Neuleaf Techd
by Neuleaf Lifespace Developers LLP · Bhugaon, Pune 412115
What’s in the report? →Possession date of Neuleaf Techd (MahaRERA P52100000181): 30 October 2033, moved from 30 June 2021 (144 months later). It has 162 homes, 89% sold or booked. 6 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100000181, and currently active. Its completion date has moved from June 2021 to October 2033: 144 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100000181, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Neuleaf Techd?
6 complaints MahaRERA par. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Neuleaf Techd has moved
30 June 2021
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT52100010241)
Reason the builder gave MahaRERA:
“The reasons for extension in date of completion are as follows:- 1. The promoter was suffering through huge financial losses as there was no abundant booking done by customers. Due to such financial constrained there was slow progress as wo…” Read the full reason
“The reasons for extension in date of completion are as follows:- 1. The promoter was suffering through huge financial losses as there was no abundant booking done by customers. Due to such financial constrained there was slow progress as work site. 2. Further, It is a fact that there was nationwide lockdown due to Covid-19 pandemic situation. Due to such pandemic situation, promoter could not progress the work at site. 3. Due to such situation there were further financial constraints on the Promoter. There have been bookings in the said project. However, Promoter seeks extension of date of…”30 June 2033
Extended at the builder's request (MahaRERA application EXT52100016680)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 68% allottees for purpose of extension of RERA registration period of the said project.”30 October 2033
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Neuleaf Techd’s extension records on MahaRERA (P52100000181), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Neuleaf Techd
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the October 2033 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100000181
- Status
- Registered and active
- Builder
- Neuleaf Lifespace Developers LLP
- Location
- Bhugaon, Pune · 412115
- Project type
- Residential / Group Housing
- Registered on
- 10 Jul 2017
- Completion date at registration
- June 2021
- Latest completion date
- October 2033
- Delay so far
- 144 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 162
- Sold or booked
- 89%
- Towers
- 4
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Neuleaf Techd, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C | 100% | 100% | 100% | 100% |
| B | 100% | 95% | 80% | 0% |
| A | 0% | 0% | 0% | 0% |
| D | 0% | 70% | 20% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- C: covers 17 floors
- B: covers 18 floors
- A: covers 6 floors
- D: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neuleaf Techd every 1–2 months.
Neuleaf Techd: buildings, flats and land, as filed on MahaRERA
- Buildings: C (17 floors, 112 units) · B (18 floors, 50 units) · A (6 floors, 14 units) · D (6 floors, 31 units)
- Car parking: 57 covered
- Land: 16,180 sq m (about 4.0 acres) · sanctioned built-up 10,576 sq m · recreational space 1,488 sq m
- Boundaries filed include: Pune Mulashi Road
- Land, as filed: Parde No 4 At Post Bhugaon Tal Mulashi Dist Pune
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Neuleaf Lifespace Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 24 months late). 7 complaints on MahaRERA across 2 projects.
Read Google reviews of Neuleaf Techd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Neuleaf Techd: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Neuleaf Techd
What is the possession date of Neuleaf Techd?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neuleaf Techd in Bhugaon, Pune is 30 October 2033 — 144 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 144 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Neuleaf Techd?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Neuleaf Techd's builder has filed on MahaRERA, the official one, is 30 October 2033, already 144 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Neuleaf Techd extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2023, giving the reason "The reasons for extension in date of completion are as follows:- 1. The promoter was suffering through huge financial losses as there was no abundant booking done by customers. Due to such financial constrained there was slow progress as work site. 2. Further, It is a fact that there was nationwide lockdown due to Covid-19 pandemic situation. Due to such pandemic situation, promoter could not progress the work at site. 3. Due to such situation there were further financial constraints on the Promoter. There have been bookings in the said project. However, Promoter seeks extension of date of…"; to 30 June 2033, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 68% allottees for purpose of extension of RERA registration period of the said project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Neuleaf Techd?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neuleaf Techd in Bhugaon, Pune is P52100000181.
Is Neuleaf Techd registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd is registered as P52100000181 and its status is "Registered and active".
What is the current construction status of Neuleaf Techd? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Neuleaf Techd have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
6 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is Neuleaf Techd safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd is registered on MahaRERA as P52100000181, its completion date has moved 144 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Neuleaf Techd?
Neuleaf Techd is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Neuleaf Techd?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Neuleaf Techd: gharkundli.com/tools/property-cost-calculator
Has Neuleaf Techd received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd is still under construction, with 30 October 2033 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Neuleaf Techd uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Neuleaf Techd was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Neuleaf Techd's possession date changes?
The latest dates are on Neuleaf Techd's MahaRERA page (P52100000181). GharKundli's Kundli Watch sends a free WhatsApp update on Neuleaf Techd every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Neuleaf Techd have?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd has 4 buildings filed: C with 17 floors and 112 units; B with 18 floors and 50 units; A with 6 floors and 14 units; D with 6 floors and 31 units.
How much parking does Neuleaf Techd have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 57 covered car parking spaces for Neuleaf Techd.
How big is the land of Neuleaf Techd?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd stands on 16,180 sq m of land (about 4.0 acres), with 10,576 sq m of sanctioned built-up area and 1,488 sq m of recreational open space.
What is the track record of Neuleaf Techd's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Lifespace Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 24 months late). 7 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Neuleaf Techd?
Google Maps has reviews of Neuleaf Techd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Neuleaf Techd?
Neuleaf Techd by Neuleaf Lifespace Developers LLP is in Bhugaon, Pune, pincode 412115, Maharashtra, and is registered on MahaRERA as P52100000181, per GharKundli's check of MahaRERA records. Its boundaries filed there include Pune Mulashi Road. Its land is filed as Parde No 4 At Post Bhugaon Tal Mulashi Dist Pune. GharKundli lists all 237 MahaRERA projects in Pirangut (412115).
How many flats are in Neuleaf Techd, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd has 162 homes in 4 towers registered on MahaRERA, and 89% of them are sold or booked.
When was Neuleaf Techd registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neuleaf Techd was registered on MahaRERA on 10 July 2017. GharKundli did not find a title report on the land on file there.
Does Neuleaf Techd have any legal issues or court cases?
No court cases are listed for Neuleaf Techd on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Neuleaf Techd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Neuleaf Lifespace Developers LLP.
Check it yourself on MahaRERA
- How to check the possession date of Neuleaf Techd
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pirangut (412115)
- Pre Eminence
- The Winds Phase-1, Sector 1B at Avian Valley
- Nakshatra Angan C Building
- Lotus Crest
- The Green Hill
- Mahindra Rivenza Phase 2
- Mahindra Rivenza Phase 1
- Nandanvan Park
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.