KOLAD HILLS

by SAIFORTUNE BUILDERS AND DEVELOPERS PRIVATE LIMITED · Kolad, Raigarh

Possession date of KOLAD HILLS: 31 December 2025, moved from 30 December 2021 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000010624. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about KOLAD HILLS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KOLAD HILLS has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT52000017942)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of % allottees for purpose of extension of RERA registration period of the said project.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000025363)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 90% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. we…”

Source: KOLAD HILLS’s extension records on MahaRERA (P52000010624), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KOLAD HILLS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000010624
Status
Lapsed (registration period ended)
Builder
SAIFORTUNE BUILDERS AND DEVELOPERS PRIVATE LIMITED
Location
Kolad, Raigarh · 402304
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2025
Delay so far
48 months
Homes
98
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of KOLAD HILLS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C - WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KOLAD HILLS every month.

KOLAD HILLS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KOLAD HILLS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KOLAD HILLS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KOLAD HILLS

What is the possession date of KOLAD HILLS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KOLAD HILLS in Kolad, Raigarh is 31 December 2025 — 48 months later than 30 December 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KOLAD HILLS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KOLAD HILLS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 48 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KOLAD HILLS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS's builder applied to MahaRERA to extend the completion date 2 times: to 31 August 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of % allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 90% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. we…".

What is the RERA number of KOLAD HILLS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KOLAD HILLS in Kolad, Raigarh is P52000010624.

Is KOLAD HILLS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS is registered as P52000010624 and its status is "Lapsed (registration period ended)".

What is the construction status of KOLAD HILLS?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on C - WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does KOLAD HILLS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is KOLAD HILLS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS is registered on MahaRERA as P52000010624, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KOLAD HILLS's possession date changes?

The latest dates are on KOLAD HILLS's MahaRERA page (P52000010624). GharKundli's Kundli Watch sends a free WhatsApp update on KOLAD HILLS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KOLAD HILLS have?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS has one building filed: C - WING with 10 floors.

How big is the land of KOLAD HILLS?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS stands on 7,890 sq m of land (about 1.9 acres), with 8,470 sq m of sanctioned built-up area and 868 sq m of recreational open space.

Where can I read reviews of KOLAD HILLS?

Google Maps has reviews of KOLAD HILLS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KOLAD HILLS?

KOLAD HILLS by SAIFORTUNE BUILDERS AND DEVELOPERS PRIVATE LIMITED is in Kolad, Raigarh (pincode 402304), Maharashtra, and is registered on MahaRERA as P52000010624, per GharKundli's check of MahaRERA records.

How many homes are in KOLAD HILLS?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS has 98 homes in 1 tower registered on MahaRERA.

When was KOLAD HILLS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLAD HILLS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KOLAD HILLS?

No court cases are listed for KOLAD HILLS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KOLAD HILLS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAIFORTUNE BUILDERS AND DEVELOPERS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

Other projects in Roha

All 8 projects in Kolad (402304) →

Other projects by SAIFORTUNE BUILDERS AND DEVELOPERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.