Sai Manas
by Sai Smaran infra and Developers · Pashane, Raigarh
Possession date of Sai Manas: 30 October 2026, moved from 31 December 2018 (90 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000008081, and currently active. Its completion date has moved from December 2018 to October 2026: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Sai Manas?
How the possession date of Sai Manas has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT52000000936)
Reason the builder gave MahaRERA:
“Hello Our Building Sai Manas is being built in Pashane, Taluka Karjat. We had first received the NA order for Ground plus two Floors. We had initially given a estimate date of completion to Maha Rera as December 31st, 2018. Right now the St…” Read the full reason
“Hello Our Building Sai Manas is being built in Pashane, Taluka Karjat. We had first received the NA order for Ground plus two Floors. We had initially given a estimate date of completion to Maha Rera as December 31st, 2018. Right now the Status of the Building 1. RCC constructions of Plinth, 1st slab and 2nd slab done, 3rd slab (that is the last Floor of the Ground plus two Floors) is being constructed and we are going to complete that by Jan 2nd week. 2. Brick work for the Ground Floor is completed; Electricity piping and Window tile work is going on, with simultaneous wall Plaster is goin…”31 August 2021
Extended at the builder's request (MahaRERA application EXT52000006171)
Reason the builder gave MahaRERA:
“Hello Our building SAI MANAS is being built on Pashane , Taluka karjat. We had received NA order for Ground Plus two floors, then we received second order for two more floors via order number LNA-(B)/P.N/149/2016 dated 31st August 2018. Rig…” Read the full reason
“Hello Our building SAI MANAS is being built on Pashane , Taluka karjat. We had received NA order for Ground Plus two floors, then we received second order for two more floors via order number LNA-(B)/P.N/149/2016 dated 31st August 2018. Right now the status of the building 1. Ground plus two floors RCC complete 3rd floor slab of Wing A and B complete , c is left. 2. Brick work for Ground Plus two floors complete 3. Internal Electrical Piping Ground Plus two floors complete 4. Window Tile framing for Ground Plus two floors complete 5. Bathroom water proofing for Bathroom and WC complete for…”23 May 2023
Extended at the builder's request (MahaRERA application EXT52000011922)
Reason the builder gave MahaRERA:
“Hello Dear sir/ Madam Sai Manas rera number expired on February 2022. We would like to request for the extension for rera for one more year. The following reason and status is mentioned below for your perusal. 1. We have enclosed 52% custom…” Read the full reason
“Hello Dear sir/ Madam Sai Manas rera number expired on February 2022. We would like to request for the extension for rera for one more year. The following reason and status is mentioned below for your perusal. 1. We have enclosed 52% customers signature approval for extension request. 2. Even though we have already put last slab of c wing and we are almost ready to put last slab for A wing. As proof we are putting the pictures for your reference. 3. We have also received approval from the bank that they are going to start releasing the funds and we should be able to complete the project and…”30 June 2026
Extended at the builder's request (MahaRERA application EXT52000027303)
Reason the builder gave MahaRERA:
“We are uploading Form 40 and the relevant details ...The reason for delay is as under The Project was delayed for several reasons 1. First we had order to build Ground plus two floors 2. Then in after couple of years we got order to build 2…” Read the full reason
“We are uploading Form 40 and the relevant details ...The reason for delay is as under The Project was delayed for several reasons 1. First we had order to build Ground plus two floors 2. Then in after couple of years we got order to build 2 more floors 3. Pandemic affecting the whole country and we could not do any work and the Contractors left the project 4. The customers delayed payment to the bank and in turn the bank did not pay us. 5. There was in between shortage of Sand and it was difficult to get Reti. The need for extension is now , the Land owner has several flats that he is ready…”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sai Manas’s extension records on MahaRERA (P52000008081), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sai Manas
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000008081
- Status
- Registered and active
- Builder
- Sai Smaran infra and Developers
- Location
- Pashane, Raigarh · 410201
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- October 2026
- Delay so far
- 90 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 37
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sai Manas, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sai Manas | 100% | 85% | 65% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Manas every month.
Sai Manas: buildings, flats and land, as filed on MahaRERA
- Buildings: Sai Manas (3 floors)
- Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 1,554 sq m · recreational space 200 sq m
The builder’s record and reviews
Sai Smaran Infra And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 63 months late). 7 complaints on MahaRERA across 2 projects.
