GharKundli

Sai Aangan

by Mangesh Eknath Thakur · Tembhode, Raigarh

Possession date of Sai Aangan: 20 August 2027, moved from 30 March 2022 (61 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000015886, and currently active. Its completion date has moved from March 2022 to August 2027: 61 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sai Aangan?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Aangan has moved

  1. 30 March 2022

    Completion date given when the project was registered

  2. 20 April 2027

    Extended at the builder's request (MahaRERA application EXT52000011777)

    Reason the builder gave MahaRERA: “The registered project is delayed due to certain issue with Covid - 19 pandemic & later due to improper & steady supply availability of building material in the area.”
  3. 20 August 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sai Aangan’s extension records on MahaRERA (P52000015886), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Aangan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the August 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000015886
Status
Registered and active
Builder
Mangesh Eknath Thakur
Location
Tembhode, Raigarh · 410206
Project type
Others
Registered on
28 Mar 2018
Completion date at registration
March 2022
Latest completion date
August 2027
Delay so far
61 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
107
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sai Aangan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sai Aangan0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Aangan every month.

Sai Aangan: buildings, flats and land, as filed on MahaRERA

  • Buildings: Sai Aangan (6 floors)
  • Land: 1,740 sq m (about 0.4 acres) · sanctioned built-up 3,681 sq m

The builder’s record and reviews

Mangesh Eknath Thakur has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 70 months); 1 still being built, 1 past the promised date (typically 39 months late); 1 lapsed. 16 complaints on MahaRERA across 3 projects.

Read Google reviews of Sai Aangan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Aangan: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Aangan

What is the possession date of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Aangan in Tembhode, Raigarh is 20 August 2027 — 61 months later than 30 March 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sai Aangan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Aangan's builder has filed on MahaRERA, the official one, is 20 August 2027, already 61 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sai Aangan extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan's builder applied to MahaRERA to extend the completion date once: to 20 April 2027, giving the reason "The registered project is delayed due to certain issue with Covid - 19 pandemic & later due to improper & steady supply availability of building material in the area.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Aangan in Tembhode, Raigarh is P52000015886.

Is Sai Aangan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan is registered as P52000015886 and its status is "Registered and active".

What is the construction status of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sai Aangan is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sai Aangan have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sai Aangan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan is registered on MahaRERA as P52000015886, its completion date has moved 61 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Aangan's possession date changes?

The latest dates are on Sai Aangan's MahaRERA page (P52000015886). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Aangan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Aangan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan has one building filed: Sai Aangan with 6 floors.

How big is the land of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan stands on 1,740 sq m of land (about 0.4 acres), with 3,681 sq m of sanctioned built-up area.

What is the track record of Sai Aangan's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangesh Eknath Thakur has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 70 months); 1 still being built, 1 past the promised date (typically 39 months late); 1 lapsed. 16 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sai Aangan?

Google Maps has reviews of Sai Aangan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Aangan?

Sai Aangan by Mangesh Eknath Thakur is in Tembhode, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000015886, per GharKundli's check of MahaRERA records.

How many homes are in Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan has 107 homes in 1 tower registered on MahaRERA.

When was Sai Aangan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan was registered on MahaRERA on 28 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Aangan?

No court cases are listed for Sai Aangan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Mangesh Eknath Thakur, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Panvel

All 2,664 projects in Panvel (410206) →

Other projects by Mangesh Eknath Thakur

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.