VIJAY ESTATE VAKAS PHASE - 1
by VIJAYGROUP HOUSING PRIVATE LIMITED · Village Vakas, Near Neral, Raigarh
Possession date of VIJAY ESTATE VAKAS PHASE - 1: 30 June 2024. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000000959. Status: Lapsed (registration period ended). 55 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2024) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about VIJAY ESTATE VAKAS PHASE - 1?
GharKundli’s full report on VIJAY ESTATE VAKAS PHASE - 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 55 complaints and 5 court cases, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000000959
- Status
- Lapsed (registration period ended)
- Builder
- VIJAYGROUP HOUSING PRIVATE LIMITED
- Location
- Village Vakas, Near Neral, Raigarh · 410101
- Project type
- Others
- Registered on
- 25 Jul 2017
- Completion date at registration
- June 2024
- Latest completion date
- June 2024
- Homes
- 1,892
- Towers
- 51
- Complaints on MahaRERA
- 55
- Court cases listed
- 5
- Title report on file
- Not found
Construction progress of VIJAY ESTATE VAKAS PHASE - 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NE 24 BUILDING NO 1 | 100% | 100% | 59% | 5% |
| NE 24 BUILDING NO 2 | 100% | 100% | 59% | 4% |
| NE 24 BUILDING NO 3 | 100% | 100% | 60% | 0% |
| NE 24 BUILDING NO 4 | 100% | 100% | 67% | 8% |
| NE 24 BUILDING NO 5 | 100% | 100% | 70% | 0% |
| NE 24 BUILDING NO 6 | 100% | 100% | 60% | 0% |
| NE 24 BUILDING NO 7 | 100% | 100% | 51% | 0% |
| NE 24 BUILDING NO 8 | 100% | 100% | 60% | 0% |
| NE 24 BUILDING NO 9 | 100% | 100% | 60% | 0% |
| NE 24 BUILDING NO 10 | 100% | 100% | 60% | 0% |
| SE 05 BUILDING NO 1 | 100% | 100% | 35% | 0% |
| SE 05 BUILDING NO 2 | 100% | 100% | 43% | 0% |
| SE 05 BUILDING NO 3 | 100% | 100% | 50% | 0% |
| SE 05 BUILDING NO 4 | 100% | 100% | 36% | 0% |
| SE 05 BUILDING NO 5 | 100% | 100% | 32% | 0% |
| SE 05 BUILDING NO 6 | 100% | 100% | 60% | 0% |
| SE 05 BUILDING NO 7 | 100% | 100% | 46% | 0% |
| SE 05 BUILDING NO 8 | 100% | 100% | 35% | 0% |
| SE 25 BUILDING NO 1 | 92% | 100% | 0% | 0% |
| SE 25 BUILDING NO 2 | 80% | 100% | 0% | 0% |
| SE 25 BUILDING NO 3 | 84% | 100% | 0% | 0% |
| SE 25 BUILDING NO 4 | 100% | 100% | 0% | 0% |
| SE 25 BUILDING NO 5 | 100% | 100% | 0% | 0% |
| SE 25 BUILDING NO 6 | 100% | 100% | 0% | 0% |
| SE 26 BUILDING NO 1 | 0% | 0% | 0% | 0% |
| SE 26 BUILDING NO 2 | 0% | 0% | 0% | 0% |
| SE 26 BUILDING NO 3 | 0% | 0% | 0% | 0% |
| SE 26 BUILDING NO 4 | 0% | 0% | 0% | 0% |
| SE 26 BUILDING NO 5 | 0% | 0% | 0% | 0% |
| SE 26 BUILDING NO 6 | 0% | 0% | 0% | 0% |
Showing 30 of 51 towers.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIJAY ESTATE VAKAS PHASE - 1 every month.
