MALUSARE RESIDENCY

by SANDEEP ENTERPRISES · Varasgao, Raigarh

Possession: MALUSARE RESIDENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000010748. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MALUSARE RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MALUSARE RESIDENCY has moved

  1. 9 April 2020

    Completion date given when the project was registered

  2. 9 April 2021

    Extended at the builder's request (MahaRERA application EXT52000005604)

    Reason the builder gave MahaRERA: “sand material not available”
  3. 9 April 2023

    Extended at the builder's request (MahaRERA application EXT52000011068)

    Reason the builder gave MahaRERA:
    “The required extension under Section 6, namely the forced major Cyclone Nisarga, disaster caused by nature affected the regular development of the project. 1. The project is in Raigad district where the first corona's wave lockdown lasted m…” Read the full reason“The required extension under Section 6, namely the forced major Cyclone Nisarga, disaster caused by nature affected the regular development of the project. 1. The project is in Raigad district where the first corona's wave lockdown lasted more months than the rest of the district. 2. Due to lack of labour, the project was closed for several months even after the first & second corona's wave lockdown ended. 3. Where there is a project (Tal-Roha, Dist.-Raigad), there was a lot of damage to the project due to Cyclone Nisarga. Due to Cyclone Nisarga, MSEDCL's electrical power supply did not las…”
  4. 9 April 2024

    Extended at the builder's request (MahaRERA application EXT52000017164)

    Reason the builder gave MahaRERA: “The required extension under Section 6, namely the forced major i.e. lack of response to the sale of flats & As the cost of construction was increasing day by day.”
  5. 9 April 2025

    Extended at the builder's request (MahaRERA application EXT52000019107)

    Reason the builder gave MahaRERA:
    “• The previous extension certificate registration was valid till 09/04/2023, so we had applied for the extension certificate in the month of March 2023 itself but due to the Technical Problem of Maharera website for extension, we followed u…” Read the full reason“• The previous extension certificate registration was valid till 09/04/2023, so we had applied for the extension certificate in the month of March 2023 itself but due to the Technical Problem of Maharera website for extension, we followed up many times by emails and personally meeting at Maharera office from 10-03-2023. After resolve the issue and completing the required documents, we got the extension certificate dated 6/10/2023 from Maharera. But due to lack of RERA certificate as per rules of Maharera, we stopped sales during this period & Due to lack of sales i.e. lack of capital, the p…”
  6. 9 October 2025

    Extended at the builder's request (MahaRERA application EXT52000027867)

    Reason the builder gave MahaRERA:
    “• Despite the lack of response to the sale of flats, the project work has been completed despite overcoming many difficulties. For this, an "Architect's certificate of completion of the project work" is attached and the process for the OC o…” Read the full reason“• Despite the lack of response to the sale of flats, the project work has been completed despite overcoming many difficulties. For this, an "Architect's certificate of completion of the project work" is attached and the process for the OC of the project has been progress. But the RERA certificate date is valid till 9/04/2025. Since the duration of RERA certificate and the time taken to obtain OC is short and since OC is a government process, it is not possible to predict how long it will take to obtain it, therefore, for the safety of the project, we need to extend the date of RERA certific…”

Source: MALUSARE RESIDENCY’s extension records on MahaRERA (P52000010748), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MALUSARE RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000010748
Status
Completed
Builder
SANDEEP ENTERPRISES
Location
Varasgao, Raigarh · 402304
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
April 2020
Latest completion date
October 2025
Delay so far
66 months
Homes
32
Sold or booked
19%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MALUSARE RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Malusare Residency100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Malusare Residency: covers full

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MALUSARE RESIDENCY every month.

MALUSARE RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: Malusare Residency (6 floors, 32 units)
  • Land: 1,213 sq m (about 0.3 acres) · sanctioned built-up 1,213 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MALUSARE RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MALUSARE RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MALUSARE RESIDENCY

What is the possession date of MALUSARE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MALUSARE RESIDENCY in Varasgao, Raigarh is 9 October 2025 — 66 months later than 9 April 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MALUSARE RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MALUSARE RESIDENCY's builder has filed on MahaRERA, the official one, is 9 October 2025, already 66 months later than the 9 April 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MALUSARE RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY's builder applied to MahaRERA to extend the completion date 5 times: to 9 April 2021, giving the reason "sand material not available"; to 9 April 2023, giving the reason "The required extension under Section 6, namely the forced major Cyclone Nisarga, disaster caused by nature affected the regular development of the project. 1. The project is in Raigad district where the first corona's wave lockdown lasted more months than the rest of the district. 2. Due to lack of labour, the project was closed for several months even after the first & second corona's wave lockdown ended. 3. Where there is a project (Tal-Roha, Dist.-Raigad), there was a lot of damage to the project due to Cyclone Nisarga. Due to Cyclone Nisarga, MSEDCL's electrical power supply did not las…"; to 9 April 2024, giving the reason "The required extension under Section 6, namely the forced major i.e. lack of response to the sale of flats & As the cost of construction was increasing day by day."; to 9 April 2025, giving the reason "• The previous extension certificate registration was valid till 09/04/2023, so we had applied for the extension certificate in the month of March 2023 itself but due to the Technical Problem of Maharera website for extension, we followed up many times by emails and personally meeting at Maharera office from 10-03-2023. After resolve the issue and completing the required documents, we got the extension certificate dated 6/10/2023 from Maharera. But due to lack of RERA certificate as per rules of Maharera, we stopped sales during this period & Due to lack of sales i.e. lack of capital, the p…"; to 9 October 2025, giving the reason "• Despite the lack of response to the sale of flats, the project work has been completed despite overcoming many difficulties. For this, an "Architect's certificate of completion of the project work" is attached and the process for the OC of the project has been progress. But the RERA certificate date is valid till 9/04/2025. Since the duration of RERA certificate and the time taken to obtain OC is short and since OC is a government process, it is not possible to predict how long it will take to obtain it, therefore, for the safety of the project, we need to extend the date of RERA certific…".

What is the RERA number of MALUSARE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MALUSARE RESIDENCY in Varasgao, Raigarh is P52000010748.

Is MALUSARE RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY is registered as P52000010748 and its status is "Completed".

What is the construction status of MALUSARE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on Malusare Residency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MALUSARE RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MALUSARE RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY is registered on MahaRERA as P52000010748, its MahaRERA status is "Completed", its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MALUSARE RESIDENCY's possession date changes?

The latest dates are on MALUSARE RESIDENCY's MahaRERA page (P52000010748). GharKundli's Kundli Watch sends a free WhatsApp update on MALUSARE RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MALUSARE RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY has one building filed: Malusare Residency with 6 floors and 32 units.

How big is the land of MALUSARE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY stands on 1,213 sq m of land (about 0.3 acres), with 1,213 sq m of sanctioned built-up area.

Where can I read reviews of MALUSARE RESIDENCY?

Google Maps has reviews of MALUSARE RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MALUSARE RESIDENCY?

MALUSARE RESIDENCY by SANDEEP ENTERPRISES is in Varasgao, Raigarh (pincode 402304), Maharashtra, and is registered on MahaRERA as P52000010748, per GharKundli's check of MahaRERA records.

How many homes are in MALUSARE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY has 32 homes in 1 tower registered on MahaRERA, and 19% of them are sold or booked.

When was MALUSARE RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MALUSARE RESIDENCY was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MALUSARE RESIDENCY?

No court cases are listed for MALUSARE RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MALUSARE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANDEEP ENTERPRISES.