by MANGESH EKNATH THAKUR · Karanja Road, RaigarhAlso near Panvel, Kamothe, Kharghar

Possession date of SAI SHAKTI: 28 February 2018. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000003230. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (February 2018) has passed.

What do you want to know about SAI SHAKTI?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SAI SHAKTI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints, and how it ended
  • Construction pace against the February 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000003230
Status
Lapsed (registration period ended)
Builder
MANGESH EKNATH THAKUR
Location
Karanja Road, Raigarh · 410209
Project type
Others
Registered on
5 Aug 2017
Completion date at registration
February 2018
Homes
19
Towers
1
Complaints on MahaRERA
6
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SAI SHAKTI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI SHAKTI0%5%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI SHAKTI every month.

SAI SHAKTI: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Mangesh Eknath Thakur has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 70 months); 1 still being built, 1 past the promised date (typically 39 months late); 1 lapsed. 16 complaints on MahaRERA across 3 projects.

Read Google reviews of SAI SHAKTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI SHAKTI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI SHAKTI

What is the possession date of SAI SHAKTI?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI SHAKTI in Karanja Road, Raigarh is 28 February 2018. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAI SHAKTI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI SHAKTI's builder has filed on MahaRERA, the official one, is 28 February 2018, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAI SHAKTI?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI SHAKTI in Karanja Road, Raigarh is P52000003230.

Is SAI SHAKTI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI is registered as P52000003230 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: Suspended, in abeyance or deregistered by MahaRERA order. MahaRERA has acted on this project by an order -- suspended, in abeyance or deregistered. Read the order to see which before paying anything.

What is the construction status of SAI SHAKTI?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI SHAKTI is 5% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI SHAKTI have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI SHAKTI safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI is registered on MahaRERA as P52000003230, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 6 complaints are listed against it and it is on MahaRERA's list "Suspended, in abeyance or deregistered by MahaRERA order". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI SHAKTI's possession date changes?

The latest dates are on SAI SHAKTI's MahaRERA page (P52000003230). GharKundli's Kundli Watch sends a free WhatsApp update on SAI SHAKTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI SHAKTI have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI has one building filed: SAI SHAKTI with 6 floors.

How big is the land of SAI SHAKTI?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI stands on 300 sq m of land (about 0.1 acres), with 450 sq m of sanctioned built-up area.

What is the track record of SAI SHAKTI's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangesh Eknath Thakur has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 70 months); 1 still being built, 1 past the promised date (typically 39 months late); 1 lapsed. 16 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI SHAKTI?

Google Maps has reviews of SAI SHAKTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI SHAKTI?

SAI SHAKTI by MANGESH EKNATH THAKUR is in Karanja Road, Raigarh (pincode 410209), near Panvel, Kamothe, Kharghar, Maharashtra, and is registered on MahaRERA as P52000003230, per GharKundli's check of MahaRERA records.

How many homes are in SAI SHAKTI?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI has 19 homes in 1 tower registered on MahaRERA.

When was SAI SHAKTI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SHAKTI was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI SHAKTI?

No court cases are listed for SAI SHAKTI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI SHAKTI?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MANGESH EKNATH THAKUR, which has 2 other projects registered on MahaRERA.