HILL VIEW
by HDG ENTERPRISES PVT LTD · Neral, Raigarh
Possession date of HILL VIEW: 30 April 2028, moved from 30 December 2019 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000008581, and currently active. Its completion date has moved from December 2019 to April 2028: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 11 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about HILL VIEW?
How the possession date of HILL VIEW has moved
30 December 2019
Completion date given when the project was registered
29 December 2020
Extended at the builder's request (MahaRERA application EXT52000002617)
Reason the builder gave MahaRERA: “we are unable to complete construction work owing to lack of labour, Shortage of Raw Material and, GST implementation followed by demonetization which are beyond the control of the promoter.”
31 December 2022
Extended at the builder's request (MahaRERA application EXT52000009788)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We are on the verge of completing the construction work and are hopeful that once we receive project extension we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects.”30 June 2025
Extended at the builder's request (MahaRERA application EXT52000016742)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.16% allottees for purpose of extension of RERA registration period of the said project”30 December 2027
Extended at the builder's request (MahaRERA application EXT52000028370)
Reason the builder gave MahaRERA:
“We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highe…” Read the full reason
“We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality.”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HILL VIEW’s extension records on MahaRERA (P52000008581), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HILL VIEW
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 11 complaints, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000008581
- Status
- Registered and active
- Builder
- HDG ENTERPRISES PVT LTD
- Location
- Neral, Raigarh · 410101
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2028
- Delay so far
- 96 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 154
- Towers
- 4
- Complaints on MahaRERA
- 11
- Court cases listed
- 0
- Appeals at the tribunal
- 11
- Title report on file
- Not found
Construction progress of HILL VIEW, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building 1- Wing 1 and Wing 2 | 100% | 100% | 100% | 70% |
| Building 2- Wing 1, 2 and 3 | 100% | 100% | 90% | 90% |
| NA | 0% | 0% | 0% | 0% |
| NA | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HILL VIEW every month.
HILL VIEW: buildings, flats and land, as filed on MahaRERA
- Buildings: Building 1- Wing 1 and Wing 2 (5 floors) · Building 2- Wing 1, 2 and 3 (5 floors)
- Land: 5,700 sq m (about 1.4 acres) · sanctioned built-up 4,718 sq m · recreational space 600 sq m
- Boundaries filed include: Neral Karjat state Highway
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HILL VIEW →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HILL VIEW: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HILL VIEW
What is the possession date of HILL VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HILL VIEW in Neral, Raigarh is 30 April 2028 — 96 months later than 30 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HILL VIEW?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HILL VIEW's builder has filed on MahaRERA, the official one, is 30 April 2028, already 96 months later than the 30 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HILL VIEW extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2020, giving the reason "we are unable to complete construction work owing to lack of labour, Shortage of Raw Material and, GST implementation followed by demonetization which are beyond the control of the promoter."; to 31 December 2022, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We are on the verge of completing the construction work and are hopeful that once we receive project extension we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects."; to 30 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.16% allottees for purpose of extension of RERA registration period of the said project"; to 30 December 2027, giving the reason "We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HILL VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HILL VIEW in Neral, Raigarh is P52000008581.
Is HILL VIEW registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW is registered as P52000008581 and its status is "Registered and active".
What is the construction status of HILL VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does HILL VIEW have complaints on MahaRERA?
11 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HILL VIEW safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW is registered on MahaRERA as P52000008581, its completion date has moved 96 months since registration and 11 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HILL VIEW's possession date changes?
The latest dates are on HILL VIEW's MahaRERA page (P52000008581). GharKundli's Kundli Watch sends a free WhatsApp update on HILL VIEW every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HILL VIEW have?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW has 2 buildings filed: Building 1- Wing 1 and Wing 2 with 5 floors; Building 2- Wing 1, 2 and 3 with 5 floors.
How big is the land of HILL VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW stands on 5,700 sq m of land (about 1.4 acres), with 4,718 sq m of sanctioned built-up area and 600 sq m of recreational open space.
Where can I read reviews of HILL VIEW?
Google Maps has reviews of HILL VIEW written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 11 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HILL VIEW?
HILL VIEW by HDG ENTERPRISES PVT LTD is in Neral, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000008581, per GharKundli's check of MahaRERA records. Its boundaries filed there include Neral Karjat state Highway.
How many homes are in HILL VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW has 154 homes in 4 towers registered on MahaRERA.
When was HILL VIEW registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HILL VIEW was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HILL VIEW?
No court cases are listed for HILL VIEW on MahaRERA, and 11 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of HILL VIEW?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HDG ENTERPRISES PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of HILL VIEW
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in pincode 410101
- A Z LANDMARK
- VANSH HEIGHTS
- SWAMI AASHRAY
- MIRA RESIDENCY
- SIGNATURE PHASE 1
- ARYA RESIDENCY P1
- ARENA ONE
- MECCA AVENUE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.