Possession date of SATYANATH: 30 October 2027, moved from 31 January 2023 (53 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000026447, and currently active. Its completion date has moved from January 2023 to October 2027: 53 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SATYANATH?
GharKundli’s full report on SATYANATH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000026447
- Status
- Registered and active
- Builder
- Sai Smaran infra and Developers
- Location
- Dahiwali Taref Need, Raigarh · 410201
- Project type
- Others
- Registered on
- 22 Sep 2020
- Completion date at registration
- January 2023
- Latest completion date
- October 2027
- Delay so far
- 53 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 4
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SATYANATH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SATYANATH | 100% | 100% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SATYANATH: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SATYANATH every month.
SATYANATH: buildings, flats and land, as filed on MahaRERA
- Buildings: SATYANATH (6 floors, 4 units)
- Land: 464 sq m (about 0.1 acres) · sanctioned built-up 603 sq m
The builder’s record and reviews
Sai Smaran Infra And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 63 months late). 7 complaints on MahaRERA across 2 projects.
Read Google reviews of SATYANATH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SATYANATH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SATYANATH
What is the possession date of SATYANATH?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SATYANATH in Dahiwali Taref Need, Raigarh is 30 October 2027 — 53 months later than 31 January 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SATYANATH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SATYANATH's builder has filed on MahaRERA, the official one, is 30 October 2027, already 53 months later than the 31 January 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SATYANATH?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SATYANATH in Dahiwali Taref Need, Raigarh is P52000026447.
Is SATYANATH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH is registered as P52000026447 and its status is "Registered and active".
What is the construction status of SATYANATH?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SATYANATH is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does SATYANATH have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SATYANATH safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH is registered on MahaRERA as P52000026447, its completion date has moved 53 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SATYANATH's possession date changes?
The latest dates are on SATYANATH's MahaRERA page (P52000026447). GharKundli's Kundli Watch sends a free WhatsApp update on SATYANATH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SATYANATH have?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH has one building filed: SATYANATH with 6 floors and 4 units.
How big is the land of SATYANATH?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH stands on 464 sq m of land (about 0.1 acres), with 603 sq m of sanctioned built-up area.
What is the track record of SATYANATH's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Smaran Infra And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 63 months late). 7 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SATYANATH?
Google Maps has reviews of SATYANATH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SATYANATH?
SATYANATH by Sai Smaran infra and Developers is in Dahiwali Taref Need, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000026447, per GharKundli's check of MahaRERA records.
How many homes are in SATYANATH?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH has 4 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was SATYANATH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SATYANATH was registered on MahaRERA on 22 September 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on SATYANATH?
No court cases are listed for SATYANATH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SATYANATH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sai Smaran infra and Developers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SATYANATH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 410201
- HOLIDAY MAIYAAN KARJAT
- RIVA RYTHM -I, J,K,L WING
- Krishna Valley Phase I
- Gajvakra Heights
- 21 ENCLAVE
- MUDRA AVENUE
- Hill Top Residency
- Ratnamisha Villas
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.