RIVERSIDE GREENS
by GROW PLUS INFRA · Dadar West, Raigarh
Possession: RIVERSIDE GREENS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000005275. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RIVERSIDE GREENS?
How the possession date of RIVERSIDE GREENS has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT52000001464)
Reason the builder gave MahaRERA: “Development of the project is completed and in process of Society Formation, Conveyance of land to Society & to obtain Sanad .”
Source: RIVERSIDE GREENS’s extension records on MahaRERA (P52000005275), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RIVERSIDE GREENS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000005275
- Status
- Completed
- Builder
- GROW PLUS INFRA
- Location
- Dadar West, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2019
- Delay so far
- 12 months
- Homes
- 172
- Towers
- 10
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of RIVERSIDE GREENS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 1A | 100% | 100% | 100% | 100% |
| 1B | 100% | 100% | 100% | 100% |
| 1C | 100% | 100% | 100% | 100% |
| 1D | 100% | 100% | 100% | 100% |
| 4A | 100% | 100% | 100% | 100% |
| 4B | 100% | 100% | 100% | 100% |
| 5A | 100% | 100% | 100% | 100% |
| 5B | 100% | 100% | 100% | 100% |
| 5C | 0% | 100% | 100% | 100% |
| 5D | 0% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RIVERSIDE GREENS every month.
RIVERSIDE GREENS: buildings, flats and land, as filed on MahaRERA
- Buildings: 1A (5 floors) · 1B (5 floors) · 1C (5 floors) · 1D (5 floors) · 4A (5 floors) · 4B (5 floors) · 5A (5 floors) · 5B (5 floors) · and 2 more
- Land: 7,552 sq m (about 1.9 acres) · sanctioned built-up 7,775 sq m · recreational space 789 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RIVERSIDE GREENS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RIVERSIDE GREENS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RIVERSIDE GREENS
What is the possession date of RIVERSIDE GREENS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RIVERSIDE GREENS in Dadar West, Raigarh is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RIVERSIDE GREENS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RIVERSIDE GREENS's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RIVERSIDE GREENS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "Development of the project is completed and in process of Society Formation, Conveyance of land to Society & to obtain Sanad .".
What is the RERA number of RIVERSIDE GREENS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RIVERSIDE GREENS in Dadar West, Raigarh is P52000005275.
Is RIVERSIDE GREENS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS is registered as P52000005275 and its status is "Completed".
What is the construction status of RIVERSIDE GREENS?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 10 towers. GharKundli's full report compares construction progress with the deadline.
Does RIVERSIDE GREENS have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RIVERSIDE GREENS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS is registered on MahaRERA as P52000005275, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RIVERSIDE GREENS's possession date changes?
The latest dates are on RIVERSIDE GREENS's MahaRERA page (P52000005275). GharKundli's Kundli Watch sends a free WhatsApp update on RIVERSIDE GREENS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RIVERSIDE GREENS have?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS has 10 buildings filed: 1A with 5 floors; 1B with 5 floors; 1C with 5 floors; 1D with 5 floors; 4A with 5 floors; 4B with 5 floors; and 4 more.
How big is the land of RIVERSIDE GREENS?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS stands on 7,552 sq m of land (about 1.9 acres), with 7,775 sq m of sanctioned built-up area and 789 sq m of recreational open space.
Where can I read reviews of RIVERSIDE GREENS?
Google Maps has reviews of RIVERSIDE GREENS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RIVERSIDE GREENS?
RIVERSIDE GREENS by GROW PLUS INFRA is in Dadar West, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000005275, per GharKundli's check of MahaRERA records.
How many homes are in RIVERSIDE GREENS?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS has 172 homes in 10 towers registered on MahaRERA.
When was RIVERSIDE GREENS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RIVERSIDE GREENS was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RIVERSIDE GREENS?
No court cases are listed for RIVERSIDE GREENS on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RIVERSIDE GREENS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GROW PLUS INFRA.
Check it yourself on MahaRERA
- How to check the possession date of RIVERSIDE GREENS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dadar West
- ARYAVRAT PROJECT
- YASH TRINITY
- Sigma Garnet
- AHILYA
- SAI ARADHYA
- BUILDARCH SAKURA
- VASANT PRABHA
- SHREE SAI ARTI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.