Possession: NEW CUFFE PARADE - LODHA ENCHANTE is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900000367. Status: Completed. 16 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NEW CUFFE PARADE - LODHA ENCHANTE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NEW CUFFE PARADE - LODHA ENCHANTE has moved

  1. 30 June 2018

    Completion date given when the project was registered

  2. 30 June 2019

    Extended at the builder's request (MahaRERA application EXT51900000599)

    Reason the builder gave MahaRERA: “As per the letter attached”

Source: NEW CUFFE PARADE - LODHA ENCHANTE’s extension records on MahaRERA (P51900000367), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NEW CUFFE PARADE - LODHA ENCHANTE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 16 complaints, and how it ended
  • Construction pace against the June 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900000367
Status
Completed
Builder
MACROTECH DEVELOPERS LIMITED
Location
Sion, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
15 Jul 2017
Completion date at registration
June 2018
Latest completion date
June 2019
Delay so far
12 months
Homes
34
Towers
1
Complaints on MahaRERA
16
Court cases listed
0
Appeals at the tribunal
7
Title report on file
Not found
Builder's other MahaRERA projects
134

Construction progress of NEW CUFFE PARADE - LODHA ENCHANTE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LODHA ENCHANTE 41st to 43RD Floor100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NEW CUFFE PARADE - LODHA ENCHANTE every month.

NEW CUFFE PARADE - LODHA ENCHANTE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.

Read Google reviews of NEW CUFFE PARADE - LODHA ENCHANTE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NEW CUFFE PARADE - LODHA ENCHANTE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NEW CUFFE PARADE - LODHA ENCHANTE

What is the possession date of NEW CUFFE PARADE - LODHA ENCHANTE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NEW CUFFE PARADE - LODHA ENCHANTE in Sion, Mumbai is 30 June 2019 — 12 months later than 30 June 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NEW CUFFE PARADE - LODHA ENCHANTE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NEW CUFFE PARADE - LODHA ENCHANTE's builder has filed on MahaRERA, the official one, is 30 June 2019, already 12 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NEW CUFFE PARADE - LODHA ENCHANTE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE's builder applied to MahaRERA to extend the completion date once: to 30 June 2019, giving the reason "As per the letter attached".

What is the RERA number of NEW CUFFE PARADE - LODHA ENCHANTE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NEW CUFFE PARADE - LODHA ENCHANTE in Sion, Mumbai is P51900000367.

Is NEW CUFFE PARADE - LODHA ENCHANTE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE is registered as P51900000367 and its status is "Completed".

What is the construction status of NEW CUFFE PARADE - LODHA ENCHANTE?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE's status on MahaRERA is "Completed". As filed by the builder, slab work on LODHA ENCHANTE 41st to 43RD Floor is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NEW CUFFE PARADE - LODHA ENCHANTE have complaints on MahaRERA?

16 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NEW CUFFE PARADE - LODHA ENCHANTE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE is registered on MahaRERA as P51900000367, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 16 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NEW CUFFE PARADE - LODHA ENCHANTE's possession date changes?

The latest dates are on NEW CUFFE PARADE - LODHA ENCHANTE's MahaRERA page (P51900000367). GharKundli's Kundli Watch sends a free WhatsApp update on NEW CUFFE PARADE - LODHA ENCHANTE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NEW CUFFE PARADE - LODHA ENCHANTE have?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE has one building filed: LODHA ENCHANTE 41st to 43RD Floor with 3 floors.

How big is the land of NEW CUFFE PARADE - LODHA ENCHANTE?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE stands on 6,792 sq m of land (about 1.7 acres), with 3,139 sq m of sanctioned built-up area and 5,346 sq m of recreational open space.

What is the track record of NEW CUFFE PARADE - LODHA ENCHANTE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NEW CUFFE PARADE - LODHA ENCHANTE?

Google Maps has reviews of NEW CUFFE PARADE - LODHA ENCHANTE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 16 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NEW CUFFE PARADE - LODHA ENCHANTE?

NEW CUFFE PARADE - LODHA ENCHANTE by MACROTECH DEVELOPERS LIMITED (Lodha) is in Sion, Mumbai (pincode 400022), near Fci, Maharashtra, and is registered on MahaRERA as P51900000367, per GharKundli's check of MahaRERA records.

How many homes are in NEW CUFFE PARADE - LODHA ENCHANTE?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE has 34 homes in 1 tower registered on MahaRERA.

When was NEW CUFFE PARADE - LODHA ENCHANTE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NEW CUFFE PARADE - LODHA ENCHANTE was registered on MahaRERA on 15 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NEW CUFFE PARADE - LODHA ENCHANTE?

No court cases are listed for NEW CUFFE PARADE - LODHA ENCHANTE on MahaRERA, and 7 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of NEW CUFFE PARADE - LODHA ENCHANTE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MACROTECH DEVELOPERS LIMITED, the company Lodha files this project under, which has 134 other projects registered on MahaRERA.

Other projects in pincode 400022

All 98 projects in Sion (400022) →

Other projects by MACROTECH DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.