POOJA NAGAR
by SHREE LAXMI NARAYAN DEVELOPERS · Neral West, Raigarh
Possession date of POOJA NAGAR: 31 March 2025, moved from 30 December 2021 (39 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000004776. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (March 2025) has passed.
What do you want to know about POOJA NAGAR?
How the possession date of POOJA NAGAR has moved
30 December 2021
Completion date given when the project was registered
29 December 2022
Extended at the builder's request (MahaRERA application EXT52000010904)
Reason the builder gave MahaRERA: “Due to Scarcity of Labour and Material in corona pandemics our project has been delayed therefor we kindly request you to accept our extension .”
31 March 2025
Extended at the builder's request (MahaRERA application EXT52000013856)
Reason the builder gave MahaRERA: “Due to the covid and not sufficient funds arranged.”
Source: POOJA NAGAR’s extension records on MahaRERA (P52000004776), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on POOJA NAGAR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000004776
- Status
- Lapsed (registration period ended)
- Builder
- SHREE LAXMI NARAYAN DEVELOPERS
- Location
- Neral West, Raigarh · 410201
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- March 2025
- Delay so far
- 39 months
- Homes
- 176
- Towers
- 8
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of POOJA NAGAR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING F | 100% | 100% | 25% | 0% |
| WING G | 0% | 0% | 0% | 0% |
| WING H | 0% | 0% | 0% | 0% |
| WING A | 100% | 100% | 100% | 0% |
| WING B | 100% | 100% | 100% | 0% |
| WING C | 100% | 100% | 78% | 0% |
| WING D | 100% | 100% | 40% | 0% |
| WING E | 100% | 100% | 25% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on POOJA NAGAR every month.
POOJA NAGAR: buildings, flats and land, as filed on MahaRERA
- Buildings: WING F (6 floors) · WING G (6 floors) · WING H (6 floors) · WING A (6 floors) · WING B (6 floors) · WING C (6 floors) · WING D (6 floors) · WING E (6 floors)
- Land: 5,500 sq m (about 1.4 acres) · sanctioned built-up 6,976 sq m · recreational space 1,011 sq m
The builder’s record and reviews
Mukund Builders & Contractors (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of POOJA NAGAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
POOJA NAGAR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about POOJA NAGAR
What is the possession date of POOJA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for POOJA NAGAR in Neral West, Raigarh is 31 March 2025 — 39 months later than 30 December 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for POOJA NAGAR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date POOJA NAGAR's builder has filed on MahaRERA, the official one, is 31 March 2025, already 39 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of POOJA NAGAR extended?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2022, giving the reason "Due to Scarcity of Labour and Material in corona pandemics our project has been delayed therefor we kindly request you to accept our extension ."; to 31 March 2025, giving the reason "Due to the covid and not sufficient funds arranged.".
What is the RERA number of POOJA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of POOJA NAGAR in Neral West, Raigarh is P52000004776.
Is POOJA NAGAR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR is registered as P52000004776 and its status is "Lapsed (registration period ended)".
What is the construction status of POOJA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does POOJA NAGAR have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is POOJA NAGAR safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR is registered on MahaRERA as P52000004776, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 39 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if POOJA NAGAR's possession date changes?
The latest dates are on POOJA NAGAR's MahaRERA page (P52000004776). GharKundli's Kundli Watch sends a free WhatsApp update on POOJA NAGAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does POOJA NAGAR have?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR has 8 buildings filed: WING F with 6 floors; WING G with 6 floors; WING H with 6 floors; WING A with 6 floors; WING B with 6 floors; WING C with 6 floors; and 2 more.
How big is the land of POOJA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR stands on 5,500 sq m of land (about 1.4 acres), with 6,976 sq m of sanctioned built-up area and 1,011 sq m of recreational open space.
What is the track record of POOJA NAGAR's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mukund Builders & Contractors (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of POOJA NAGAR?
Google Maps has reviews of POOJA NAGAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is POOJA NAGAR?
POOJA NAGAR by SHREE LAXMI NARAYAN DEVELOPERS is in Neral West, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000004776, per GharKundli's check of MahaRERA records.
How many homes are in POOJA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR has 176 homes in 8 towers registered on MahaRERA.
When was POOJA NAGAR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), POOJA NAGAR was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on POOJA NAGAR?
No court cases are listed for POOJA NAGAR on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of POOJA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE LAXMI NARAYAN DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of POOJA NAGAR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Karjat
- VRINDAVAN HOMES
- SWAMI AASHRAY
- Ratnamisha Villas
- 21 ENCLAVE
- Krishna Valley Phase I
- MUDRA AVENUE
- Hill Top Residency
- Gajvakra Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.