VIJAY ESTATE VAKAS PHASE - 1: buildings, flats and land, as filed on MahaRERA
- Buildings: NE 24 BUILDING NO 1 (5 floors) · NE 24 BUILDING NO 2 (5 floors) · NE 24 BUILDING NO 3 (5 floors) · NE 24 BUILDING NO 4 (5 floors) · NE 24 BUILDING NO 5 (5 floors) · NE 24 BUILDING NO 6 (5 floors) · NE 24 BUILDING NO 7 (5 floors) · NE 24 BUILDING NO 8 (5 floors) · and 22 more
- Land: 20,167 sq m (about 5.0 acres) · sanctioned built-up 72,492 sq m · recreational space 5,589 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VIJAY ESTATE VAKAS PHASE - 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VIJAY ESTATE VAKAS PHASE - 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VIJAY ESTATE VAKAS PHASE - 1
What is the possession date of VIJAY ESTATE VAKAS PHASE - 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VIJAY ESTATE VAKAS PHASE - 1 in Village Vakas, Near Neral, Raigarh is 30 June 2024. That date has already passed.
Is the builder's possession date different from the MahaRERA date for VIJAY ESTATE VAKAS PHASE - 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VIJAY ESTATE VAKAS PHASE - 1's builder has filed on MahaRERA, the official one, is 30 June 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of VIJAY ESTATE VAKAS PHASE - 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VIJAY ESTATE VAKAS PHASE - 1 in Village Vakas, Near Neral, Raigarh is P52000000959.
Is VIJAY ESTATE VAKAS PHASE - 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1 is registered as P52000000959 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of VIJAY ESTATE VAKAS PHASE - 1?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.
Does VIJAY ESTATE VAKAS PHASE - 1 have complaints on MahaRERA?
55 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VIJAY ESTATE VAKAS PHASE - 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1 is registered on MahaRERA as P52000000959, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 55 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VIJAY ESTATE VAKAS PHASE - 1's possession date changes?
The latest dates are on VIJAY ESTATE VAKAS PHASE - 1's MahaRERA page (P52000000959). GharKundli's Kundli Watch sends a free WhatsApp update on VIJAY ESTATE VAKAS PHASE - 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VIJAY ESTATE VAKAS PHASE - 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1 has 30 buildings filed: NE 24 BUILDING NO 1 with 5 floors; NE 24 BUILDING NO 2 with 5 floors; NE 24 BUILDING NO 3 with 5 floors; NE 24 BUILDING NO 4 with 5 floors; NE 24 BUILDING NO 5 with 5 floors; NE 24 BUILDING NO 6 with 5 floors; and 24 more.
How big is the land of VIJAY ESTATE VAKAS PHASE - 1?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1 stands on 20,167 sq m of land (about 5.0 acres), with 72,492 sq m of sanctioned built-up area and 5,589 sq m of recreational open space.
Where can I read reviews of VIJAY ESTATE VAKAS PHASE - 1?
Google Maps has reviews of VIJAY ESTATE VAKAS PHASE - 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 55 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VIJAY ESTATE VAKAS PHASE - 1?
VIJAY ESTATE VAKAS PHASE - 1 by VIJAYGROUP HOUSING PRIVATE LIMITED is in Village Vakas, Near Neral, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000000959, per GharKundli's check of MahaRERA records.
How many homes are in VIJAY ESTATE VAKAS PHASE - 1?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1 has 1,892 homes in 51 towers registered on MahaRERA.
When was VIJAY ESTATE VAKAS PHASE - 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VIJAY ESTATE VAKAS PHASE - 1 was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VIJAY ESTATE VAKAS PHASE - 1?
5 court cases are listed for VIJAY ESTATE VAKAS PHASE - 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of VIJAY ESTATE VAKAS PHASE - 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIJAYGROUP HOUSING PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of VIJAY ESTATE VAKAS PHASE - 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410101
- A Z LANDMARK
- VANSH HEIGHTS
- SWAMI AASHRAY
- MIRA RESIDENCY
- SIGNATURE PHASE 1
- ARYA RESIDENCY P1
- ARENA ONE
- MECCA AVENUE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.