by Vinayak Developers · Borivali West, MumbaiAlso near Borivali East, Rajendra Nagar, Dahisar East

Possession date of Jessika Chs.Ltd.: 30 June 2025, moved from 30 December 2020 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800011498. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about Jessika Chs.Ltd.?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Jessika Chs.Ltd. has moved

  1. 30 December 2020

    Completion date given when the project was registered

  2. 30 June 2021

    Extended at the builder's request (MahaRERA application EXT51800008953)

    Reason the builder gave MahaRERA: “Due to change MCGM policies, new DCR 2034 and covid pandemic”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800012084)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30 JUNE 2023”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800017056)

    Reason the builder gave MahaRERA: “WORK COMPLETION ON PROCESS”
  5. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024110)

    Reason the builder gave MahaRERA:
    “Initially, Jessika CHS Ltd. engaged a contractor for the construction of the project. However, due to severe delays and unsatisfactory performance, compounded by a significant fund crunch, the said contractor was unable to complete the cons…” Read the full reason“Initially, Jessika CHS Ltd. engaged a contractor for the construction of the project. However, due to severe delays and unsatisfactory performance, compounded by a significant fund crunch, the said contractor was unable to complete the construction work as agreed. This resulted in contractual disputes between Jessika CHS Ltd. and the said contractor, leading to prolonged litigation. The legal proceedings and subsequent termination of the contract delayed progress considerably, creating a substantial impact on the project timeline. To resume and accelerate construction, Jessika CHS Ltd. and…”

Source: Jessika Chs.Ltd.’s extension records on MahaRERA (P51800011498), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Jessika Chs.Ltd.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 1 court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011498
Status
Lapsed (registration period ended)
Builder
Vinayak Developers
Location
Borivali West, Mumbai · 400092
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2020
Latest completion date
June 2025
Delay so far
54 months
Homes
36
Towers
1
Complaints on MahaRERA
2
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
15

Construction progress of Jessika Chs.Ltd., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A and B100%50%50%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jessika Chs.Ltd. every month.

Jessika Chs.Ltd.: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A and B (10 floors)
  • Land: 804 sq m (about 0.2 acres) · sanctioned built-up 1,444 sq m · recreational space 434 sq m
  • Boundaries filed include: Padam Society, borivaly Railway Station, Park View Society, N R Karode Marg
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Jessika Chs.Ltd. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jessika Chs.Ltd.: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Jessika Chs.Ltd.

What is the possession date of Jessika Chs.Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jessika Chs.Ltd. in Borivali West, Mumbai is 30 June 2025 — 54 months later than 30 December 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Jessika Chs.Ltd.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jessika Chs.Ltd.'s builder has filed on MahaRERA, the official one, is 30 June 2025, already 54 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Jessika Chs.Ltd. extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd.'s builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2021, giving the reason "Due to change MCGM policies, new DCR 2034 and covid pandemic"; to 30 June 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30 JUNE 2023"; to 30 June 2024, giving the reason "WORK COMPLETION ON PROCESS"; to 30 June 2025, giving the reason "Initially, Jessika CHS Ltd. engaged a contractor for the construction of the project. However, due to severe delays and unsatisfactory performance, compounded by a significant fund crunch, the said contractor was unable to complete the construction work as agreed. This resulted in contractual disputes between Jessika CHS Ltd. and the said contractor, leading to prolonged litigation. The legal proceedings and subsequent termination of the contract delayed progress considerably, creating a substantial impact on the project timeline. To resume and accelerate construction, Jessika CHS Ltd. and…".

What is the RERA number of Jessika Chs.Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jessika Chs.Ltd. in Borivali West, Mumbai is P51800011498.

Is Jessika Chs.Ltd. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd. is registered as P51800011498 and its status is "Lapsed (registration period ended)".

What is the construction status of Jessika Chs.Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd.'s status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Wing A and B is 50% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Jessika Chs.Ltd. have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Jessika Chs.Ltd. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd. is registered on MahaRERA as P51800011498, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Jessika Chs.Ltd.'s possession date changes?

The latest dates are on Jessika Chs.Ltd.'s MahaRERA page (P51800011498). GharKundli's Kundli Watch sends a free WhatsApp update on Jessika Chs.Ltd. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Jessika Chs.Ltd. have?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd. has one building filed: Wing A and B with 10 floors.

How big is the land of Jessika Chs.Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd. stands on 804 sq m of land (about 0.2 acres), with 1,444 sq m of sanctioned built-up area and 434 sq m of recreational open space.

Where can I read reviews of Jessika Chs.Ltd.?

Google Maps has reviews of Jessika Chs.Ltd. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Jessika Chs.Ltd.?

Jessika Chs.Ltd. by Vinayak Developers is in Borivali West, Mumbai (pincode 400092), near Borivali East, Rajendra Nagar, Dahisar East, Maharashtra, and is registered on MahaRERA as P51800011498, per GharKundli's check of MahaRERA records. Its boundaries filed there include Padam Society, borivaly Railway Station, Park View Society, N R Karode Marg.

How many homes are in Jessika Chs.Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd. has 36 homes in 1 tower registered on MahaRERA.

When was Jessika Chs.Ltd. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jessika Chs.Ltd. was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Jessika Chs.Ltd.?

1 court case is listed for Jessika Chs.Ltd. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Jessika Chs.Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vinayak Developers, which has 15 other projects registered on MahaRERA.

Other projects in pincode 400092

All 362 projects in Borivali West (400092) →

Other projects by Vinayak Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.