Read Google reviews of Sai Manas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sai Manas: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sai Manas
What is the possession date of Sai Manas?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Manas in Pashane, Raigarh is 30 October 2026 — 90 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Sai Manas?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Manas's builder has filed on MahaRERA, the official one, is 30 October 2026, already 90 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sai Manas extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2019, giving the reason "Hello Our Building Sai Manas is being built in Pashane, Taluka Karjat. We had first received the NA order for Ground plus two Floors. We had initially given a estimate date of completion to Maha Rera as December 31st, 2018. Right now the Status of the Building 1. RCC constructions of Plinth, 1st slab and 2nd slab done, 3rd slab (that is the last Floor of the Ground plus two Floors) is being constructed and we are going to complete that by Jan 2nd week. 2. Brick work for the Ground Floor is completed; Electricity piping and Window tile work is going on, with simultaneous wall Plaster is goin…"; to 31 August 2021, giving the reason "Hello Our building SAI MANAS is being built on Pashane , Taluka karjat. We had received NA order for Ground Plus two floors, then we received second order for two more floors via order number LNA-(B)/P.N/149/2016 dated 31st August 2018. Right now the status of the building 1. Ground plus two floors RCC complete 3rd floor slab of Wing A and B complete , c is left. 2. Brick work for Ground Plus two floors complete 3. Internal Electrical Piping Ground Plus two floors complete 4. Window Tile framing for Ground Plus two floors complete 5. Bathroom water proofing for Bathroom and WC complete for…"; to 23 May 2023, giving the reason "Hello Dear sir/ Madam Sai Manas rera number expired on February 2022. We would like to request for the extension for rera for one more year. The following reason and status is mentioned below for your perusal. 1. We have enclosed 52% customers signature approval for extension request. 2. Even though we have already put last slab of c wing and we are almost ready to put last slab for A wing. As proof we are putting the pictures for your reference. 3. We have also received approval from the bank that they are going to start releasing the funds and we should be able to complete the project and…"; to 30 June 2026, giving the reason "We are uploading Form 40 and the relevant details ...The reason for delay is as under The Project was delayed for several reasons 1. First we had order to build Ground plus two floors 2. Then in after couple of years we got order to build 2 more floors 3. Pandemic affecting the whole country and we could not do any work and the Contractors left the project 4. The customers delayed payment to the bank and in turn the bank did not pay us. 5. There was in between shortage of Sand and it was difficult to get Reti. The need for extension is now , the Land owner has several flats that he is ready…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sai Manas?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Manas in Pashane, Raigarh is P52000008081.
Is Sai Manas registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas is registered as P52000008081 and its status is "Registered and active".
What is the construction status of Sai Manas?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sai Manas is 85% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does Sai Manas have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sai Manas safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas is registered on MahaRERA as P52000008081, its completion date has moved 90 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sai Manas's possession date changes?
The latest dates are on Sai Manas's MahaRERA page (P52000008081). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Manas every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sai Manas have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas has one building filed: Sai Manas with 3 floors.
How big is the land of Sai Manas?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas stands on 2,000 sq m of land (about 0.5 acres), with 1,554 sq m of sanctioned built-up area and 200 sq m of recreational open space.
What is the track record of Sai Manas's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Smaran Infra And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 63 months late). 7 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sai Manas?
Google Maps has reviews of Sai Manas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sai Manas?
Sai Manas by Sai Smaran infra and Developers is in Pashane, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000008081, per GharKundli's check of MahaRERA records.
How many homes are in Sai Manas?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas has 37 homes in 1 tower registered on MahaRERA.
When was Sai Manas registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Manas was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Sai Manas?
No court cases are listed for Sai Manas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sai Manas?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sai Smaran infra and Developers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sai Manas
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Raigad →
Other projects in Karjat
- DEEPJYOTI CITY
- HIMALAYA GARDENS
- HIMALAYA GARDENS
- SWAMI AASHRAY
- Ratnamisha Villas
- 21 ENCLAVE
- Krishna Valley Phase I
- MUDRA AVENUE
Other projects by Sai Smaran infra and Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.