CYRSTAL PLAZA
by MANGESH EKNATH THAKUR · Tandelwadi, RaigarhAlso near Kamothe, Nerul, Navi Mumbai
Possession: CYRSTAL PLAZA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000008712. Status: Completed. 9 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about CYRSTAL PLAZA?
How the possession date of CYRSTAL PLAZA has moved
31 December 2018
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT52000008876)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We have almost completed the construction work and are hopeful that once we receive project extension, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects. Various private and Government offices have not been working at full strength and the complete supply…”31 December 2024
Extended at the builder's request (MahaRERA application EXT52000013010)
Reason the builder gave MahaRERA:
“We had applied for the OC before the granted date of completion of this project. But there is a delay in OC from the sanctioning authority. Hence, we are not able to get registered the apartment booked/ sold to some clients in their name du…” Read the full reason
“We had applied for the OC before the granted date of completion of this project. But there is a delay in OC from the sanctioning authority. Hence, we are not able to get registered the apartment booked/ sold to some clients in their name due to expired date of completion of the project, further causing loss to the clients. So, kindly, please give the extension, so that we can avoid the loss & inconvenience caused to our clients in this project while we receive the OC as soon as possible.”
Source: CYRSTAL PLAZA’s extension records on MahaRERA (P52000008712), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CYRSTAL PLAZA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 9 complaints, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000008712
- Status
- Completed
- Builder
- MANGESH EKNATH THAKUR
- Location
- Tandelwadi, Raigarh · 410209
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2024
- Delay so far
- 72 months
- Homes
- 19
- Towers
- 1
- Complaints on MahaRERA
- 9
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of CYRSTAL PLAZA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CRYSTAL PLAZA | 100% | 5% | 0% | 15% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CYRSTAL PLAZA every month.
CYRSTAL PLAZA: buildings, flats and land, as filed on MahaRERA
- Buildings: CRYSTAL PLAZA (6 floors)
- Land: 300 sq m (about 0.1 acres) · sanctioned built-up 450 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mangesh Eknath Thakur has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 70 months); 1 still being built, 1 past the promised date (typically 39 months late); 1 lapsed. 16 complaints on MahaRERA across 3 projects.
Read Google reviews of CYRSTAL PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CYRSTAL PLAZA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CYRSTAL PLAZA
What is the possession date of CYRSTAL PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CYRSTAL PLAZA in Tandelwadi, Raigarh is 31 December 2024 — 72 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for CYRSTAL PLAZA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CYRSTAL PLAZA's builder has filed on MahaRERA, the official one, is 31 December 2024, already 72 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CYRSTAL PLAZA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We have almost completed the construction work and are hopeful that once we receive project extension, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects. Various private and Government offices have not been working at full strength and the complete supply…"; to 31 December 2024, giving the reason "We had applied for the OC before the granted date of completion of this project. But there is a delay in OC from the sanctioning authority. Hence, we are not able to get registered the apartment booked/ sold to some clients in their name due to expired date of completion of the project, further causing loss to the clients. So, kindly, please give the extension, so that we can avoid the loss & inconvenience caused to our clients in this project while we receive the OC as soon as possible.".
What is the RERA number of CYRSTAL PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CYRSTAL PLAZA in Tandelwadi, Raigarh is P52000008712.
Is CYRSTAL PLAZA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA is registered as P52000008712 and its status is "Completed".
What is the construction status of CYRSTAL PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA's status on MahaRERA is "Completed". As filed by the builder, slab work on CRYSTAL PLAZA is 5% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does CYRSTAL PLAZA have complaints on MahaRERA?
9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is CYRSTAL PLAZA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA is registered on MahaRERA as P52000008712, its MahaRERA status is "Completed", its completion date has moved 72 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CYRSTAL PLAZA's possession date changes?
The latest dates are on CYRSTAL PLAZA's MahaRERA page (P52000008712). GharKundli's Kundli Watch sends a free WhatsApp update on CYRSTAL PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CYRSTAL PLAZA have?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA has one building filed: CRYSTAL PLAZA with 6 floors.
How big is the land of CYRSTAL PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA stands on 300 sq m of land (about 0.1 acres), with 450 sq m of sanctioned built-up area.
What is the track record of CYRSTAL PLAZA's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangesh Eknath Thakur has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 70 months); 1 still being built, 1 past the promised date (typically 39 months late); 1 lapsed. 16 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CYRSTAL PLAZA?
Google Maps has reviews of CYRSTAL PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CYRSTAL PLAZA?
CYRSTAL PLAZA by MANGESH EKNATH THAKUR is in Tandelwadi, Raigarh (pincode 410209), near Kamothe, Nerul, Navi Mumbai, Maharashtra, and is registered on MahaRERA as P52000008712, per GharKundli's check of MahaRERA records.
How many homes are in CYRSTAL PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA has 19 homes in 1 tower registered on MahaRERA.
When was CYRSTAL PLAZA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CYRSTAL PLAZA was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on CYRSTAL PLAZA?
No court cases are listed for CYRSTAL PLAZA on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of CYRSTAL PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MANGESH EKNATH THAKUR, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CYRSTAL PLAZA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Panvel
- PRAKASH TOWER
- SAI SIDDHI MADHUBAN
- Sai Nilay
- Shivesh Mahavir
- Crystal Co-Operative Housing Society Limited
- Indiabulls Park 2
- Indiabulls Park 1
- Indiabulls Park 4
Other projects by MANGESH EKNATH THAKUR
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.