthasya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of TOP One Arthasya?

TOP One Arthasya by TOP FLOOR REALTY LLP is in Wagle I.E., Thane, pincode 400604 (near Panchpakhadi, Naupada, Charai), Maharashtra, and is registered on MahaRERA as PC1330002500892, per GharKundli's check of MahaRERA records. Its boundaries filed there include ESTATE ROAD. GharKundli lists all 87 MahaRERA projects in Wagle Estate (400604).

How many flats are in TOP One Arthasya, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya has 0 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was TOP One Arthasya registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TOP One Arthasya was registered on MahaRERA on 22 September 2025. GharKundli did not find a title report on the land on file there.

Does TOP One Arthasya have any legal issues or court cases?

No court cases are listed for TOP One Arthasya on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of TOP One Arthasya?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TOP FLOOR REALTY LLP.

Other projects in Wagle Estate (400604)

All 87 projects in Wagle Estate (400604) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.